Breadcrumb

School of Business New Building

The new School of Business building complex will be a flagship facility, serving as the permanent home for the School. The building will complement the School of Business’ existing space program and fully address enrollment-driven needs in pursuit of their aspiration to become the premier center of management research and education in the Inland Empire.


Project Scope:

The proposed building will provide about 38,500 ASF within approximately to 63,400 GSF, along with exterior circulation and gathering areas. The program includes the following spaces:

  • Classrooms and Educational Spaces
  • Student Support Spaces
  • Academic Offices and Support Spaces
  • Administrative Offices and Support Spaces
  • Shared Building Resources (Lobby, Multipurpose room(s) etc)

School of Business Project Updates

  • 950592 UCR SBB - Construction Alert #71

    Current Week

    Construction Activities

     

    Location

    Activity

    Equipment Used

    Anticipated Disturbance

    SBB (Lot 8) 

    Install PV Panel System - North of E Line

    NA

    NA

    SBB (Lot 8) 

    Cement Board – EXT-L1

    NA

    NA

    SBB (Lot 8) 

    Secondary Air Barrier– EXT-L1

    NA

    NA

    SBB (Lot 8)

    Drainage Layer– EXT-NE

    NA

    NA

    SBB (Lot 8)

    Cement Board– EXT-NE

    NA

    NA

    SBB (Lot 8) 

    Secondary Air Barrier– EXT-SW

    NA

    NA

    SBB (Lot 8)

    Erect Stairs– EXT-SW

    NA

    NA

    SBB (Lot 8)

    Install Communications Racks/Equipment -ELEC-L1

    NA

    NA

    SBB (Lot 8)

    Controls Hook-up Equipment (Incl. Refrigerant Alarm) – MECH-L1

    NA

    NA

    SBB (Lot 8)

    Plumbing Piping, Hook-up & Insulation– MECH-L1

    NA

    NA

    SBB (Lot 8)

    Frame Remaining Walls, Soffits & Hard lids – INT-L1

    NA

    NA

    SBB (Lot 8)

    Install O/H Supply & Return Ductwork Branch & Seismic – INT-AUD

    NA

    NA

    SBB (Lot 8)

    Pull Electrical – INT-AUD

    NA

    NA

    SBB (Lot 8) 

    Pull Low Voltage Cable – INT-AUD

    NA

    NA

    SBB (Lot 8)

    Install Conduit – ELEC-AUD

    NA

    NA

    SBB (Lot 8)

    Install Conduit – ELEC-L2

    NA

    NA

    SBB (Lot 8)

    Hang 2nd Side Drywall & Inspect - INT-L2

    NA

    NA

    SBB (Lot 8)

    Pull Low Voltage Cable- INT-L2

    NA

    NA

    SBB (Lot 8)

    Install Backing – RR-L2

    NA

    NA

    SBB (Lot 8)

    Install Insulation and Inspect – RR-L2

    NA

    NA

    SBB (Lot 8)

    Hang Drywall & Inspect– RR-L2

    NA

    NA

    SBB (Lot 8)

    Install Conduit – ELEC-L3

    NA

    NA

    SBB (Lot 8)

    Install Hardlid Electrical – INT-L3

    NA

    NA

    SBB (Lot 8)

    Install In-Wall Plumbing – INT-L3

    NA

    NA

    SBB (Lot 8)

    Install In-Wall & Hard lid Electrical– RR-L3

    NA

    NA

    SBB (Lot 8)

    Install Backing– RR-L3

    NA

    NA

    SBB (Lot 8)

    Install O/H Mechanical Equipment & Ductwork Mains & Seismic – INT-L4

    NA

    NA

    SBB (Lot 8)

    Install Conduit – ELEC-L4

    NA

    NA

    SBB (Lot 8)

    Install In-Wall & Branch Electrical – INT-L4

    NA

    NA

    SBB (Lot 8)

    Install In-Wall Low Voltage – INT-L4

    NA

    NA

    SBB (Lot 8)

    Install Hardlid Electrical – INT-L4

    NA

    NA

    SBB (Lot 8)

    Machine Room Wiring, Start-up, Running Platform - ELEV

    NA

    NA

    SBB (Lot 8)

    F/R/P Site Walls – SITE-AP

    NA

    NA

    SBB (Lot 8)

    Install Site Lighting Underground – SITE-AP

    NA

    NA

     

    Week of March 25, 2024

    Construction Activities 

     

    Location

    Activity

    Equipment Used

    Anticipated Disturbance

    SBB (Lot 8) 

    Curtain Wall – Frames – EXT-L1

    NA

    NA

    SBB (Lot 8) 

    Set Thin Brick – EXT-L1

    NA

    NA

    SBB (Lot 8) 

    Cement Board – EXT-NE

    NA

    NA

    SBB (Lot 8)

    Secondary Air Barrier – EXT-NE

    NA

    NA

    SBB (Lot 8)

    Set Thin Brick – EXT-SW

    NA

    NA

    SBB (Lot 8) 

    Punched Openings – Frames – EXT-SW

    NA

    NA

    SBB (Lot 8)

    Curtain Wall – Frames – EXT-SW

    NA

    NA

    SBB (Lot 8)

    Install In-Wall & Branch Electrical - INT-L1

    NA

    NA

    SBB (Lot 8)

    Install In-Wall Low Voltage - INT-L1

    NA

    NA

    SBB (Lot 8)

    Hang Drywall – INT-AUD

    NA

    NA

    SBB (Lot 8)

    Pressure Test Ductwork – INT-AUD

    NA

    NA

    SBB (Lot 8)

    Install Ductwork Insulation – INT-AUD

    NA

    NA

    SBB (Lot 8)

    Install Feeder Cable / Home Runs – ELEC-AUD

    NA

    NA

    SBB (Lot 8) 

    Install Switchgear MSB – ELEC-L1

    NA

    NA

    SBB (Lot 8)

    Install Feeder Cable / Home Runs – ELEC-L2

    NA

    NA

    SBB (Lot 8)

    Tape Walls Soffits & Hard lids – RR-L2

    NA

    NA

    SBB (Lot 8)

    Install Feeder Cable / Home Runs – ELEC-L3

    NA

    NA

    SBB (Lot 8)

    Hang 1st Side Drywall – INT-L3

    NA

    NA

    SBB (Lot 8)

    Install Cable Tray– INT-L3

    NA

    NA

    SBB (Lot 8) 

    Pull Electrical– INT-L3

    NA

    NA

    SBB (Lot 8)

    Install Insulation & Inspect– INT-L3

    NA

    NA

    SBB (Lot 8)

    Fire Tape– INT-L3

    NA

    NA

    SBB (Lot 8)

    Install Insulation & Inspect – RR-L3

    NA

    NA

    SBB (Lot 8)

    Hang Drywall & Inspect – RR-L3

    NA

    NA

    SBB (Lot 8)

    Install O/H Mechanical Equipment & Ductwork Mains & Seismic – INT-L4

    NA

    NA

    SBB (Lot 8) 

    Install O/H Supply & Return Ductwork Branch & Seismic – INT-L4

    NA

    NA

    SBB (Lot 8)

    Pull Electrical – INT-L4

    NA

    NA

    SBB (Lot 8)

    Hang Top Down Drywall – RR-L4

    NA

    NA

    SBB (Lot 8)

    Fire Tape – RR-L4

    NA

    NA

    SBB (Lot 8)

    Fire Caulk Head of Wall – RR-L4

    NA

    NA

    SBB (Lot 8)

    Complete Install Guide Rails - ELEV

    NA

    NA

     

    Week of April 1, 2024

    Construction Activities 

     

    Location

    Activity

    Equipment Used

    Anticipated Disturbance

    SBB (Lot 8) 

    Install Roofing System - South of E Line

    NA

    NA

    SBB (Lot 8) 

    Curtain Wall – Frames – EXT-L1

    NA

    NA

    SBB (Lot 8) 

    Set Thin Brick – EXT-L1

    NA

    NA

    SBB (Lot 8)

    Punched Openings – Frames – EXT-NE

    NA

    NA

    SBB (Lot 8)

    Curtain Wall – Frames – EXT-NE

    NA

    NA

    SBB (Lot 8) 

    Set Thin Brick – EXT-NE

    NA

    NA

    SBB (Lot 8)

    Set Thin Brick – EXT-SW

    NA

    NA

    SBB (Lot 8)

    Punched Openings – Frames – EXT-SW

    NA

    NA

    SBB (Lot 8)

    Curtain Wall – Frames – EXT-SW

    NA

    NA

    SBB (Lot 8)

    F/R/P Stair Treads/Landings – EXT-SW

    NA

    NA

    SBB (Lot 8)

    Install Feeder Cable / Home Runs – ELEC-L1

    NA

    NA

    SBB (Lot 8)

    Set Distribution Board HDP-1A - MECH-L1

    NA

    NA

    SBB (Lot 8)

    Install Feeder Cable from MSB - MECH-L1

    NA

    NA

    SBB (Lot 8) 

    Install In-Wall & Branch Electrical – INT-L1

    NA

    NA

    SBB (Lot 8)

    Install In-Wall Low Voltage – INT-L1

    NA

    NA

    SBB (Lot 8)

    Install Hardlid Electrical – INT-L1

    NA

    NA

    SBB (Lot 8)

    Install In-Wall Plumbing – INT-L1

    NA

    NA

    SBB (Lot 8)

    Install Cable Tray – INT-L1

    NA

    NA

    SBB (Lot 8)

    Frame Ceiling – RR-L1

    NA

    NA

    SBB (Lot 8)

    Fire Tape - INT-AUD

    NA

    NA

    SBB (Lot 8)

    Hang 2nd Side Drywall & Inspect - INT-AUD

    NA

    NA

    SBB (Lot 8)

    Install Ductwork Insulation – INT-AUD

    NA

    NA

    SBB (Lot 8)

    Install Conduit to Switchgear – ELEC-L1

    NA

    NA

    SBB (Lot 8)

    Tape Walls Soffits & Hard lids – INT-L2

    NA

    NA

    SBB (Lot 8)

    Hang 1st Side Drywall – INT-L3

    NA

    NA

    SBB (Lot 8)

    Pull Low Voltage Cable – INT-L3

    NA

    NA

    SBB (Lot 8)

    Pull Electrical – INT-L3

    NA

    NA

    SBB (Lot 8)

    Install Insulation & Inspect – INT-L3

    NA

    NA

    SBB (Lot 8)

    Install O/H Mechanical Equipment & Ductwork Mains & Seismic – INT-L4

    NA

    NA

    SBB (Lot 8)

    Install O/H Supply & Return Ductwork Branch & Seismic – INT-L4

    NA

    NA

    SBB (Lot 8)

    Pull Electrical – INT-L4

    NA

    NA

    SBB (Lot 8)

    Fire Tape – RR-L4

    NA

    NA

    SBB (Lot 8)

    Fire Caulk Head of Wall – RR-L4

    NA

    NA

    SBB (Lot 8)

    Frame Ceiling – RR-L4

    NA

    NA

    SBB (Lot 8)

    Install Entrances and Doors - ELEV

    NA

    NA

    SBB (Lot 8)

    Frame Elevator Fronts - ELEV

    NA

    NA

    SBB (Lot 8)

    Install Hoistway Wiring - ELEV

    NA

    NA

     

    Current and Upcoming Anticipated Closures

    The following shutdown(s)/ closures are anticipated as indicated below. Updates to this schedule will be released weekly in the Project Construction Advisories until the work is complete.  Please contact John Franklin with any specific questions or concerns at john.franklin@ucr.edu.

     

    Description

    Location

    Duration & Date

    Impacted Buildings/ Facilities

    Lot 8

    Lot 8

    Permanently 

    Lot 8

    Lot 43

    Lot 43

    Indefinitely 

    Lot 43

    Anderson Park

    Anderson Park

    Indefinitely

    Anderson Park

  • 950592 UCR SBB - Construction Alert #70

    Current Week

    Construction Activities

     

    Location

    Activity

    Equipment Used

    Anticipated Disturbance

    SBB (Lot 8)

    Controls Hook-up Equipment

    NA

    NA

    SBB (Lot 8)

    Coordinate Drainage Layer Install – EXT-L1

    NA

    NA

    SBB (Lot 8)

    Drainage Layer – EXT-L1

    NA

    NA

    SBB (Lot 8)

    Flashings / Window Surrounds – EXT-NE

    NA

    NA

    SBB (Lot 8)

    Erect Steel Structure for Stairs - EXT-SW

    NA

    NA

    SBB (Lot 8)

    Drainage Layer - EXT-SW

    NA

    NA

    SBB (Lot 8)

    Install Conduit – ELEC-L1

    NA

    NA

    SBB (Lot 8)

    HVAC Ductwork, Hook-up & Insulation – MECH-L1

    NA

    NA

    SBB (Lot 8)

    HVAC Piping, Hook-up & Insulation – MECH-L1

    NA

    NA

    SBB (Lot 8)

    Set Plumbing Equipment – MECH-L1

    NA

    NA

    SBB (Lot 8)

    Install Operable Partition Track -INT-L1

    NA

    NA

    SBB (Lot 8)

    Install In-Wall & Branch Electrical – INT-AUD

    NA

    NA

    SBB (Lot 8)

    Install In-Wall Low Voltage – INT-AUD

    NA

    NA

    SBB (Lot 8)

    Frame Soffit – INT-AUD

    NA

    NA

    SBB (Lot 8)

    Install O/H Supply & Return Ductwork Branch & Seismic – INT-AUD

    NA

    NA

    SBB (Lot 8)

    Hang 1st Side Drywall – INT-L2

    NA

    NA

    SBB (Lot 8)

    Pull Electrical– INT-L2

    NA

    NA

    SBB (Lot 8)

    Install Insulation & Inspect– INT-L2

    NA

    NA

    SBB (Lot 8)

    Install Cable Tray– INT-L2

    NA

    NA

    SBB (Lot 8)

    Install In-Wall & Hard lid Electrical – RR-L2

    NA

    NA

    SBB (Lot 8)

    Install Ductwork Insulation – INT-L3

    NA

    NA

    SBB (Lot 8)

    Pressure Test Ductwork – INT-L3

    NA

    NA

    SBB (Lot 8)

    Install Conduit – ELEC-L3

    NA

    NA

    SBB (Lot 8)

    Install In-Wall & Branch Electrical – INT-L3

    NA

    NA

    SBB (Lot 8)

    Install In-Wall Low Voltage – INT-L3

    NA

    NA

    SBB (Lot 8)

    Frame Ceiling – RR-L3

    NA

    NA

    SBB (Lot 8)

    Hang 1st Side Top Down Drywall – INT-L4

    NA

    NA

    SBB (Lot 8)

    Install Insulation & Inspect – INT-L4

    NA

    NA

    SBB (Lot 8)

    Hang 2nd Side Top Down Drywall & Inspect – INT-L4

    NA

    NA

    SBB (Lot 8)

    Insulate Test Hot/Cold Supply & Return Mech Lines – INT-L4

    NA

    NA

    SBB (Lot 8)

    Install Mechanical / FSD's – ELEC-L4

    NA

    NA

    SBB (Lot 8)

    Frame Remaining Walls, Soffits & Hard lids – INT-L4

    NA

    NA

    SBB (Lot 8)

    Install In-Wall Plumbing

    NA

    NA

    SBB (Lot 8)

    Install In-Wall & Branch Electrical

    NA

    NA

    SBB (Lot 8)

    Install In-Wall Low Voltage

    NA

    NA

    SBB (Lot 8)

    Install Hardlid Electrical

    NA

    NA

    SBB (Lot 8)

    Install Irrigation Sleeves – SITE-AP

    NA

    NA

    SBB (Lot 8)

    Install Site Lighting Underground – SITE-AP

    NA

    NA

     

