Glen Mor 2 Student Apartments
GLEN MOR 2 STUDENT APARTMENTS
Community Contact Information
CONSTRUCTION-RELATED CONCERNS
| During Business Hours (Monday - Friday, 8 a.m. - 5 p.m.) | |||
|---|---|---|---|
| David Forman, AIA | Capital Programs: Architects & Engineers | Sr. Project Manager | 951-827-1393 |
| 24 Hours - 7 Days (CONSTRUCTION-RELATED CONCERNS ONLY) | |||
| Contractor Representative | Balfour Beatty Inc. | 951-842-0537 | |
For general information, call Balfour Beatty Construction, (951) 827-4091 during normal working hours Monday-Friday, 7:00 a.m. - 4:00 p.m.
GLEN MOR 2 STUDENT APARTMENTS PROJECT DETAILS
The ten acre project is located at the east end of the campus between Glen Mor 1 Student Apartments and W. Big Springs Road. Project details:
- 800 Student Apartment Beds in five, five-story buildings
- A Resident Services Office building
- Resident Community Services – computer lab, meeting rooms, fitness room, swimming pool and outdoor recreation spaces
- A Food Emporium
- A Conference Center
- A three-level, 596 stall Parking Structure for residents
The $145M project is funded solely through housing revenue bonds and is scheduled to open in Fall 2013.

Schedule
| Description | Start | Complete | Remarks | |
| 1 | Electrical Underground | 01/30/2012 | 04/27/2012 | |
| 2 | Wet Utilities Underground | 01/16/2012 | 04/27/2012 | |
| 3 | Testing Sewer & Water Mains | 04/16/2012 | 05/11/2012 |