    Week of March 18, 2024

    Construction Activities 

     

    Location

    Activity

    Equipment Used

    Anticipated Disturbance

    SBB (Lot 8)

    Install PV Panel System - North of E Line

    NA

    NA

    SBB (Lot 8)

    Cement Board – EXT-L1

    NA

    NA

    SBB (Lot 8)

    Secondary Air Barrier– EXT-L1

    NA

    NA

    SBB (Lot 8)

    Drainage Layer– EXT-NE

    NA

    NA

    SBB (Lot 8)

    Cement Board– EXT-NE

    NA

    NA

    SBB (Lot 8)

    Secondary Air Barrier– EXT-SW

    NA

    NA

    SBB (Lot 8)

    Erect Stairs– EXT-SW

    NA

    NA

    SBB (Lot 8)

    Install Communications Racks/Equipment -ELEC-L1

    NA

    NA

    SBB (Lot 8)

    Controls Hook-up Equipment (Incl. Refrigerant Alarm) – MECH-L1

    NA

    NA

    SBB (Lot 8)

    Plumbing Piping, Hook-up & Insulation– MECH-L1

    NA

    NA

    SBB (Lot 8)

    Frame Remaining Walls, Soffits & Hard lids – INT-L1

    NA

    NA

    SBB (Lot 8)

    Install O/H Supply & Return Ductwork Branch & Seismic – INT-AUD

    NA

    NA

    SBB (Lot 8)

    Pull Electrical – INT-AUD

    NA

    NA

    SBB (Lot 8)

    Pull Low Voltage Cable – INT-AUD

    NA

    NA

    SBB (Lot 8)

    Install Conduit – ELEC-AUD

    NA

    NA

    SBB (Lot 8)

    Install Conduit – ELEC-L2

    NA

    NA

    SBB (Lot 8)

    Hang 2nd Side Drywall & Inspect - INT-L2

    NA

    NA

    SBB (Lot 8)

    Pull Low Voltage Cable- INT-L2

    NA

    NA

    SBB (Lot 8)

    Install Backing – RR-L2

    NA

    NA

    SBB (Lot 8)

    Install Insulation and Inspect – RR-L2

    NA

    NA

    SBB (Lot 8)

    Hang Drywall & Inspect– RR-L2

    NA

    NA

    SBB (Lot 8)

    Install Conduit – ELEC-L3

    NA

    NA

    SBB (Lot 8)

    Install Hardlid Electrical – INT-L3

    NA

    NA

    SBB (Lot 8)

    Install In-Wall Plumbing – INT-L3

    NA

    NA

    SBB (Lot 8)

    Install In-Wall & Hard lid Electrical– RR-L3

    NA

    NA

    SBB (Lot 8)

    Install Backing– RR-L3

    NA

    NA

    SBB (Lot 8)

    Install O/H Mechanical Equipment & Ductwork Mains & Seismic – INT-L4

    NA

    NA

    SBB (Lot 8)

    Install Conduit – ELEC-L4

    NA

    NA

    SBB (Lot 8)

    Install In-Wall & Branch Electrical – INT-L4

    NA

    NA

    SBB (Lot 8)

    Install In-Wall Low Voltage – INT-L4

    NA

    NA

    SBB (Lot 8)

    Install Hardlid Electrical – INT-L4

    NA

    NA

    SBB (Lot 8)

    Machine Room Wiring, Start-up, Running Platform - ELEV

    NA

    NA

    SBB (Lot 8)

    F/R/P Site Walls – SITE-AP

    NA

    NA

    SBB (Lot 8)

    Install Site Lighting Underground – SITE-AP

    NA

    NA

     

    Week of March 25, 2024

    Construction Activities 

     

    Location

    Activity

    Equipment Used

    Anticipated Disturbance

    SBB (Lot 8)

    Curtain Wall – Frames – EXT-L1

    NA

    NA

    SBB (Lot 8)

    Set Thin Brick – EXT-L1

    NA

    NA

    SBB (Lot 8)

    Cement Board – EXT-NE

    NA

    NA

    SBB (Lot 8)

    Secondary Air Barrier – EXT-NE

    NA

    NA

    SBB (Lot 8)

    Set Thin Brick – EXT-SW

    NA

    NA

    SBB (Lot 8)

    Punched Openings – Frames – EXT-SW

    NA

    NA

    SBB (Lot 8)

    Curtain Wall – Frames – EXT-SW

    NA

    NA

    SBB (Lot 8)

    Install In-Wall & Branch Electrical - INT-L1

    NA

    NA

    SBB (Lot 8)

    Install In-Wall Low Voltage - INT-L1

    NA

    NA

    SBB (Lot 8)

    Hang Drywall – INT-AUD

    NA

    NA

    SBB (Lot 8)

    Pressure Test Ductwork – INT-AUD

    NA

    NA

    SBB (Lot 8)

    Install Ductwork Insulation – INT-AUD

    NA

    NA

    SBB (Lot 8)

    Install Feeder Cable / Home Runs – ELEC-AUD

    NA

    NA

    SBB (Lot 8)

    Install Switchgear MSB – ELEC-L1

    NA

    NA

    SBB (Lot 8)

    Install Feeder Cable / Home Runs – ELEC-L2

    NA

    NA

    SBB (Lot 8)

    Tape Walls Soffits & Hard lids – RR-L2

    NA

    NA

    SBB (Lot 8)

    Install Feeder Cable / Home Runs – ELEC-L3

    NA

    NA

    SBB (Lot 8)

    Hang 1st Side Drywall – INT-L3

    NA

    NA

    SBB (Lot 8)

    Install Cable Tray– INT-L3

    NA

    NA

    SBB (Lot 8)

    Pull Electrical– INT-L3

    NA

    NA

    SBB (Lot 8)

    Install Insulation & Inspect– INT-L3

    NA

    NA

    SBB (Lot 8)

    Fire Tape– INT-L3

    NA

    NA

    SBB (Lot 8)

    Install Insulation & Inspect – RR-L3

    NA

    NA

    SBB (Lot 8)

    Hang Drywall & Inspect – RR-L3

    NA

    NA

    SBB (Lot 8)

    Install O/H Mechanical Equipment & Ductwork Mains & Seismic – INT-L4

    NA

    NA

    SBB (Lot 8)

    Install O/H Supply & Return Ductwork Branch & Seismic – INT-L4

    NA

    NA

    SBB (Lot 8)

    Pull Electrical – INT-L4

    NA

    NA

    SBB (Lot 8)

    Hang Top Down Drywall – RR-L4

    NA

    NA

    SBB (Lot 8)

    Fire Tape – RR-L4

    NA

    NA

    SBB (Lot 8)

    Fire Caulk Head of Wall – RR-L4

    NA

    NA

    SBB (Lot 8)

    Complete Install Guide Rails - ELEV

    NA

    NA

     

    Current and Upcoming Anticipated Closures

    The following shutdown(s)/ closures are anticipated as indicated below. Updates to this schedule will be released weekly in the Project Construction Advisories until the work is complete.  Please contact John Franklin with any specific questions or concerns at john.franklin@ucr.edu.

     

    Description

    Location

    Duration & Date

    Impacted Buildings/ Facilities

    Lot 8

    Lot 8

    Permanently

    Lot 8

    Lot 43

    Lot 43

    Indefinitely

    Lot 43

    Anderson Park

    Anderson Park

    Indefinitely

    Anderson Park

  • 950592 UCR SBB - Construction Alert #69

    Current Week

    Construction Activities

     

    Location

    Activity

    Equipment Used

    Anticipated Disturbance

    SBB (Lot 8)

    HVAC Ductwork, Hook-up & Insulation

    NA

    NA

    SBB (Lot 8)

    Stuff & Spray Deck Edge

    NA

    NA

    SBB (Lot 8)

    Install PV Panel System - South of E Line

    NA

    NA

    SBB (Lot 8)

    Curtain Wall – Frames – EXT-L1

    NA

    NA

    SBB (Lot 8)

    Set Thin Brick – EXT-L1

    NA

    NA

    SBB (Lot 8)

    Curtain Wall – Frames – EXT-NE

    NA

    NA

    SBB (Lot 8)

    Punched Openings – Glass – EXT-NE

    NA

    NA

    SBB (Lot 8)

    Secondary Air Barrier – EXT-SW

    NA

    NA

    SBB (Lot 8)

    F/R/P Stair Treads/Landings – EXT-SW

    NA

    NA

    SBB (Lot 8)

    HVAC Piping, Hook-up & Insulation – MECH-L1

    NA

    NA

    SBB (Lot 8)

    Plumbing Piping, Hook-up & Insulation – MECH-L1

    NA

    NA

    SBB (Lot 8)

    Pull Low Voltage Cable – INT-L1

    NA

    NA

    SBB (Lot 8)

    Pull Electrical – INT-L1

    NA

    NA

    SBB (Lot 8)

    Install O/H Mechanical Equipment & Ductwork Mains & Seismic – INT-AUD

    NA

    NA

    SBB (Lot 8)

    Install Conduit – ELEC-AUD

    NA

    NA

    SBB (Lot 8)

    Install O/H Electrical Home Runs – INT-L2

    NA

    NA

    SBB (Lot 8)

    Insulate Test Hot/Cold Supply & Return Mech Lines – INT-L2

    NA

    NA

    SBB (Lot 8)

    Install Conduit – ELEC-L2

    NA

    NA

    SBB (Lot 8)

    Install O/H Hot/Cold Supply & Return Branch Mech Lines & Seismic – INT-L3

    NA

    NA

    SBB (Lot 8)

    Install O/H Electrical Home Runs – INT-L3

    NA

    NA

    SBB (Lot 8)

    Install Ductwork Insulation – INT-L3

    NA

    NA

    SBB (Lot 8)

    Install O/H Supply & Return Ductwork Branch & Seismic – INT-L4

    NA

    NA

    SBB (Lot 8)

    Install Lights and Receptacles - ELEV

    NA

    NA

    SBB (Lot 8)

    F/R/P Site Walls – Anderson Park

    NA

    NA

     

    Week of March 11, 2024

    Construction Activities 

     

    Location

    Activity

    Equipment Used

    Anticipated Disturbance

    SBB (Lot 8)

    Install PV Panel System - South of E Line

    NA

    NA

    SBB (Lot 8)

    Curtain Wall – Frames – EXT-L1

    NA

    NA

    SBB (Lot 8)

    Set Thin Brick – EXT-L1

    NA

    NA

    SBB (Lot 8)

    Punched Openings – Glass – EXT-NE

    NA

    NA

    SBB (Lot 8)

    Set Thin Brick – EXT-NE

    NA

    NA

    SBB (Lot 8)

    Punched Openings – Frames - EXT-SW

    NA

    NA

    SBB (Lot 8)

    F/R/P Stair Treads/Landings - EXT-SW

    NA

    NA

    SBB (Lot 8)

    Set Thin Brick - EXT-SW

    NA

    NA

    SBB (Lot 8)

    Hang 1st Side Drywall – INT-L1

    NA

    NA

    SBB (Lot 8)

    Pull Low Voltage Cable – INT-L1

    NA

    NA

    SBB (Lot 8)

    Pull Electrical – INT-L1

    NA

    NA

    SBB (Lot 8)

    Install Fire Sprinkler Mains, Branches & Seismic – INT-AUD

    NA

    NA

    SBB (Lot 8)

    Install O/H Waste & Vent – INT-AUD

    NA

    NA

    SBB (Lot 8)

    Install Conduit – ELEC-AUD

    NA

    NA

    SBB (Lot 8)

    Frame Remaining Walls, Soffits & Hard lids – INT-L2

    NA

    NA

    SBB (Lot 8)

    Install O/H Hot/Cold Supply & Return Branch Mech Lines & Seismic – INT-L3

    NA

    NA

    SBB (Lot 8)

    Install O/H Electrical Home Runs – INT-L3

    NA

    NA

    SBB (Lot 8)

    Install O/H Supply & Return Ductwork Branch & Seismic – INT-L4              

    NA

    NA

    SBB (Lot 8)

    Set, Hook-up & Terminate MTS – Electrical

    NA

    NA

     

    Week of March 18, 2024

    Construction Activities 

     

    Location

    Activity

    Equipment Used

    Anticipated Disturbance

    SBB (Lot 8)

    Install PV Panel System - North of E Line

    NA

    NA

    SBB (Lot 8)

    Cement Board – EXT-L1

    NA

    NA

    SBB (Lot 8)

    Secondary Air Barrier– EXT-L1

    NA

    NA

    SBB (Lot 8)

    Drainage Layer– EXT-NE

    NA

    NA

    SBB (Lot 8)

    Cement Board– EXT-NE

    NA

    NA

    SBB (Lot 8)

    Secondary Air Barrier– EXT-SW

    NA

    NA

    SBB (Lot 8)

    Erect Stairs– EXT-SW

    NA

    NA

    SBB (Lot 8)

    Install Communications Racks/Equipment -ELEC-L1

    NA

    NA

    SBB (Lot 8)

    Controls Hook-up Equipment (Incl. Refrigerant Alarm) – MECH-L1

    NA

    NA

    SBB (Lot 8)

    Plumbing Piping, Hook-up & Insulation– MECH-L1

    NA

    NA

    SBB (Lot 8)

    Frame Remaining Walls, Soffits & Hard lids – INT-L1

    NA

    NA

    SBB (Lot 8)

    Install O/H Supply & Return Ductwork Branch & Seismic – INT-AUD

    NA

    NA

    SBB (Lot 8)

    Pull Electrical – INT-AUD

    NA

    NA

    SBB (Lot 8)

    Pull Low Voltage Cable – INT-AUD

    NA

    NA

    SBB (Lot 8)

    Install Conduit – ELEC-AUD

    NA

    NA

    SBB (Lot 8)

    Install Conduit – ELEC-L2

    NA

    NA

    SBB (Lot 8)

    Hang 2nd Side Drywall & Inspect - INT-L2

    NA

    NA

    SBB (Lot 8)

    Pull Low Voltage Cable- INT-L2

    NA

    NA

    SBB (Lot 8)

    Install Backing – RR-L2

    NA

    NA

    SBB (Lot 8)

    Install Insulation and Inspect – RR-L2

    NA

    NA

    SBB (Lot 8)

    Hang Drywall & Inspect– RR-L2

    NA

    NA

    SBB (Lot 8)

    Install Conduit – ELEC-L3

    NA

    NA

    SBB (Lot 8)

    Install Hardlid Electrical – INT-L3

    NA

    NA

    SBB (Lot 8)

    Install In-Wall Plumbing – INT-L3

    NA

    NA

    SBB (Lot 8)

    Install In-Wall & Hard lid Electrical– RR-L3

    NA

    NA

    SBB (Lot 8)

    Install Backing– RR-L3

    NA

    NA

    SBB (Lot 8)

    Install O/H Mechanical Equipment & Ductwork Mains & Seismic – INT-L4

    NA

    NA

    SBB (Lot 8)

    Install Conduit – ELEC-L4

    NA

    NA

    SBB (Lot 8)

    Install In-Wall & Branch Electrical – INT-L4

    NA

    NA

    SBB (Lot 8)

    Install In-Wall Low Voltage – INT-L4

    NA

    NA

    SBB (Lot 8)

    Install Hardlid Electrical – INT-L4

    NA

    NA

    SBB (Lot 8)

    Machine Room Wiring, Start-up, Running Platform - ELEV

    NA

    NA

    SBB (Lot 8)

    F/R/P Site Walls – SITE-AP

    NA

    NA

    SBB (Lot 8)

    Install Site Lighting Underground – SITE-AP

    NA

    NA

     

    Current and Upcoming Anticipated Closures

    The following shutdown(s)/ closures are anticipated as indicated below. Updates to this schedule will be released weekly in the Project Construction Advisories until the work is complete.  Please contact John Franklin with any specific questions or concerns at john.franklin@ucr.edu.

     

    Description

    Location

    Duration & Date

    Impacted Buildings/ Facilities

    Lot 8

    Lot 8

    Permanently

    Lot 8

    Lot 43

    Lot 43

    Indefinitely

    Lot 43

    Anderson Park

    Anderson Park

    Indefinitely

    Anderson Park

  • 950592 UCR SBB - Construction Alert #68

    Current Week

    Construction Activities

     

    Location

    Activity

    Equipment Used

    Anticipated Disturbance

    SBB (Lot 8)

    Electrical Hook-up Equipment

    NA

    NA

    SBB (Lot 8)

    Install PV Panel Secondary Framing - North of E Line

    Crane

    Noise Due to Equipment

    SBB (Lot 8)

    HVAC Piping, Hook-up & Insulation

    NA

    NA

    SBB (Lot 8)

    Flashings / Window Surrounds – EXT-L1

    NA

    NA

    SBB (Lot 8)

    Drainage Layer – EXT-L1

    NA

    NA

    SBB (Lot 8)

    Cement Board – EXT-L1

    NA

    NA

    SBB (Lot 8)

    Rigid Insulation & Air Water Barrier – EXT-NE

    NA

    NA

    SBB (Lot 8)

    Field Measure for Curtain Wall – EXT-NE

    NA

    NA

    SBB (Lot 8)

    Flashings / Window Surrounds – EXT-SW

    NA

    NA

    SBB (Lot 8)

    Drainage Layer – EXT-SW

    NA

    NA

    SBB (Lot 8)

    Install O/H Electrical Home Runs – INT-L1

    NA

    NA

    SBB (Lot 8)

    Install Ductwork Insulation – INT-L1

    NA

    NA

    SBB (Lot 8)

    HVAC Ductwork, Hook-up & Insulation – MECH-L1

    NA

    NA

    SBB (Lot 8)

    Controls Hook-up Equipment – MECH-L1

    NA

    NA

    SBB (Lot 8)

    HVAC Piping, Hook-up & Insulation – MECH-L1

    NA

    NA

    SBB (Lot 8)

    Plumbing Piping, Hook-up & Insulation – MECH-L1

    NA

    NA

    SBB (Lot 8)

    Install Hot/Cold Domestic Water Lines & Seismic – MECH-L1

    NA

    NA

    SBB (Lot 8)

    Tape Walls – MECH-L1

    NA

    NA

    SBB (Lot 8)

    Install O/H Supply & Return Ductwork Branch & Seismic – INT-L2

    NA

    NA

    SBB (Lot 8)

    Install Hot/Cold Domestic Water Lines & Seismic – INT-L3

    NA

    NA

    SBB (Lot 8)

    Install O/H Waste & Vent – INT-L3

    NA

    NA

    SBB (Lot 8)

    Install O/H Mechanical Equipment & Ductwork Mains & Seismic – INT-L3

    NA

    NA

    SBB (Lot 8)

    Tape Walls – ELEC-L3

    NA

    NA

     

    Week of March 4, 2024

    Construction Activities 

     

    Location

    Activity

    Equipment Used

    Anticipated Disturbance

    SBB (Lot 8)

    HVAC Ductwork, Hook-up & Insulation

    NA

    NA

    SBB (Lot 8)

    Stuff & Spray Deck Edge

    NA

    NA

    SBB (Lot 8)

    Install PV Panel System - South of E Line

    Crane

    Noise Due to Equipment

    SBB (Lot 8)

    Curtain Wall – Frames – EXT-L1

    NA

    NA

    SBB (Lot 8)

    Set Thin Brick – EXT-L1

    NA

    NA

    SBB (Lot 8)

    Curtain Wall – Frames – EXT-NE

    NA

    NA

    SBB (Lot 8)

    Punched Openings – Glass – EXT-NE

    NA

    NA

    SBB (Lot 8)

    Secondary Air Barrier – EXT-SW

    NA

    NA

    SBB (Lot 8)

    F/R/P Stair Treads/Landings – EXT-SW

    NA

    NA

    SBB (Lot 8)

    HVAC Piping, Hook-up & Insulation – MECH-L1

    NA

    NA

    SBB (Lot 8)

    Plumbing Piping, Hook-up & Insulation – MECH-L1

    NA

    NA

    SBB (Lot 8)

    Pull Low Voltage Cable – INT-L1

    NA

    NA

    SBB (Lot 8)

    Pull Electrical – INT-L1

    NA

    NA

    SBB (Lot 8)

    Install O/H Mechanical Equipment & Ductwork Mains & Seismic – INT-AUD

    NA

    NA

    SBB (Lot 8)

    Install Conduit – ELEC-AUD

    NA

    NA

    SBB (Lot 8)

    Install O/H Electrical Home Runs – INT-L2

    NA

    NA

    SBB (Lot 8)

    Insulate Test Hot/Cold Supply & Return Mech Lines – INT-L2

    NA

    NA

    SBB (Lot 8)

    Install Conduit – ELEC-L2

    NA

    NA

    SBB (Lot 8)

    Install O/H Hot/Cold Supply & Return Branch Mech Lines & Seismic – INT-L3

    NA

    NA

    SBB (Lot 8)

    Install O/H Electrical Home Runs – INT-L3

    NA

    NA

    SBB (Lot 8)

    Install Ductwork Insulation – INT-L3

    NA

    NA

    SBB (Lot 8)

    Install O/H Supply & Return Ductwork Branch & Seismic – INT-L4

    NA

    NA

    SBB (Lot 8)

    Install Lights and Receptacles - ELEV

    NA

    NA

    SBB (Lot 8)

    F/R/P Site Walls – Anderson Park

    NA

    NA

     

    Week of March 11, 2024

    Construction Activities 

     

    Location

    Activity

    Equipment Used

    Anticipated Disturbance

    SBB (Lot 8)

    Install PV Panel System - South of E Line

    Crane

    Noise Due to Equipment

    SBB (Lot 8)

    Curtain Wall – Frames – EXT-L1

    NA

    NA

    SBB (Lot 8)

    Set Thin Brick – EXT-L1

    NA

    NA

    SBB (Lot 8)

    Punched Openings – Glass – EXT-NE

    NA

    NA

    SBB (Lot 8)

    Set Thin Brick – EXT-NE

    NA

    NA

    SBB (Lot 8)

    Punched Openings – Frames - EXT-SW

    NA

    NA

    SBB (Lot 8)

    F/R/P Stair Treads/Landings - EXT-SW

    NA

    NA

    SBB (Lot 8)

    Set Thin Brick - EXT-SW

    NA

    NA

    SBB (Lot 8)

    Hang 1st Side Drywall – INT-L1

    NA

    NA

    SBB (Lot 8)

    Pull Low Voltage Cable – INT-L1

    NA

    NA

    SBB (Lot 8)

    Pull Electrical – INT-L1

    NA

    NA

    SBB (Lot 8)

    Install Fire Sprinkler Mains, Branches & Seismic – INT-AUD

    NA

    NA

    SBB (Lot 8)

    Install O/H Waste & Vent – INT-AUD

    NA

    NA

    SBB (Lot 8)

    Install Conduit – ELEC-AUD

    NA

    NA

    SBB (Lot 8)

    Frame Remaining Walls, Soffits & Hard lids – INT-L2

    NA

    NA

    SBB (Lot 8)

    Install O/H Hot/Cold Supply & Return Branch Mech Lines & Seismic – INT-L3

    NA

    NA

    SBB (Lot 8)

    Install O/H Electrical Home Runs – INT-L3

    NA

    NA

    SBB (Lot 8)

    Install O/H Supply & Return Ductwork Branch & Seismic – INT-L4          

    NA

    NA

    SBB (Lot 8)

    Set, Hook-up & Terminate MTS – Electrical

    NA

    NA

     

     

    Current and Upcoming Anticipated Closures

    The following shutdown(s)/ closures are anticipated as indicated below. Updates to this schedule will be released weekly in the Project Construction Advisories until the work is complete.  Please contact John Franklin with any specific questions or concerns at john.franklin@ucr.edu.

     

    Description

    Location

    Duration & Date

    Impacted Buildings/ Facilities

    Lot 8

    Lot 8

    Permanently

    Lot 8

    Lot 43

    Lot 43

    Indefinitely

    Lot 43

    Anderson Park

    Anderson Park

    Indefinitely

    Anderson Park

  • 950592 UCR SBB - Construction Alert #67

    Current Week

    Construction Activities

     

    Location

    Activity

    Equipment Used

    Anticipated Disturbance

    SBB (Lot 8)

    Exterior Framing – East Elevation

    NA

    NA

    SBB (Lot 8)

    F/R/P Stair Treads/Landings – EXT-NE

    NA

    NA

    SBB (Lot 8)

    Exterior Framing - North Elevation – EXT-NE

    NA

    NA

    SBB (Lot 8)

    Rigid Insulation & Air Water Barrier – EXT-NE

    NA

    NA

    SBB (Lot 8)

    Field Measure for Curtain Wall – EXT-NE

    NA

    NA

    SBB (Lot 8)

    Flashings / Window Surrounds – EXT-NE

    NA

    NA

    SBB (Lot 8)

    Erect Steel Structure for Stairs – EXT-SW

    NA

    NA

    SBB (Lot 8)

    Rigid Insulation & Air Water Barrier– EXT-SW

    NA

    NA

    SBB (Lot 8)

    Exterior Framing - South Elevation– EXT-SW

    NA

    NA

    SBB (Lot 8)

    Field Measure for Curtain Wall– EXT-SW

    NA

    NA

    SBB (Lot 8)

    Flashings / Window Surrounds– EXT-SW

    NA

    NA

    SBB (Lot 8)

    Drainage Layer– EXT-SW

    NA

    NA

    SBB (Lot 8)

    Cement Board– EXT-SW

    NA

    NA

    SBB (Lot 8)

    Secondary Air Barrier– EXT-SW

    NA

    NA

    SBB (Lot 8)

    Erect Stairs– EXT-SW

    NA

    NA

    SBB (Lot 8)

    Install Ductwork Insulation– INT-L1

    NA

    NA

    SBB (Lot 8)

    Pressure Test Hot/Cold Supply & Return Mech Lines– INT-L1

    NA

    NA

    SBB (Lot 8)

    Insulate Test Hot/Cold Supply & Return Mech Lines– INT-L1

    NA

    NA

    SBB (Lot 8)

    HVAC Ductwork, Hook-up & Insulation – MECH-L1

    NA

    NA

    SBB (Lot 8)

    Controls Hook-up Equipment (Incl. Refrigerant Alarm) – MECH-L1

    NA

    NA

    SBB (Lot 8)

    HVAC Piping, Hook-up & Insulation – MECH-L1

    NA

    NA

    SBB (Lot 8)

    Plumbing Piping, Hook-up & Insulation – MECH-L1

    NA

    NA

    SBB (Lot 8)

    Set Distribution Board HDP-1A – MECH-L1

    NA

    NA

    SBB (Lot 8)

    Hang Drywall – INT-AUD

    NA

    NA

    SBB (Lot 8)

    Tape Walls – ELEC-AUD

    NA

    NA

    SBB (Lot 8)

    Fire Caulk Head of Wall – ELEC-AUD

    NA

    NA

    SBB (Lot 8)

    Prime & 1st Coat of Paint, Walls & Exposed Ceilings – ELEC-AUD

    NA

    NA

    SBB (Lot 8)

    Install Hot/Cold Supply & Return Mech Lines & Seismic – INT-L2

    NA

    NA

    SBB (Lot 8)

    Pressure Test Ductwork– INT-L2

    NA

    NA

    SBB (Lot 8)

    Install O/H Electrical Home Runs – INT-L2

    NA

    NA

    SBB (Lot 8)

    Tape Walls – ELEC-L3

    NA

    NA

    SBB (Lot 8)

    Fire Caulk Head of Wall– ELEC-L3

    NA

    NA

    SBB (Lot 8)

    Fire Tape – INT-L4

    NA

    NA

    SBB (Lot 8)

    Fire Caulk Head of Wall – INT-L4

    NA

    NA

    SBB (Lot 8)

    Install O/H Waste and Vent – INT-L4

    NA

    NA

    SBB (Lot 8)

    Install Insulation and Inspect – ELEC-L4

    NA

    NA

    SBB (Lot 8)

    Hang Drywall and Inspect – ELEC-L4

    NA

    NA

    SBB (Lot 8)

    Tape Walls – ELEC-L4

    NA

    NA

     

    Week of February 26, 2024

    Construction Activities 

     

    Location

    Activity

    Equipment Used

    Anticipated Disturbance

    SBB (Lot 8)

    Electrical Hook-up Equipment

    NA

    NA

    SBB (Lot 8)

    Install PV Panel Secondary Framing - North of E Line

    Crane

    Noise Due to Equipment

    SBB (Lot 8)

    HVAC Piping, Hook-up & Insulation

    NA

    NA

    SBB (Lot 8)

    Flashings / Window Surrounds – EXT-L1

    NA

    NA

    SBB (Lot 8)

    Drainage Layer – EXT-L1

    NA

    NA

    SBB (Lot 8)

    Cement Board – EXT-L1

    NA

    NA

    SBB (Lot 8)

    Rigid Insulation & Air Water Barrier – EXT-NE

    NA

    NA

    SBB (Lot 8)

    Field Measure for Curtain Wall – EXT-NE

    NA

    NA

    SBB (Lot 8)

    Flashings / Window Surrounds – EXT-SW

    NA

    NA

    SBB (Lot 8)

    Drainage Layer – EXT-SW

    NA

    NA

    SBB (Lot 8)

    Install O/H Electrical Home Runs – INT-L1

    NA

    NA

    SBB (Lot 8)

    Install Ductwork Insulation – INT-L1

    NA

    NA

    SBB (Lot 8)

    HVAC Ductwork, Hook-up & Insulation – MECH-L1

    NA

    NA

    SBB (Lot 8)

    Controls Hook-up Equipment – MECH-L1

    NA

    NA

    SBB (Lot 8)

    HVAC Piping, Hook-up & Insulation – MECH-L1

    NA

    NA

    SBB (Lot 8)

    Plumbing Piping, Hook-up & Insulation – MECH-L1

    NA

    NA

    SBB (Lot 8)

    Install Hot/Cold Domestic Water Lines & Seismic – MECH-L1

    NA

    NA

    SBB (Lot 8)

    Tape Walls – MECH-L1

    NA

    NA

    SBB (Lot 8)

    Install O/H Supply & Return Ductwork Branch & Seismic – INT-L2

    NA

    NA

    SBB (Lot 8)

    Install Hot/Cold Domestic Water Lines & Seismic – INT-L3

    NA

    NA

    SBB (Lot 8)

    Install O/H Waste & Vent – INT-L3

    NA

    NA

    SBB (Lot 8)

    Install O/H Mechanical Equipment & Ductwork Mains & Seismic – INT-L3

    NA

    NA

    SBB (Lot 8)

    Tape Walls – ELEC-L3

    NA

    NA

     

    Week of March 4, 2024

    Construction Activities 

     

    Location

    Activity

    Equipment Used

    Anticipated Disturbance

    SBB (Lot 8)

    HVAC Ductwork, Hook-up & Insulation

    NA

    NA

    SBB (Lot 8)

    Stuff & Spray Deck Edge

    NA

    NA

    SBB (Lot 8)

    Install PV Panel System - South of E Line

    NA

    NA

    SBB (Lot 8)

    Curtain Wall – Frames – EXT-L1

    NA

    NA

    SBB (Lot 8)

    Set Thin Brick – EXT-L1

    NA

    NA

    SBB (Lot 8)

    Curtain Wall – Frames – EXT-NE

    NA

    NA

    SBB (Lot 8)

    Punched Openings – Glass – EXT-NE

    NA

    NA

    SBB (Lot 8)

    Secondary Air Barrier – EXT-SW

    NA

    NA

    SBB (Lot 8)

    F/R/P Stair Treads/Landings – EXT-SW

    NA

    NA

    SBB (Lot 8)

    HVAC Piping, Hook-up & Insulation – MECH-L1

    NA

    NA

    SBB (Lot 8)

    Plumbing Piping, Hook-up & Insulation – MECH-L1

    NA

    NA

    SBB (Lot 8)

    Pull Low Voltage Cable – INT-L1

    NA

    NA

    SBB (Lot 8)

    Pull Electrical – INT-L1

    NA

    NA

    SBB (Lot 8)

    Install O/H Mechanical Equipment & Ductwork Mains & Seismic – INT-AUD

    NA

    NA

    SBB (Lot 8)

    Install Conduit – ELEC-AUD

    NA

    NA

    SBB (Lot 8)

    Install O/H Electrical Home Runs – INT-L2

    NA

    NA

    SBB (Lot 8)

    Insulate Test Hot/Cold Supply & Return Mech Lines – INT-L2

    NA

    NA

    SBB (Lot 8)

    Install Conduit – ELEC-L2

    NA

    NA

    SBB (Lot 8)

    Install O/H Hot/Cold Supply & Return Branch Mech Lines & Seismic – INT-L3

    NA

    NA

    SBB (Lot 8)

    Install O/H Electrical Home Runs – INT-L3

    NA

    NA

    SBB (Lot 8)

    Install Ductwork Insulation – INT-L3

    NA

    NA

    SBB (Lot 8)

    Install O/H Supply & Return Ductwork Branch & Seismic – INT-L4

    NA

    NA

    SBB (Lot 8)

    Install Lights and Receptacles - ELEV

    NA

    NA

    SBB (Lot 8)

    F/R/P Site Walls – Anderson Park

    NA

    NA

     

     

    Current and Upcoming Anticipated Closures

    The following shutdown(s)/ closures are anticipated as indicated below. Updates to this schedule will be released weekly in the Project Construction Advisories until the work is complete.  Please contact John Franklin with any specific questions or concerns at john.franklin@ucr.edu.

     

    Description

    Location

    Duration & Date

    Impacted Buildings/ Facilities

    Lot 8

    Lot 8

    Permanently

    Lot 8

    Lot 43

    Lot 43

    Indefinitely

    Lot 43

    Anderson Park

    Anderson Park

    Indefinitely

    Anderson Park

  • 950592 UCR SBB - Construction Alert #59

    Current Week

    Construction Activities

     

    Location

    Activity

    Equipment Used

    Anticipated Disturbance

    SBB (Lot 8) Concrete

    Edge Form / Bulkhead SOG North – Auditorium Steps

    NA

    NA

    SBB (Lot 8) Concrete

    Rebar – Auditorium Steps

    NA

    NA

    SBB (Lot 8) Concrete

    Underslab Electrical Rough-in - Auditorium Steps

    NA

    NA

    SBB (Lot 8) Concrete

    Form Steps - Auditorium

    NA

    NA

    SBB (Lot 8) Concrete

    Close Two Side Forms – Vert L5

    NA

    NA

    SBB (Lot 8) Concrete

    Pour – Vert L5

    Concrete Pump

    Noise due to Equipment

    SBB (Lot 8) Concrete

    Strip Walls and columns – Vert L5

    NA

    NA

    SBB (Lot 8) Concrete

    Cure for Steel Erection – Vert L5

    NA

    NA

    SBB (Lot 8) Concrete

    Strip and Haul off Form System – Deck L5

    Crane

    Noise due to Equipment

    SBB (Lot 8)

    Install Roof Drains

    NA

    NA

    SBB (Lot 8)

    Soffit Framing – EXT L1

    NA

    NA

    SBB (Lot 8)

    Flashing and Window Surrounds-EXT L1

    NA

    NA

    SBB (Lot 8)

    Rigid Insulation and Air Water Barrier – EXT L1

    NA

    NA

    SBB (Lot 8)

    Electrical Rough-in Soffits – EXT L1

    NA

    NA

    SBB (Lot 8) Concrete

    Form Grand Stair – INT L1

    NA

    NA

    SBB (Lot 8)

    Install Fire Sprinkler Mains, Branches, & Seismic

    NA

    NA

    SBB (Lot 8) Concrete

    Remove Re-Shore – INT L2

    NA

    NA

    SBB (Lot 8)

    Frame Interference Walls and Install Foor Frames – INT L2

    NA

    NA

    SBB (Lot 8)

    Install Early MEP to Support Top Drown Drywall – INT L2

    NA

    NA

    SBB (Lot 8) Concrete

    F/R/P Walls at Transformer Yard

    Concrete Pump

    Noise due to Equipment

    SBB (Lot 8)

    Install Fire Water College Place to SBB POC

    NA

    NA

     

    Week of January 1, 2023

    Construction Activities 

     

    Location

    Activity

    Equipment Used

    Anticipated Disturbance

    SBB (Lot 8) Concrete

    Underslab Electrical Rough-in - Auditorium Steps

    NA

    NA

    SBB (Lot 8) Concrete

    Form Steps - Auditorium

    NA

    NA

    SBB (Lot 8)

    QC / Inspection – Auditorium

    NA

    NA

    SBB (Lot 8)

    Strip and Haul Off Form system

    Crane

    Noise due to Equipment

    SBB (Lot 8)

    Install Roofing at Mechanical Equipment Pad

    NA

    NA

    SBB (Lot 8)

    Install Mechanical Duct Pipe Supports – Roof

    NA

    NA

    SBB (Lot 8)

    Set Scaffold to Roof

    NA

    NA

    SBB (Lot 8)

    Install Temp Roofing at Low Roof

    NA

    NA

    SBB (Lot 8)

    Set Scaffold for level 2

    NA

    NA

    SBB (Lot 8)

    Erect Tube Steel Structure

    Crane

    Noise due to Equipment

    SBB (Lot 8)

    Form Grand Stair

    NA

    NA

    SBB (Lot 8)

    Install Mechanical / FSD’s – Electrical/BDF Room

    NA

    NA

    SBB (Lot 8)

    Install In-Wall Electrical – Electrical/BDF Room

    NA

    NA

    SBB (Lot 8)

    Hang 1st Side Top Down Drywall – INT-L2

    NA

    NA

    SBB (Lot 8)

    Install Insulation & Inspect -INT-L2

    NA

    NA

    SBB (Lot 8)

    Layout Framing and Install Top Track

    NA

    NA

    SBB (Lot 8) Concrete

    F/R/P Walls at Transformer Yard Slab

    Concrete Pump

    Noise due to Equipment

    SBB (Lot 8) Concrete

    F/R/P Transformer Yard Slab

    Concrete Pump

    Noise due to Equipment

     

    Week of January 8, 2023

    Construction Activities 

     

    Location

    Activity

    Equipment Used

    Anticipated Disturbance

    SBB (Lot 8) Concrete

    Pour Steps Auditorium

    Concrete Pump

    Noise due to Equipment

    SBB (Lot 8) Concrete

    Strip Edge Form / Bulkhead – Auditorium Steps

    NA

    NA

    SBB (Lot 8)

    Install Roofing Mechanical Equipment Pad

    NA

    NA

    SBB (Lot 8)

    Install Mechanical Duct / Pipe Supports - Roof

    Crane

    Noise due to Equipment

    SBB (Lot 8)

    MEP Stub-up Penetration - Roof

    NA

    NA

    SBB (Lot 8)

    Drainage Layer – EXT-L1

    NA

    NA

    SBB (Lot 8)

    Cement Board – EXT-L1

    NA

    NA

    SBB (Lot 8)

    Secondary Air Barrier – EXT-L1

    NA

    NA

    SBB (Lot 8)

    Electrical Rough-in Soffits – EXT-L1

    NA

    NA

    SBB (Lot 8)

    Soffit Sheathing – EXT-L1

    NA

    NA

    SBB (Lot 8)

    Misc In-Wall Steel for canopy-EXT-NE

    NA

    NA

    SBB (Lot 8)

    Exterior Framing – East Elevation L1

    NA

    NA

    SBB (Lot 8)

    Erect Stairs – EXT-NE

    NA

    NA

    SBB (Lot 8)

    Install Temp Roofing

    NA

    NA

    SBB (Lot 8)

    Erect Tube Steel Structure-EXT SW

    NA

    NA

    SBB (Lot 8)

    Install Metal Decking – EXT SW

    NA

    NA

    SBB (Lot 8) Concrete

    Pour Grand Stair – INT-L1

    Concrete Pump

    Noise due to Equipment

    SBB (Lot 8)

    Install O/H Waste and Vent – INT-L1

    NA

    NA

    SBB (Lot 8)

    Install Hot/Cold Domestic Water Lines and Seismic – INT-L1

    NA

    NA

    SBB (Lot 8)

    Install O/H Mechanical Equipment and Ductwork Mains and Seismic – INT-L1

    NA

    NA

    SBB (Lot 8)

    Install In-Wall Electrical – Elec-L1

    NA

    NA

    SBB (Lot 8)

    Install Backing – Elec-L1

    NA

    NA

    SBB (Lot 8)

    Install Insulation and Inspect – Elect-L1

    NA

    NA

    SBB (Lot 8)

    Layout Framing and Install Top Track – Auditorium

    NA

    NA

    SBB (Lot 8)

    Fire Tape – INT-L2

    NA

    NA

    SBB (Lot 8)

    Fire Caulk Head of Wall – INT-L2

    NA

    NA

    SBB (Lot 8)

    Frame Interference Walls and Install Door Framed – INT-L3

    NA

    NA

    SBB (Lot 8)

    Install Early MEP to Support Top Down Drywall – INT-L3

    NA

    NA

    SBB (Lot 8)

    Rough Grade / Cut Curbs – Anderson Park

    Loader

    Noise due to Equipment

     

    Current and Upcoming Anticipated Closures

    The following shutdown(s)/ closures are anticipated as indicated below. Updates to this schedule will be released weekly in the Project Construction Advisories until the work is complete.  Please contact John Franklin with any specific questions or concerns at john.franklin@ucr.edu.

     

    Description

    Location

    Duration & Date

    Impacted Buildings/ Facilities

    Lot 8

    Lot 8

    Permanently

    Lot 8

    Lot 43

    Lot 43

    Indefinitely

    Lot 43

    Anderson Park

    Anderson Park

    Indefinitely

    Anderson Park

  • 950592 UCR SBB - Construction Alert #66

    Current Week

    Construction Activities

     

    Location

    Activity

    Equipment Used

    Anticipated Disturbance

    SBB (Lot 8)

    Install PV Panel Secondary Framing - South of E Line

    Crane

    Noise Due to Equipment

    SBB (Lot 8)

    Set Mechanical Equipment - Roof

    Crane

    Noise Due to Equipment

    SBB (Lot 8)

    Flashings / Window Surrounds – EXT-L1

    NA

    NA

    SBB (Lot 8)

    Drainage Layer – EXT-L1

    NA

    NA

    SBB (Lot 8)

    Cement Board – EXT-L1

    NA

    NA

    SBB (Lot 8)

    Exterior Framing – East Elevation

    NA

    NA

    SBB (Lot 8)

    F/R/P Stair Treads/Landings – EXT-NE

    NA

    NA

    SBB (Lot 8)

    Exterior Framing - North Elevation – EXT-NE

    NA

    NA

    SBB (Lot 8)

    Rigid Insulation & Air Water Barrier – EXT-NE

    NA

    NA

    SBB (Lot 8)

    Field Measure for Curtain Wall – EXT-NE

    NA

    NA

    SBB (Lot 8)

    Flashings / Window Surrounds – EXT-NE

    NA

    NA

    SBB (Lot 8)

    Erect Steel Structure for Stairs – EXT-SW

    NA

    NA

    SBB (Lot 8)

    Rigid Insulation & Air Water Barrier– EXT-SW

    NA

    NA

    SBB (Lot 8)

    Exterior Framing - South Elevation– EXT-SW

    NA

    NA

    SBB (Lot 8)

    Field Measure for Curtain Wall– EXT-SW

    NA

    NA

    SBB (Lot 8)

    Flashings / Window Surrounds– EXT-SW

    NA

    NA

    SBB (Lot 8)

    Drainage Layer– EXT-SW

    NA

    NA

    SBB (Lot 8)

    Cement Board– EXT-SW

    NA

    NA

    SBB (Lot 8)

    Secondary Air Barrier– EXT-SW

    NA

    NA

    SBB (Lot 8)

    Erect Stairs– EXT-SW

    NA

    NA

    SBB (Lot 8)

    Install O/H Hot/Cold Supply and Return Branch Mech Lines – INT-L1

    NA

    NA

    SBB (Lot 8)

    Install Ductwork Insulation– INT-L1

    NA

    NA

    SBB (Lot 8)

    Pressure Test Hot/Cold Supply & Return Mech Lines– INT-L1

    NA

    NA

    SBB (Lot 8)

    Insulate Test Hot/Cold Supply & Return Mech Lines– INT-L1

    NA

    NA

    SBB (Lot 8)

    HVAC Ductwork, Hook-up & Insulation – MECH-L1

    NA

    NA

    SBB (Lot 8)

    Controls Hook-up Equipment (Incl. Refrigerant Alarm) – MECH-L1

    NA

    NA

    SBB (Lot 8)

    HVAC Piping, Hook-up & Insulation – MECH-L1

    NA

    NA

    SBB (Lot 8)

    Plumbing Piping, Hook-up & Insulation – MECH-L1

    NA

    NA

    SBB (Lot 8)

    Set Distribution Board HDP-1A – MECH-L1

    NA

    NA

    SBB (Lot 8)

    Frame Remaining Walls, Soffits & Hard lids – INT-L1

    NA

    NA

    SBB (Lot 8)

    Install Insulation & Inspect - AUD

    NA

    NA

    SBB (Lot 8)

    Install Backing – ELEC-AUD

    NA

    NA

    SBB (Lot 8)

    Install Insulation & Inspect – ELEC-AUD

    NA

    NA

    SBB (Lot 8)

    Hang Drywall & Inspect – ELEC-AUD

    NA

    NA

    SBB (Lot 8)

    Install Hot/Cold Domestic Water Lines & Seismic – INT-L3

    NA

    NA

    SBB (Lot 8)

    Install O/H Waste & Vent – INT-L3

    NA

    NA

    SBB (Lot 8)

    Install O/H Mechanical Equipment & Ductwork Mains & Seismic – INT-L3

    NA

    NA

    SBB (Lot 8)

    Install Backing – ELEC-L3

    NA

    NA

    SBB (Lot 8)

    Install Insulation & Inspect – ELEC-L3

    NA

    NA

    SBB (Lot 8)

    Hang Drywall and Inspect – ELEC-L3

    NA

    NA

    SBB (Lot 8)

    Hang 1st Side Top Down Drywall – INT-L4

    NA

    NA

    SBB (Lot 8)

    Install Insulation and Inspect – INT-L4

    NA

    NA

    SBB (Lot 8)

    Hang 2nd Side Top Down Drywall & Inspect– INT-L4

    NA

    NA

    SBB (Lot 8)

    Install Mechanical / FSD's – ELEC-L4

    NA

    NA

    SBB (Lot 8)

    Install In-Wall Electrical – ELEC-L4

    NA

    NA

    SBB (Lot 8)

    Install Backing – ELEC-L4

    NA

    NA

     

    Week of February 19, 2024

    Construction Activities 

     

    Location

    Activity

    Equipment Used

    Anticipated Disturbance

    SBB (Lot 8)

    Exterior Framing – East Elevation

    NA

    NA

    SBB (Lot 8)

    F/R/P Stair Treads/Landings – EXT-NE

    NA

    NA

    SBB (Lot 8)

    Exterior Framing - North Elevation – EXT-NE

    NA

    NA

    SBB (Lot 8)

    Rigid Insulation & Air Water Barrier – EXT-NE

    NA

    NA

    SBB (Lot 8)

    Field Measure for Curtain Wall – EXT-NE

    NA

    NA

    SBB (Lot 8)

    Flashings / Window Surrounds – EXT-NE

    NA

    NA

    SBB (Lot 8)

    Erect Steel Structure for Stairs – EXT-SW

    NA

    NA

    SBB (Lot 8)

    Rigid Insulation & Air Water Barrier– EXT-SW

    NA

    NA

    SBB (Lot 8)

    Exterior Framing - South Elevation– EXT-SW

    NA

    NA

    SBB (Lot 8)

    Field Measure for Curtain Wall– EXT-SW

    NA

    NA

    SBB (Lot 8)

    Flashings / Window Surrounds– EXT-SW

    NA

    NA

    SBB (Lot 8)

    Drainage Layer– EXT-SW

    NA

    NA

    SBB (Lot 8)

    Cement Board– EXT-SW

    NA

    NA

    SBB (Lot 8)

    Secondary Air Barrier– EXT-SW

    NA

    NA

    SBB (Lot 8)

    Erect Stairs– EXT-SW

    NA

    NA

    SBB (Lot 8)

    Install Ductwork Insulation– INT-L1

    NA

    NA

    SBB (Lot 8)

    Pressure Test Hot/Cold Supply & Return Mech Lines– INT-L1

    NA

    NA

    SBB (Lot 8)

    Insulate Test Hot/Cold Supply & Return Mech Lines– INT-L1

    NA

    NA

    SBB (Lot 8)

    HVAC Ductwork, Hook-up & Insulation – MECH-L1

    NA

    NA

    SBB (Lot 8)

    Controls Hook-up Equipment (Incl. Refrigerant Alarm) – MECH-L1

    NA

    NA

    SBB (Lot 8)

    HVAC Piping, Hook-up & Insulation – MECH-L1

    NA

    NA

    SBB (Lot 8)

    Plumbing Piping, Hook-up & Insulation – MECH-L1

    NA

    NA

    SBB (Lot 8)

    Set Distribution Board HDP-1A – MECH-L1

    NA

    NA

    SBB (Lot 8)

    Hang Drywall – INT-AUD

    NA

    NA

    SBB (Lot 8)

    Tape Walls – ELEC-AUD

    NA

    NA

    SBB (Lot 8)

    Fire Caulk Head of Wall – ELEC-AUD

    NA

    NA

    SBB (Lot 8)

    Prime & 1st Coat of Paint, Walls & Exposed Ceilings – ELEC-AUD

    NA

    NA

    SBB (Lot 8)

    Install Hot/Cold Supply & Return Mech Lines & Seismic – INT-L2

    NA

    NA

    SBB (Lot 8)

    Pressure Test Ductwork– INT-L2

    NA

    NA

    SBB (Lot 8)

    Install O/H Electrical Home Runs – INT-L2

    NA

    NA

    SBB (Lot 8)

    Tape Walls – ELEC-L3

    NA

    NA

    SBB (Lot 8)

    Fire Caulk Head of Wall– ELEC-L3

    NA

    NA

    SBB (Lot 8)

    Fire Tape – INT-L4

    NA

    NA

    SBB (Lot 8)

    Fire Caulk Head of Wall – INT-L4

    NA

    NA

    SBB (Lot 8)

    Install O/H Waste and Vent – INT-L4

    NA

    NA

    SBB (Lot 8)

    Install Insulation and Inspect – ELEC-L4

    NA

    NA

    SBB (Lot 8)

    Hang Drywall and Inspect – ELEC-L4

    NA

    NA

    SBB (Lot 8)

    Tape Walls – ELEC-L4

    NA

    NA

     

    Week of February 26, 2024

    Construction Activities 

     

    Location

    Activity

    Equipment Used

    Anticipated Disturbance

    SBB (Lot 8)

    Electrical Hook-up Equipment

    NA

    NA

    SBB (Lot 8)

    Install PV Panel Secondary Framing - North of E Line

    NA

    NA

    SBB (Lot 8)

    HVAC Piping, Hook-up & Insulation

    NA

    NA

    SBB (Lot 8)

    Flashings / Window Surrounds – EXT-L1

    NA

    NA

    SBB (Lot 8)

    Drainage Layer – EXT-L1

    NA

    NA

    SBB (Lot 8)

    Cement Board – EXT-L1

    NA

    NA

    SBB (Lot 8)

    Rigid Insulation & Air Water Barrier – EXT-NE

    NA

    NA

    SBB (Lot 8)

    Field Measure for Curtain Wall – EXT-NE

    NA

    NA

    SBB (Lot 8)

    Flashings / Window Surrounds – EXT-SW

    NA

    NA

    SBB (Lot 8)

    Drainage Layer – EXT-SW

    NA

    NA

    SBB (Lot 8)

    Install O/H Electrical Home Runs – INT-L1

    NA

    NA

    SBB (Lot 8)

    Install Ductwork Insulation – INT-L1

    NA

    NA

    SBB (Lot 8)

    HVAC Ductwork, Hook-up & Insulation – MECH-L1

    NA

    NA

    SBB (Lot 8)

    Controls Hook-up Equipment – MECH-L1

    NA

    NA

    SBB (Lot 8)

    HVAC Piping, Hook-up & Insulation – MECH-L1

    NA

    NA

    SBB (Lot 8)

    Plumbing Piping, Hook-up & Insulation – MECH-L1

    NA

    NA

    SBB (Lot 8)

    Install Hot/Cold Domestic Water Lines & Seismic – MECH-L1

    NA

    NA

    SBB (Lot 8)

    Tape Walls – MECH-L1

    NA

    NA

    SBB (Lot 8)

    Install O/H Supply & Return Ductwork Branch & Seismic – INT-L2

    NA

    NA

    SBB (Lot 8)

    Install Hot/Cold Domestic Water Lines & Seismic – INT-L3

    NA

    NA

    SBB (Lot 8)

    Install O/H Waste & Vent – INT-L3

    NA

    NA

    SBB (Lot 8)

    Install O/H Mechanical Equipment & Ductwork Mains & Seismic – INT-L3

    NA

    NA

    SBB (Lot 8)

    Tape Walls – ELEC-L3

    NA

    NA

     

    Current and Upcoming Anticipated Closures

    The following shutdown(s)/ closures are anticipated as indicated below. Updates to this schedule will be released weekly in the Project Construction Advisories until the work is complete.  Please contact John Franklin with any specific questions or concerns at john.franklin@ucr.edu.

     

    Description

    Location

    Duration & Date

    Impacted Buildings/ Facilities

    Lot 8

    Lot 8

    Permanently

    Lot 8

    Lot 43

    Lot 43

    Indefinitely

    Lot 43

    Anderson Park

    Anderson Park

    Indefinitely

    Anderson Park

  • 950592 UCR SBB - Construction Alert #65

    Current Week

    Construction Activities

     

    Location

    Activity

    Equipment Used

    Anticipated Disturbance

    SBB (Lot 8)

    Install PV Panel Structural Steel

    Crane

    Noise Due to Equipment

    SBB (Lot 8)

    Erect Stairs – EXT-NE

    NA

    NA

    SBB (Lot 8)

    Install Metal Decking – EXT-SW

    NA

    NA

    SBB (Lot 8)

    Install O/H Supply and Return Ductwork – L1

    NA

    NA

    SBB (Lot 8)

    Install O/H Supply and Return Mech Lines –L1

    NA

    NA

    SBB (Lot 8)

    Pressure Test Ductwork – INT-L1

    NA

    NA

    SBB (Lot 8)

    Tape Walls – ELEC-L1

    NA

    NA

    SBB (Lot 8)

    Fire Caulk Head of Wall – ELEC-L1

    NA

    NA

    SBB (Lot 8)

    Install In-Wall Plumbing – AUD

    NA

    NA

    SBB (Lot 8)

    Install Storm, Overflow, Sewer Lines and Seismic – AUD

    NA

    NA

    SBB (Lot 8)

    Install Mechanical / FSD’s – ELEC-AUD

    NA

    NA

    SBB (Lot 8)

    Install In-Wall Electrical – ELEC-AUD

    NA

    NA

    SBB (Lot 8)

    Install O/H Waste and Vent – INT-L2

    NA

    NA

    SBB (Lot 8)

    Install O/H Supply and Return Ductwork – INT-L2

    NA

    NA

    SBB (Lot 8)

    Tape Walls – ELEC-L2

    NA

    NA

    SBB (Lot 8)

    Fire Caulk Head of Wall – ELEC-L2

    NA

    NA

    SBB (Lot 8)

    Install Early MEP to Support Top Down Drywall - INT-L3

    NA

    NA

    SBB (Lot 8)

    Hang 1st Side Top Down Drywall - INT-L3

    NA

    NA

    SBB (Lot 8)

    Install Insulation & Inspect - INT-L3

    NA

    NA

    SBB (Lot 8)

    Fire Tape - INT-L3

    NA

    NA

    SBB (Lot 8)

    Fire Caulk Head of Wall - INT-L3

    NA

    NA

    SBB (Lot 8)

    Install Mechanical / FSD's – ELEC-L3

    NA

    NA

    SBB (Lot 8)

    Install In-Wall Electrical – ELEC-L3

    NA

    NA

    SBB (Lot 8)

    Frame Interference Walls & Install Door Frames – INT-L4

    NA

    NA

    SBB (Lot 8)

    Install Early MEP to Support Top Down Drywall – INT-L4

    NA

    NA

     

    Week of February 12, 2024

    Construction Activities 

     

    Location

    Activity

    Equipment Used

    Anticipated Disturbance

    SBB (Lot 8)

    Install PV Panel Secondary Framing - South of E Line

    Crane

    Noise Due to Equipment

    SBB (Lot 8)

    Set Mechanical Equipment - Roof

    Crane

    Noise Due to Equipment

    SBB (Lot 8)

    Flashings / Window Surrounds – EXT-L1

    NA

    NA

    SBB (Lot 8)

    Drainage Layer – EXT-L1

    NA

    NA

    SBB (Lot 8)

    Cement Board – EXT-L1

    NA

    NA

    SBB (Lot 8)

    Exterior Framing – East Elevation

    NA

    NA

    SBB (Lot 8)

    F/R/P Stair Treads/Landings – EXT-NE

    NA

    NA

    SBB (Lot 8)

    Exterior Framing - North Elevation – EXT-NE

    NA

    NA

    SBB (Lot 8)

    Rigid Insulation & Air Water Barrier – EXT-NE

    NA

    NA

    SBB (Lot 8)

    Field Measure for Curtain Wall – EXT-NE

    NA

    NA

    SBB (Lot 8)

    Flashings / Window Surrounds – EXT-NE

    NA

    NA

    SBB (Lot 8)

    Erect Steel Structure for Stairs – EXT-SW

    NA

    NA

    SBB (Lot 8)

    Rigid Insulation & Air Water Barrier– EXT-SW

    NA

    NA

    SBB (Lot 8)

    Exterior Framing - South Elevation– EXT-SW

    NA

    NA

    SBB (Lot 8)

    Field Measure for Curtain Wall– EXT-SW

    NA

    NA

    SBB (Lot 8)

    Flashings / Window Surrounds– EXT-SW

    NA

    NA

    SBB (Lot 8)

    Drainage Layer– EXT-SW

    NA

    NA

    SBB (Lot 8)

    Cement Board– EXT-SW

    NA

    NA

    SBB (Lot 8)

    Secondary Air Barrier– EXT-SW

    NA

    NA

    SBB (Lot 8)

    Erect Stairs– EXT-SW

    NA

    NA

    SBB (Lot 8)

    Install O/H Hot/Cold Supply and Return Branch Mech Lines – INT-L1

    NA

    NA

    SBB (Lot 8)

    Install Ductwork Insulation– INT-L1

    NA

    NA

    SBB (Lot 8)

    Pressure Test Hot/Cold Supply & Return Mech Lines– INT-L1

    NA

    NA

    SBB (Lot 8)

    Insulate Test Hot/Cold Supply & Return Mech Lines– INT-L1

    NA

    NA

    SBB (Lot 8)

    HVAC Ductwork, Hook-up & Insulation – MECH-L1

    NA

    NA

    SBB (Lot 8)

    Controls Hook-up Equipment (Incl. Refrigerant Alarm) – MECH-L1

    NA

    NA

    SBB (Lot 8)

    HVAC Piping, Hook-up & Insulation – MECH-L1

    NA

    NA

    SBB (Lot 8)

    Plumbing Piping, Hook-up & Insulation – MECH-L1

    NA

    NA

    SBB (Lot 8)

    Set Distribution Board HDP-1A – MECH-L1

    NA

    NA

    SBB (Lot 8)

    Frame Remaining Walls, Soffits & Hard lids – INT-L1

    NA

    NA

    SBB (Lot 8)

    Install Insulation & Inspect - AUD

    NA

    NA

    SBB (Lot 8)

    Install Backing – ELEC-AUD

    NA

    NA

    SBB (Lot 8)

    Install Insulation & Inspect – ELEC-AUD

    NA

    NA

    SBB (Lot 8)

    Hang Drywall & Inspect – ELEC-AUD

    NA

    NA

    SBB (Lot 8)

    Install Hot/Cold Domestic Water Lines & Seismic – INT-L3

    NA

    NA

    SBB (Lot 8)

    Install O/H Waste & Vent – INT-L3

    NA

    NA

    SBB (Lot 8)

    Install O/H Mechanical Equipment & Ductwork Mains & Seismic – INT-L3

    NA

    NA

    SBB (Lot 8)

    Install Backing – ELEC-L3

    NA

    NA

    SBB (Lot 8)

    Install Insulation & Inspect – ELEC-L3

    NA

    NA

    SBB (Lot 8)

    Hang Drywall and Inspect – ELEC-L3

    NA

    NA

    SBB (Lot 8)

    Hang 1st Side Top Down Drywall – INT-L4

    NA

    NA

    SBB (Lot 8)

    Install Insulation and Inspect – INT-L4

    NA

    NA

    SBB (Lot 8)

    Hang 2nd Side Top Down Drywall & Inspect– INT-L4

    NA

    NA

    SBB (Lot 8)

    Install Mechanical / FSD's – ELEC-L4

    NA

    NA

    SBB (Lot 8)

    Install In-Wall Electrical – ELEC-L4

    NA

    NA

    SBB (Lot 8)

    Install Backing – ELEC-L4

    NA

    NA

     

    Week of February 19, 2024

    Construction Activities 

     

    Location

    Activity

    Equipment Used

    Anticipated Disturbance

    SBB (Lot 8)

    Exterior Framing – East Elevation

    NA

    NA

    SBB (Lot 8)

    F/R/P Stair Treads/Landings – EXT-NE

    NA

    NA

    SBB (Lot 8)

    Exterior Framing - North Elevation – EXT-NE

    NA

    NA

    SBB (Lot 8)

    Rigid Insulation & Air Water Barrier – EXT-NE

    NA

    NA

    SBB (Lot 8)

    Field Measure for Curtain Wall – EXT-NE

    NA

    NA

    SBB (Lot 8)

    Flashings / Window Surrounds – EXT-NE

    NA

    NA

    SBB (Lot 8)

    Erect Steel Structure for Stairs – EXT-SW

    NA

    NA

    SBB (Lot 8)

    Rigid Insulation & Air Water Barrier– EXT-SW

    NA

    NA

    SBB (Lot 8)

    Exterior Framing - South Elevation– EXT-SW

    NA

    NA

    SBB (Lot 8)

    Field Measure for Curtain Wall– EXT-SW

    NA

    NA

    SBB (Lot 8)

    Flashings / Window Surrounds– EXT-SW

    NA

    NA

    SBB (Lot 8)

    Drainage Layer– EXT-SW

    NA

    NA

    SBB (Lot 8)

    Cement Board– EXT-SW

    NA

    NA

    SBB (Lot 8)

    Secondary Air Barrier– EXT-SW

    NA

    NA

    SBB (Lot 8)

    Erect Stairs– EXT-SW

    NA

    NA

    SBB (Lot 8)

    Install Ductwork Insulation– INT-L1

    NA

    NA

    SBB (Lot 8)

    Pressure Test Hot/Cold Supply & Return Mech Lines– INT-L1

    NA

    NA

    SBB (Lot 8)

    Insulate Test Hot/Cold Supply & Return Mech Lines– INT-L1

    NA

    NA

    SBB (Lot 8)

    HVAC Ductwork, Hook-up & Insulation – MECH-L1

    NA

    NA

    SBB (Lot 8)

    Controls Hook-up Equipment (Incl. Refrigerant Alarm) – MECH-L1

    NA

    NA

    SBB (Lot 8)

    HVAC Piping, Hook-up & Insulation – MECH-L1

    NA

    NA

    SBB (Lot 8)

    Plumbing Piping, Hook-up & Insulation – MECH-L1

    NA

    NA

    SBB (Lot 8)

    Set Distribution Board HDP-1A – MECH-L1

    NA

    NA

    SBB (Lot 8)

    Hang Drywall – INT-AUD

    NA

    NA

    SBB (Lot 8)

    Tape Walls – ELEC-AUD

    NA

    NA

    SBB (Lot 8)

    Fire Caulk Head of Wall – ELEC-AUD

    NA

    NA

    SBB (Lot 8)

    Prime & 1st Coat of Paint, Walls & Exposed Ceilings – ELEC-AUD

    NA

    NA

    SBB (Lot 8)

    Install Hot/Cold Supply & Return Mech Lines & Seismic – INT-L2

    NA

    NA

    SBB (Lot 8)

    Pressure Test Ductwork– INT-L2

    NA

    NA

    SBB (Lot 8)

    Install O/H Electrical Home Runs – INT-L2

    NA

    NA

    SBB (Lot 8)

    Tape Walls – ELEC-L3

    NA

    NA

    SBB (Lot 8)

    Fire Caulk Head of Wall– ELEC-L3

    NA

    NA

    SBB (Lot 8)

    Fire Tape – INT-L4

    NA

    NA

    SBB (Lot 8)

    Fire Caulk Head of Wall – INT-L4

    NA

    NA

    SBB (Lot 8)

    Install O/H Waste and Vent – INT-L4

    NA

    NA

    SBB (Lot 8)

    Install Insulation and Inspect – ELEC-L4

    NA

    NA

    SBB (Lot 8)

    Hang Drywall and Inspect – ELEC-L4

    NA

    NA

    SBB (Lot 8)

    Tape Walls – ELEC-L4

    NA

    NA

     

    Current and Upcoming Anticipated Closures

    The following shutdown(s)/ closures are anticipated as indicated below. Updates to this schedule will be released weekly in the Project Construction Advisories until the work is complete.  Please contact John Franklin with any specific questions or concerns at john.franklin@ucr.edu.

     

    Description

    Location

    Duration & Date

    Impacted Buildings/ Facilities

    Lot 8

    Lot 8

    Permanently

    Lot 8

    Lot 43

    Lot 43

    Indefinitely

    Lot 43

    Anderson Park

    Anderson Park

    Indefinitely

    Anderson Park

  • 950592 UCR SBB - Construction Alert #64

    Current Week

    Construction Activities

     

    Location

    Activity

    Equipment Used

    Anticipated Disturbance

    SBB (Lot 8)

    INSTALL PV STRUCTURAL STEEL

    NA

    NA

    SBB (Lot 8)

    PROCURE EXTERIOR FLASHINGS

    NA

    NA

    SBB (Lot 8)

    WEATHER BARRIER – EXT-NE

    NA

    NA

    SBB (Lot 8)

    ERECT STAIR – EXT-NE

    NA

    NA

    SBB (Lot 8) Concrete

    EXTERIOR FRAMING – EXT-NE

    NA

    NA

    SBB (Lot 8)

    INSTALL METAL DECKING – EXT-SW

    NA

    NA

    SBB (Lot 8)

    INSTALL HOT/COLD DOMESTIC WATER LINES AND SEISMIC – INT-L1

    NA

    NA

    SBB (Lot 8)

    INSTALL O/H SUPPLY AND RETURN DUCTWORK BRANCH AND SEISMIC – INT-L1

    NA

    NA

    SBB (Lot 8)

    PRESSURE TEST DUCTOWRK – INT-L1

    NA

    NA

    SBB (Lot 8)

    INSTALL O/H ELECTRICAL HOME RUNS – INT-L1

    NA

    NA

    SBB (Lot 8)

    FIRE CAULKING HEAD OF WALL – ELEC-L1

    NA

    NA

    SBB (Lot 8)

    INSTALL IN-WALL AND BRANCH ELECTRICAL – AUDITORIUM

    NA

    NA

    SBB (Lot 8)

    INSTALL IN-WALL LOW VOLTAGE – AUDITORIUM

    NA

    NA

    SBB (Lot 8)

    INSTALL IN-WALL PLUMBING – AUDITORIUM

    NA

    NA

    SBB (Lot 8)

    INSTALL INSULATION AND INSPECT – AUDITORIUM

    NA

    NA

    SBB (Lot 8)

    INSTALL MECHANICAL / FSD’s – AUDITORIUM

    NA

    NA

    SBB (Lot 8)

    INSTALL O/H WASTE AND VENT – ELEC-L2

    NA

    NA

    SBB (Lot 8)

    HANG DRYWALL AND INSPECT – ELEC-L2

    NA

    NA

    SBB (Lot 8)

    INSTALL INSULATION AND INSPECT – ELECT-L2

    NA

    NA

    SBB (Lot 8)

    TAPE WALLS – ELECT-L2

    NA

    NA

    SBB (Lot 8)

    INSTALL EARLY MEP TO SUPPORT TOP DOWN DRYWALL – INT-L3

    NA

    NA

    SBB (Lot 8)

    HANG 1ST SIDE TOP-DOWN DRYWALL – INT-L3

    NA

    NA

    SBB (Lot 8)

    HANG 2ND SIDE TOP-DOWN DRYWALL AND INSPECT – INT-L3

    NA

    NA

    SBB (Lot 8)

    INSTALL INSULATION AND INSPECT – INT-L3

    NA

    NA

    SBB (Lot 8)

    FIRE TAPE – INT-L3

    NA

    NA

    SBB (Lot 8)

    FIRE CAULKING HEAD OF WALL – INT-L3

    NA

    NA

    SBB (Lot 8)

    INSTALL MECHANICAL / FSD’s – ELEC-L3

    NA

    NA

    SBB (Lot 8)

    INSTALL IN-WALL ELECTRICAL – ELEC-L3

    NA

    NA

    SBB (Lot 8)

    INSTALL BACKING – ELEC-L3

    NA

    NA

    SBB (Lot 8)

    INSTALL EARLY MEP TO SUPPORT TOP-DOWN DRYWALL – INT-L4

    NA

    NA

    SBB (Lot 8)

    HANG 1ST SIDE TOP-DOWN DRYWALL – INT-L4

    NA

    NA

    SBB (Lot 8)

    INSTALL INSULATION AND INSPECT – INT-L4

    NA

    NA

    SBB (Lot 8)

    F/R/P TRANSFORMER YARD SLAB

    Concrete Pump

    Noise due to equipment

     

    Week of February 5, 2024

    Construction Activities 

     

    Location

    Activity

    Equipment Used

    Anticipated Disturbance

    SBB (Lot 8)

    INSTALL ROOFING AT MECHANICAL EQUIPMETN PAD

    NA

    NA

    SBB (Lot 8)

    INSTALL PV PANEL SECONDARY FRAMING

    NA

    NA

    SBB (Lot 8)

    FLASHING / WINDOW SURROUNDS – EXT-L1

    NA

    NA

    SBB (Lot 8)

    DRAINING LAYER – EXT-L1

    NA

    NA

    SBB (Lot 8)

    PRECAST PANELS – EXT-L1

    NA

    NA

    SBB (Lot 8)

    F/R/P TAIR TREAD/LANDINGS – EXT-NE

    NA

    NA

    SBB (Lot 8)

    EXTERIOR FRAMING – NORTH ELEVATION

    NA

    NA

    SBB (Lot 8)

    RIGID INSULATION AND AIR WATER BARRIER – EXT-NE

    NA

    NA

    SBB (Lot 8)

    ERECT STEEL STRUCTURE FOR STAIRS – EXT-SW

    NA

    NA

    SBB (Lot 8)

    INSTALL O/H HOT/COLD SUPPLY AND RETURN BRANCH MECH LINES – INT-L1

    NA

    NA

    SBB (Lot 8)

    INSTALL DUCTWORK INSULATION – INT-L1

    NA

    NA

    SBB (Lot 8)

    PRESSURE TEST HOT/COLD SUPPLY AND RETURN MECH LINES – INT-L1

    NA

    NA

    SBB (Lot 8)

    PRIME AND 1ST COAT OF PAINT, WALLS, AND EXPOSED CEILINGS – ELEC-L1

    NA

    NA

    SBB (Lot 8)

    INSTALL ELECTRICAL GEAR – ELEC-L1

    NA

    NA

    SBB (Lot 8)

    HANG DRYWALL – AUDITORIUM

    NA

    NA

    SBB (Lot 8)

    INSTALL IN-WALL ELECTRICAL – ELEC-AUD

    NA

    NA

    SBB (Lot 8)

    INSTALL BACKING – ELEC-AUD

    NA

    NA

    SBB (Lot 8)

    INSTALL INSULATION AND INSEPCT – ELEC-AUD

    NA

    NA

    SBB (Lot 8)

    HANG DRYWALL AND INSPECT – ELEC-AUD

    NA

    NA

    SBB (Lot 8)

    INSTALL O/H SUPPLY AND RETURN DUCTOWRK BRANCH AND SEISMIC – INT-L2

    NA

    NA

    SBB (Lot 8)

    FIRE CAULKING HEAD OF WALL – ELEC-L2

    NA

    NA

    SBB (Lot 8)

    PRIME AND FIRST COAT OF PAINT WALLS AND EXPOSED CEILINGS – ELEC-L2

    NA

    NA

    SBB (Lot 8)

    INSTALL HOT/COLD DOMESTIC WATER LINES – INT-L3

    NA

    NA

    SBB (Lot 8)

    INSTALL O/H WASTE AND VENT – INT-L3

    NA

    NA

    SBB (Lot 8)

    INSTALL O/H MECH EQUIPMENT AND DUCTWORK MAINS AND SEISMIC – INT-L3

    NA

    NA

    SBB (Lot 8)

    INSTALL INSULATION AND INSPECT – ELEC-L3

    NA

    NA

    SBB (Lot 8)

    HANG DRYWALL AND INSPECT – ELEC-L3

    NA

    NA

    SBB (Lot 8)

    TAPE WALLS – ELEC-L3

    NA

    NA

    SBB (Lot 8)

    HANG 2ND SIDE TOP DOWN DRYWALL AND INSPECT – INT-L4

    NA

    NA

    SBB (Lot 8)

    FIRE TAPE – INT-L4

    NA

    NA

    SBB (Lot 8)

    FIRE CAULKING HEAD OF WALL – INT-L4

    NA

    NA

    SBB (Lot 8)

    INSTALL MECHANICAL / FSD’s – ELEC-L4

    NA

    NA

    SBB (Lot 8)

    ISTALL IN-WALL ELECTRICAL – ELEC-L4

    NA

    NA

    SBB (Lot 8)

    INSTALL BACKING – ELEC-L4

    NA

    NA

     

    Week of February 12, 2024

    Construction Activities 

     

    Location

    Activity

    Equipment Used

    Anticipated Disturbance

    SBB (Lot 8)

    SET MECHANICAL EQUIPMENT – ROOF

    NA

    NA

    SBB (Lot 8)

    ELECTRICAL HOOKUP EQUPMENT – ROOF

    NA

    NA

    SBB (Lot 8)

    INSTALL PV PANEL SECONDARY FRAMING – ROOF

    NA

    NA

    SBB (Lot 8)

    FLASHING / WINDOW SURROUNDS – EXT-L1

    NA

    NA

    SBB (Lot 8)

    DRAINAGE LAYER – EXT-L1

    NA

    NA

    SBB (Lot 8)

    CEMENT BOARD – EXT-L1

    NA

    NA

    SBB (Lot 8)

    ELECRCIAL ROUGH-IN SOFFITS – EXT-L1

    NA

    NA

    SBB (Lot 8)

    SOFFIT SHEATHING – EXT-L1

    NA

    NA

    SBB (Lot 8)

    F/R/P STAIR TREADS / LANDINGS

    NA

    NA

    SBB (Lot 8)

    EXTERIOR FRAMING – NORTH ELECATION – EXT-L1

    NA

    NA

    SBB (Lot 8)

    RIGID INSULATION AND AIR WATER BARRIER – EXT-NE

    NA

    NA

    SBB (Lot 8)

    FIELD MEASURE FOR CURTAIN WALL – EXT-NE

    NA

    NA

    SBB (Lot 8)

    ERRECT STEEL STRUCTURE FOR STAIRS

    NA

    NA

    SBB (Lot 8)

    RIGID INSULATION AND AIR WATER BARRIER – EXT-SW

    NA

    NA

    SBB (Lot 8)

    EXTERIOR FRAMING – SOUTH ELEVATION

    NA

    NA

    SBB (Lot 8)

    FIELD MEASURE FOR CURTAIN WALL

    NA

    NA

    SBB (Lot 8)

    FLASHINGS / WINDOW SURROUNDS – EXT-SW

    NA

    NA

    SBB (Lot 8)

    INSTALL O/H ELECTRICAL HOME RUNS – INT-L1

    NA

    NA

    SBB (Lot 8)

    INSTALL O/H HOT/COLD SUPPLY AND RETURN BRNCH MECH LINES – INT-L1

    NA

    NA

    SBB (Lot 8)

    INSTALL DUCTWORK INSULATION – INT-L1

    NA

    NA

    SBB (Lot 8)

    PRESSURE TEST HOT/COLD SUPPLY AND RETURN MECH LINES – INT-L1

    NA

    NA

    SBB (Lot 8)

    SET MECHANICAL AND PLUMBING EQUIPMENT – MECH-L1

    NA

    NA

    SBB (Lot 8)

    HVAC DUCTWORK, HOOKUP, AND INSULATION – MECH-L1

    NA

    NA

    SBB (Lot 8)

    CONTROLS HOOK-UP EQUIPMENT – MECH-L1

    NA

    NA

    SBB (Lot 8)

    HANG DRYWALL AND INSPECT – ELEC-L3

    NA

    NA

    SBB (Lot 8)

    TAPE WALLS – ELEC-L3

    NA

    NA

    SBB (Lot 8)

    HANG 1ST SIDE TOP DOWN DRYWALL – INT-L4

    NA

    NA

    SBB (Lot 8)

    INSTALL INSULATION AND INSPECT – INT-L4

    NA

    NA

    SBB (Lot 8)

    HANG 2ND SIDE TOP DOWN DRYWALL AND INSPECT – INT-L4

    NA

    NA

    SBB (Lot 8)

    FIRE TAPE – INT-L4

    NA

    NA

    SBB (Lot 8)

    FIRE CAULK HEAD OF WALL – INT-L4

    NA

    NA

    SBB (Lot 8)

    INSTALL IN-WALL ELECTRICAL – ELEC-L4

    NA

    NA

    SBB (Lot 8)

    INSTALL BACKING – ELEC-L4

    NA

    NA

    SBB (Lot 8)

    INSTALL COMMUNICATIONS DUCTBANK AND VAULT FROM MH-14 TO SBB POC

    NA

    NA

     

    Current and Upcoming Anticipated Closures

    The following shutdown(s)/ closures are anticipated as indicated below. Updates to this schedule will be released weekly in the Project Construction Advisories until the work is complete.  Please contact John Franklin with any specific questions or concerns at john.franklin@ucr.edu.

     

    Description

    Location

    Duration & Date

    Impacted Buildings/ Facilities

    Lot 8

    Lot 8

    Permanently

    Lot 8

    Lot 43

    Lot 43

    Indefinitely

    Lot 43

    Anderson Park

    Anderson Park

    Indefinitely

    Anderson Park

  • 950592 UCR SBB - Construction Alert #63

    Current Week

    Construction Activities

     

    Location

    Activity

    Equipment Used

    Anticipated Disturbance

    SBB (Lot 8) 

    INSTALL MECHANICAL DUCT / PIPE SUPPORTS - ROOF

    NA

    NA

    SBB (Lot 8) 

    RIGID INSULATION AND AIR WATER BARRIER – EXT-L1 

    NA

    NA

    SBB (Lot 8)

    FIELD MEASURE FOR CURTAIN WALL – EXT-L1

    NA

    NA

    SBB (Lot 8)

    SOFFIT SHEATHING – EXT-L1

    NA

    NA

    SBB (Lot 8) Concrete

    SET SCAFFOLDS FOR LEVEL TO ROOF – EXT-NE

    NA

    NA

    SBB (Lot 8)

    MISC IN-WALL STEEL FOR CANOPY – EXT-NE

    NA

    NA

    SBB (Lot 8)

    ERECT STEEL STRUCTURE FOR STAIRS – EXT-NE

    NA

    NA

    SBB (Lot 8)

    ERECT SCAFFOLD EAST ELEVATION – EXT-NE

    NA

    NA

    SBB (Lot 8)

    SET SCAFFOLD FOR LEVEL 3 TO ROOF

    NA

    NA

    SBB (Lot 8)

    INSTALL IN-WALL ELECTRICAL – ELEC-L1

    NA

    NA

    SBB (Lot 8)

    INSTALL INSULATION AND ISNEPCT – ELEC-L1

    NA

    NA

    SBB (Lot 8)

    HANG DRYWALL AND ISNTEPCT – ELEC-L1

    NA

    NA

    SBB (Lot 8)

    TAPE WALLS – ELEC-L1

    NA

    NA

    SBB (Lot 8)

    SET MECHANICAL AND PLUMBING EQUIPMENT – MECH-L1

    NA

    NA

    SBB (Lot 8)

    FRAME WALLS – AUDITORIUM

    NA

    NA

    SBB (Lot 8)

    TOP-DOWN DRYWALL AND HEAD OF WALL – AUDITORIUM

    NA

    NA

    SBB (Lot 8) 

    FIRE TAPE – INT-L2

    NA

    NA

    SBB (Lot 8)

    FIRE CAULK HEAD OF WALL – INT-L2

    NA

    NA

    SBB (Lot 8)

    INSTALL HOT/COLD DOMESTIC WATER LINES AND SEISMIC – INT-L2

    NA

    NA

    SBB (Lot 8)

    INSTALL O/H MECHANICAL EQUIPMENT AND DUCTWORK MAINS AND SEISMIC – INT-L2

    NA

    NA

    SBB (Lot 8)

    INSTALL MECHANICAL / FSDs – ELEC-L2

    NA

    NA

    SBB (Lot 8)

    INSTALL BACKING – ELEC-L2

    NA

    NA

    SBB (Lot 8)

    FRAME INTERFERENCE WALLS AND INSTALL DOOR FRAMES – INT-L3

    NA

    NA

    SBB (Lot 8)

    INSTALL FIRE SPRINKLER MAINS, BRANCHES, AND SEISIC – INT-L3

    NA

    NA

    SBB (Lot 8)

    INSTALL STORM, OVERFLOW, SEWER LINES, AND SEISMIC – INT-L3

    NA

    NA

    SBB (Lot 8)

    TRANSFORMER YARD FENCE FOOTING

    NA

    NA

     

    Week of January 29, 2024

    Construction Activities 

     

    Location

    Activity

    Equipment Used

    Anticipated Disturbance

    SBB (Lot 8) 

    INSTALL PV STRUCTURAL STEEL

    NA

    NA

    SBB (Lot 8) 

    PROCURE EXTERIOR FLASHINGS

    NA

    NA

    SBB (Lot 8) 

    WEATHER BARRIER – EXT-NE

    NA

    NA

    SBB (Lot 8)

    ERECT STAIR – EXT-NE

    NA

    NA

    SBB (Lot 8)

    EXTERIOR FRAMING – EXT-NE

    NA

    NA

    SBB (Lot 8) 

    INSTALL METAL DECKING – EXT-SW

    NA

    NA

    SBB (Lot 8)

    INSTALL HOT/COLD DOMESTIC WATER LINES AND SEISMIC – INT-L1

    NA

    NA

    SBB (Lot 8)

    INSTALL O/H SUPPLY AND RETURN DUCTWORK BRANCH AND SEISMIC – INT-L1

    NA

    NA

    SBB (Lot 8)

    PRESSURE TEST DUCTOWRK – INT-L1

    NA

    NA

    SBB (Lot 8)

    INSTALL O/H ELECTRICAL HOME RUNS – INT-L1

    NA

    NA

    SBB (Lot 8)

    FIRE CAULKING HEAD OF WALL – ELEC-L1

    NA

    NA

    SBB (Lot 8)

    INSTALL IN-WALL AND BRANCH ELECTRICAL – AUDITORIUM

    NA

    NA

    SBB (Lot 8)

    INSTALL IN-WALL LOW VOLTAGE – AUDITORIUM

    NA

    NA

    SBB (Lot 8) 

    INSTALL IN-WALL PLUMBING – AUDITORIUM

    NA

    NA

    SBB (Lot 8)

    INSTALL INSULATION AND INSPECT – AUDITORIUM

    NA

    NA

    SBB (Lot 8)

    INSTALL MECHANICAL / FSD’s – AUDITORIUM 

    NA

    NA

    SBB (Lot 8)

    INSTALL O/H WASTE AND VENT – ELEC-L2

    NA

    NA

    SBB (Lot 8)

    HANG DRYWALL AND INSPECT – ELEC-L2

    NA

    NA

    SBB (Lot 8)

    INSTALL INSULATION AND INSPECT – ELECT-L2

    NA

    NA

    SBB (Lot 8)

    TAPE WALLS – ELECT-L2

    NA

    NA

    SBB (Lot 8)

    INSTALL EARLY MEP TO SUPPORT TOP DOWN DRYWALL – INT-L3

    NA

    NA

    SBB (Lot 8)

    HANG 1ST SIDE TOP-DOWN DRYWALL – INT-L3

    NA

    NA

    SBB (Lot 8)

    HANG 2ND SIDE TOP-DOWN DRYWALL AND INSPECT – INT-L3

    NA

    NA

    SBB (Lot 8)

    INSTALL INSULATION AND INSPECT – INT-L3

    NA

    NA

    SBB (Lot 8)

    FIRE TAPE – INT-L3

    NA

    NA

    SBB (Lot 8)

    FIRE CAULKING HEAD OF WALL – INT-L3

    NA

    NA

    SBB (Lot 8)

    INSTALL MECHANICAL / FSD’s – ELEC-L3

    NA

    NA

    SBB (Lot 8)

    INSTALL IN-WALL ELECTRICAL – ELEC-L3

    NA

    NA

    SBB (Lot 8)

    INSTALL BACKING – ELEC-L3

    NA

    NA

    SBB (Lot 8)

    INSTALL EARLY MEP TO SUPPORT TOP-DOWN DRYWALL – INT-L4

    NA

    NA

    SBB (Lot 8)

    HANG 1ST SIDE TOP-DOWN DRYWALL – INT-L4

    NA

    NA

    SBB (Lot 8)

    INSTALL INSULATION AND INSPECT – INT-L4

    NA

    NA

    SBB (Lot 8)

    F/R/P TRANSFORMER YARD SLAB

    NA

    NA

     

    Week of February 5, 2024

    Construction Activities 

     

    Location

    Activity

    Equipment Used

    Anticipated Disturbance

    SBB (Lot 8) 

    INSTALL ROOFING AT MECHANICAL EQUIPMETN PAD 

    NA

    NA

    SBB (Lot 8) 

    INSTALL PV PANEL SECONDARY FRAMING

    NA

    NA

    SBB (Lot 8) 

    FLASHING / WINDOW SURROUNDS – EXT-L1

    NA

    NA

    SBB (Lot 8)

    DRAINING LAYER – EXT-L1

    NA

    NA

    SBB (Lot 8)

    PRECAST PANELS – EXT-L1

    NA

    NA

    SBB (Lot 8) 

    F/R/P TAIR TREAD/LANDINGS – EXT-NE

    NA

    NA

    SBB (Lot 8)

    EXTERIOR FRAMING – NORTH ELEVATION 

    NA

    NA

    SBB (Lot 8)

    RIGID INSULATION AND AIR WATER BARRIER – EXT-NE

    NA

    NA

    SBB (Lot 8)

    ERECT STEEL STRUCTURE FOR STAIRS – EXT-SW

    NA

    NA

    SBB (Lot 8)

    INSTALL O/H HOT/COLD SUPPLY AND RETURN BRANCH MECH LINES – INT-L1

    NA

    NA

    SBB (Lot 8)

    INSTALL DUCTWORK INSULATION – INT-L1

    NA

    NA

    SBB (Lot 8)

    PRESSURE TEST HOT/COLD SUPPLY AND RETURN MECH LINES – INT-L1

    NA

    NA

    SBB (Lot 8)

    PRIME AND 1ST COAT OF PAINT, WALLS, AND EXPOSED CEILINGS – ELEC-L1

    NA

    NA

    SBB (Lot 8) 

    INSTALL ELECTRICAL GEAR – ELEC-L1

    NA

    NA

    SBB (Lot 8)

    HANG DRYWALL – AUDITORIUM

    NA

    NA

    SBB (Lot 8)

    INSTALL IN-WALL ELECTRICAL – ELEC-AUD

    NA

    NA

    SBB (Lot 8)

    INSTALL BACKING – ELEC-AUD

    NA

    NA

    SBB (Lot 8)

    INSTALL INSULATION AND INSEPCT – ELEC-AUD

    NA

    NA

    SBB (Lot 8)

    HANG DRYWALL AND INSPECT – ELEC-AUD

    NA

    NA

    SBB (Lot 8)

    INSTALL O/H SUPPLY AND RETURN DUCTOWRK BRANCH AND SEISMIC – INT-L2

    NA

    NA

    SBB (Lot 8)

    FIRE CAULKING HEAD OF WALL – ELEC-L2

    NA

    NA

    SBB (Lot 8)

    PRIME AND FIRST COAT OF PAINT WALLS AND EXPOSED CEILINGS – ELEC-L2

    NA

    NA

    SBB (Lot 8)

    INSTALL HOT/COLD DOMESTIC WATER LINES – INT-L3

    NA

    NA

    SBB (Lot 8)

    INSTALL O/H WASTE AND VENT – INT-L3

    NA

    NA

    SBB (Lot 8)

    INSTALL O/H MECH EQUIPMENT AND DUCTWORK MAINS AND SEISMIC – INT-L3

    NA

    NA

    SBB (Lot 8)

    INSTALL INSULATION AND INSPECT – ELEC-L3

    NA

    NA

    SBB (Lot 8)

    HANG DRYWALL AND INSPECT – ELEC-L3

    NA

    NA

    SBB (Lot 8)

    TAPE WALLS – ELEC-L3

    NA

    NA

    SBB (Lot 8)

    HANG 2ND SIDE TOP DOWN DRYWALL AND INSPECT – INT-L4

    NA

    NA

    SBB (Lot 8)

    FIRE TAPE – INT-L4

    NA

    NA

    SBB (Lot 8)

    FIRE CAULKING HEAD OF WALL – INT-L4

    NA

    NA

    SBB (Lot 8)

    INSTALL MECHANICAL / FSD’s – ELEC-L4

    NA

    NA

    SBB (Lot 8)

    ISTALL IN-WALL ELECTRICAL – ELEC-L4

    NA

    NA

    SBB (Lot 8)

    INSTALL BACKING – ELEC-L4

    NA

    NA

     

    Current and Upcoming Anticipated Closures

    The following shutdown(s)/ closures are anticipated as indicated below. Updates to this schedule will be released weekly in the Project Construction Advisories until the work is complete.  Please contact John Franklin with any specific questions or concerns at john.franklin@ucr.edu.

     

    Description

    Location

    Duration & Date

    Impacted Buildings/ Facilities

    Lot 8

    Lot 8

    Permanently 

    Lot 8

    Lot 43

    Lot 43

    Indefinitely 

    Lot 43

    Anderson Park

    Anderson Park

    Indefinitely

    Anderson Park

  • 950592 UCR SBB - Construction Alert #62

    Current Week

    Construction Activities

     

    Location

    Activity

    Equipment Used

    Anticipated Disturbance

    SBB (Lot 8) Concrete

    F/R/P Walls at Transformer Yard

    Crane and Concrete Pump

    Noise due to equipment

    SBB (Lot 8) Concrete

    F/R/P Transformer Yard Slab

    Crane and Concrete Pump

    Noise due to equipment

    SBB (Lot 8)

    Vapor Retarder Sheet Air Barrier

    NA

    NA

    SBB (Lot 8)

    Flashing / Window Surrounds – Ext-L1

    NA

    NA

    SBB (Lot 8)

    Install Temp Roofing Low Roofs – Ext NE

    NA

    NA

    SBB (Lot 8)

    Erect Steel Structure for Stairs – Ext NE

    NA

    NA

    SBB (Lot 8)

    Set Scaffold to Roof – Ext NE

    NA

    NA

    SBB (Lot 8)

    Misc In-Wall Steel for Canopy – Ext NE

    NA

    NA

    SBB (Lot 8)

    Install Temp Roofing at Low Roofs– Ext SW

    NA

    NA

    SBB (Lot 8) Concrete

    Pour Grand Stair – Int-L1

    Concrete Pump

    Noise due to equipment

    SBB (Lot 8) Concrete

    Strip Grand Stair – Int-L1

    NA

    NA

    SBB (Lot 8)

    Install O/H Mechanical Equipment and Ductwork Mains and Seismic – Int-L1

    NA

    NA

    SBB (Lot 8)

    Install In-Wall Electrical – Int-L1

    NA

    NA

    SBB (Lot 8)

    Install Backing – Int-L1

    NA

    NA

    SBB (Lot 8)

    Layout Framing and Install Top Track – Int-Auditorium

    NA

    NA

    SBB (Lot 8)

    Hang 2nd Side Top Down Drywall and Inspect – Int-L2

    NA

    NA

    SBB (Lot 8)

    Fire Tape – Int-L2

    NA

    NA

    SBB (Lot 8)

    Fire Caulking Head of Wall – Int-L2

    NA

    NA

    SBB (Lot 8)

    Frame Interference Walls and Install Door Frames – Int-L3

    NA

    NA

    SBB (Lot 8)

    Concrete

    Pour CIP Stair to L4

    Concrete Pump

    Noise due to equipment

    SBB (Lot 8)

    Concrete

    Strip CIP Stair to L4

    NA

    NA

    SBB (Lot 8)

    Install Storm, Overflow, Sewer Lines and Seismic – Int-L4

    NA

    NA

     

    Week of January 22, 2023

    Construction Activities 

     

    Location

    Activity

    Equipment Used

    Anticipated Disturbance

    SBB (Lot 8)

    Install Roofing at mechanical Equipment Pad

    NA

    NA

    SBB (Lot 8)

    Drainage Layer – Ext-L1

    NA

    NA

    SBB (Lot 8)

    Cement Board – Ext-L1

    NA

    NA

    SBB (Lot 8)

    Weather Barrier – Ext-L1

    NA

    NA

    SBB (Lot 8) Concrete

    Erect Stairs – Ext-NE

    NA

    NA

    SBB (Lot 8)

    Exterior Framing – Ext-NE

    NA

    NA

    SBB (Lot 8)

    Erect Tube Steel Structure – Ext-SW

    NA

    NA

    SBB (Lot 8)

    Set Scaffold for Level 3 to Roof – Ext-SW

    NA

    NA

    SBB (Lot 8)

    Install Metal Decking – Ext-SW

    NA

    NA

    SBB (Lot 8)

    Install O/H Supply and Return Ductwork Branch and Seismic – Int-L1

    NA

    NA

    SBB (Lot 8)

    Install Hot and Cold Supply and Return Mech Lunes and Seismic – Int-L1

    NA

    NA

    SBB (Lot 8)

    Install Insulation and Inspect – Elec-L1

    NA

    NA

    SBB (Lot 8)

    Hang Drywall and Inspect – Elec-L1

    NA

    NA

    SBB (Lot 8)

    Tape Walls – Elec-L1

    NA

    NA

    SBB (Lot 8)

    Frame Walls – Int-Auditorium

    NA

    NA

    SBB (Lot 8)

    Install O/H Waste and Vent – Int-L2

    NA

    NA

    SBB (Lot 8)

    Install O/H Mechanical Equipment and Ductwork Mains and Seismic – Int-L2

    NA

    NA

    SBB (Lot 8)

    Install Mechanical / FSD’s – Elec-L2

    NA

    NA

    SBB (Lot 8)

    Install Early MEP to support Top Down Drywall – Int-L3

    NA

    NA

    SBB (Lot 8)

    Hang 1st Side Top Down Drywall – Int-L3

    NA

    NA

    SBB (Lot 8)

    Install Insulation and Inspect – Int-L3

    NA

    NA

    SBB (Lot 8)

    Hang 2nd Side Top Down Drywall and Inspect – Int-L3

    NA

    NA

    SBB (Lot 8)

    Layout Framing and Install Top Track – Second Pass – Int-L3

    NA

    NA

    SBB (Lot 8)

    Frame Interference Walls and Install Door Frames – Second Pass – Int-L3

    NA

    NA

    SBB (Lot 8)

    Install Fire Sprinkler Mains, Branches and Seismic – Int-L3

    NA

    NA

    SBB (Lot 8)

    Install Storm, Overflow, Sewer Lines and Seismic – Int-L3

    NA

    NA

    SBB (Lot 8)

    Layout Framing and Install Top Track – Int-L4

    NA

    NA

     

    Week of January 29, 2023

    Construction Activities 

     

    Location

    Activity

    Equipment Used

    Anticipated Disturbance

    SBB (Lot 8)

    Drainage Layer – EXT-L1

    NA

    NA

    SBB (Lot 8)

    Cement Board – EXT-L1

    NA

    NA

    SBB (Lot 8)

    Secondary Air Barrier – EXT-L1

    NA

    NA

    SBB (Lot 8)

    Precast Panels – EXT-L1

    NA

    NA

    SBB (Lot 8)

    Exterior Framing – West Elevation

    NA

    NA

    SBB (Lot 8)

    Install Hot/Cold Supply and Return Mech Lines and Seismic

    NA

    NA

    SBB (Lot 8)

    Tape Walls – Elec-L1

    NA

    NA

    SBB (Lot 8)

    Install O/H Supply and Return Ductwork – INT-L1

     

     

    SBB (Lot 8)

    Install Hot/Cold Domestic Water Lines and Seismic – INT-L2

    NA

    NA

    SBB (Lot 8)

    Install Fire Sprinkler Mains branches and Seismic – INT-L4

    NA

    NA

    SBB (Lot 8)

    Install in-wall and branch electrical – Auditorium

    NA

    NA

    SBB (Lot 8)

    Install In-wall Low Voltage – Auditorium

    NA

    NA

    SBB (Lot 8)

    Install Storm overflow, sewer lines, and seismic – INT-L3

    NA

    NA

     

     

    Current and Upcoming Anticipated Closures

    The following shutdown(s)/ closures are anticipated as indicated below. Updates to this schedule will be released weekly in the Project Construction Advisories until the work is complete.  Please contact John Franklin with any specific questions or concerns at john.franklin@ucr.edu.

     

    Description

    Location

    Duration & Date

    Impacted Buildings/ Facilities

    Lot 8

    Lot 8

    Permanently

    Lot 8

    Lot 43

    Lot 43

    Indefinitely

    Lot 43

    Anderson Park

    Anderson Park

    Indefinitely

    Anderson Park

  • 950592 UCR SBB - Construction Alert #61

    Current Week

    Construction Activities

     

    Location

    Activity

    Equipment Used

    Anticipated Disturbance

    SBB (Lot 8) Concrete

    Cure Deck for Moisture Testing

    NA

    NA

    SBB (Lot 8) Concrete

    MEP Stub-up Penetrations

    NA

    NA

    SBB (Lot 8)

    Install Mechanical Duct Pipe Supports

    NA

    NA

    SBB (Lot 8)

    Install Roof Drains

    NA

    NA

    SBB (Lot 8)

    Soffit Framing – Ext-L1

    NA

    NA

    SBB (Lot 8)

    Rigid Insulation and Air water barrier – Ext-L1

    NA

    NA

    SBB (Lot 8)

    Electrical Rough-in Soffits – Ext-L1

    NA

    NA

    SBB (Lot 8)

    Soffit Sheathing – Ext-L1

    NA

    NA

    SBB (Lot 8) Concrete

    Rebar Grand Stair – Int-L1

    NA

    NA

    SBB (Lot 8)

    Install O/H waste and vent – Int-L1

    NA

    NA

    SBB (Lot 8)

    Install Mechanical / FSDs – Elec-L1

    NA

    NA

    SBB (Lot 8)

    Hang 1st Side Top Down Drywall – Int-L2

    NA

    NA

    SBB (Lot 8)

    Install Insulation and Inspect – Int-L2

    NA

    NA

    SBB (Lot 8)

    Install Fire Sprinkler Mains, Branch and Seismic – Int-L2

    NA

    NA

    SBB (Lot 8) Concrete

    Rebar CIP Stair to L4

    NA

    NA

    SBB (Lot 8)

    Install Fire Water – College Place to SBB POC

    NA

    NA

    SBB (Lot 8) Concrete

    F/R/P Walls at Transformer Yard

    Crane and Concrete Pump

    Noise due to equipment

    SBB (Lot 8) Concrete

    F/R/P Transformer Yard Slab

    Crane and Concrete Pump

    Noise due to equipment

     

    Week of January 15, 2023

    Construction Activities 

     

    Location

    Activity

    Equipment Used

    Anticipated Disturbance

    SBB (Lot 8) Concrete

    F/R/P Walls at Transformer Yard

    Crane and Concrete Pump

    Noise due to equipment

    SBB (Lot 8) Concrete

    F/R/P Transformer Yard Slab

    Crane and Concrete Pump

    Noise due to equipment

    SBB (Lot 8)

    Vapor Retarder Sheet Air Barrier

    NA

    NA

    SBB (Lot 8)

    Flashing / Window Surrounds – Ext-L1

    NA

    NA

    SBB (Lot 8)

    Install Temp Roofing Low Roofs – Ext NE

    NA

    NA

    SBB (Lot 8)

    Erect Steel Structure for Stairs – Ext NE

    NA

    NA

    SBB (Lot 8)

    Set Scaffold to Roof – Ext NE

    NA

    NA

    SBB (Lot 8)

    Misc In-Wall Steel for Canopy – Ext NE

    NA

    NA

    SBB (Lot 8)

    Install Temp Roofing at Low Roofs– Ext SW

    NA

    NA

    SBB (Lot 8) Concrete

    Pour Grand Stair – Int-L1

    Concrete Pump

    Noise due to equipment

    SBB (Lot 8) Concrete

    Strip Grand Stair – Int-L1

    NA

    NA

    SBB (Lot 8)

    Install O/H Mechanical Equipment and Ductwork Mains and Seismic – Int-L1

    NA

    NA

    SBB (Lot 8)

    Install In-Wall Electrical – Int-L1

    NA

    NA

    SBB (Lot 8)

    Install Backing – Int-L1

    NA

    NA

    SBB (Lot 8)

    Layout Framing and Install Top Track – Int-Auditorium

    NA

    NA

    SBB (Lot 8)

    Hang 2nd Side Top Down Drywall and Inspect – Int-L2

    NA

    NA

    SBB (Lot 8)

    Fire Tape – Int-L2

    NA

    NA

    SBB (Lot 8)

    Fire Caulking Head of Wall – Int-L2

    NA

    NA

    SBB (Lot 8)

    Frame Interference Walls and Install Door Frames – Int-L3

    NA

    NA

    SBB (Lot 8)

    Concrete

    Pour CIP Stair to L4

    Concrete Pump

    Noise due to equipment

    SBB (Lot 8)

    Concrete

    Strip CIP Stair to L4

    NA

    NA

    SBB (Lot 8)

    Install Storm, Overflow, Sewer Lines and Seismic – Int-L4

    NA

    NA

     

    Week of January 22, 2023

    Construction Activities 

     

    Location

    Activity

    Equipment Used

    Anticipated Disturbance

    SBB (Lot 8)

    Install Roofing at mechanical Equipment Pad

    NA

    NA

    SBB (Lot 8)

    Drainage Layer – Ext-L1

    NA

    NA

    SBB (Lot 8)

    Cement Board – Ext-L1

    NA

    NA

    SBB (Lot 8)

    Weather Barrier – Ext-L1

    NA

    NA

    SBB (Lot 8) Concrete

    Erect Stairs – Ext-NE

    NA

    NA

    SBB (Lot 8)

    Exterior Framing – Ext-NE

    NA

    NA

    SBB (Lot 8)

    Erect Tube Steel Structure – Ext-SW

    NA

    NA

    SBB (Lot 8)

    Set Scaffold for Level 3 to Roof – Ext-SW

    NA

    NA

    SBB (Lot 8)

    Install Metal Decking – Ext-SW

    NA

    NA

    SBB (Lot 8)

    Install O/H Supply and Return Ductwork Branch and Seismic – Int-L1

    NA

    NA

    SBB (Lot 8)

    Install Hot and Cold Supply and Return Mech Lunes and Seismic – Int-L1

    NA

    NA

    SBB (Lot 8)

    Install Insulation and Inspect – Elec-L1

    NA

    NA

    SBB (Lot 8)

    Hang Drywall and Inspect – Elec-L1

    NA

    NA

    SBB (Lot 8)

    Tape Walls – Elec-L1

    NA

    NA

    SBB (Lot 8)

    Frame Walls – Int-Auditorium

    NA

    NA

    SBB (Lot 8)

    Install O/H Waste and Vent – Int-L2

    NA

    NA

    SBB (Lot 8)

    Install O/H Mechanical Equipment and Ductwork Mains and Seismic – Int-L2

    NA

    NA

    SBB (Lot 8)

    Install Mechanical / FSD’s – Elec-L2

    NA

    NA

    SBB (Lot 8)

    Install Early MEP to support Top Down Drywall – Int-L3

    NA

    NA

    SBB (Lot 8)

    Hang 1st Side Top Down Drywall – Int-L3

    NA

    NA

    SBB (Lot 8)

    Install Insulation and Inspect – Int-L3

    NA

    NA

    SBB (Lot 8)

    Hang 2nd Side Top Down Drywall and Inspect – Int-L3

    NA

    NA

    SBB (Lot 8)

    Layout Framing and Install Top Track – Second Pass – Int-L3

    NA

    NA

    SBB (Lot 8)

    Frame Interference Walls and Install Door Frames – Second Pass – Int-L3

    NA

    NA

    SBB (Lot 8)

    Install Fire Sprinkler Mains, Branches and Seismic – Int-L3

    NA

    NA

    SBB (Lot 8)

    Install Storm, Overflow, Sewer Lines and Seismic – Int-L3

    NA

    NA

    SBB (Lot 8)

    Layout Framing and Install Top Track – Int-L4

    NA

    NA

     

    Current and Upcoming Anticipated Closures

    The following shutdown(s)/ closures are anticipated as indicated below. Updates to this schedule will be released weekly in the Project Construction Advisories until the work is complete.  Please contact John Franklin with any specific questions or concerns at john.franklin@ucr.edu.

     

    Description

    Location

    Duration & Date

    Impacted Buildings/ Facilities

    Lot 8

    Lot 8

    Permanently

    Lot 8

    Lot 43

    Lot 43

    Indefinitely

    Lot 43

    Anderson Park

    Anderson Park

    Indefinitely

    Anderson Park

  • 950592 UCR SBB - Construction Alert #60

    Current Week

    Construction Activities

     

    Location

    Activity

    Equipment Used

    Anticipated Disturbance

    SBB (Lot 8) Concrete

    Underslab Electrical Rough-in - Auditorium Steps

    NA

    NA

    SBB (Lot 8) Concrete

    Form Steps - Auditorium

    NA

    NA

    SBB (Lot 8)

    QC / Inspection – Auditorium

    NA

    NA

    SBB (Lot 8)

    Strip and Haul Off Form system

    Crane

    Noise due to Equipment

    SBB (Lot 8)

    Install Roofing at Mechanical Equipment Pad

    NA

    NA

    SBB (Lot 8)

    Install Mechanical Duct Pipe Supports – Roof

    NA

    NA

    SBB (Lot 8)

    Set Scaffold to Roof

    NA

    NA

    SBB (Lot 8)

    Install Temp Roofing at Low Roof

    NA

    NA

    SBB (Lot 8)

    Set Scaffold for level 2

    NA

    NA

    SBB (Lot 8)

    Erect Tube Steel Structure

    Crane

    Noise due to Equipment

    SBB (Lot 8)

    Form Grand Stair

    NA

    NA

    SBB (Lot 8)

    Install Mechanical / FSD’s – Electrical/BDF Room

    NA

    NA

    SBB (Lot 8)

    Install In-Wall Electrical – Electrical/BDF Room

    NA

    NA

    SBB (Lot 8)

    Hang 1st Side Top Down Drywall – INT-L2

    NA

    NA

    SBB (Lot 8)

    Install Insulation & Inspect -INT-L2

    NA

    NA

    SBB (Lot 8)

    Layout Framing and Install Top Track

    NA

    NA

    SBB (Lot 8) Concrete

    F/R/P Walls at Transformer Yard Slab

    Concrete Pump

    Noise due to Equipment

    SBB (Lot 8) Concrete

    F/R/P Transformer Yard Slab

    Concrete Pump

    Noise due to Equipment

    SBB (Lot 8)

    Drainage Layer – EXT-L1

    NA

    NA

     

    Week of January 8, 2023

    Construction Activities 

     

    Location

    Activity

    Equipment Used

    Anticipated Disturbance

    SBB (Lot 8) Concrete

    Pour Steps Auditorium

    Concrete Pump

    Noise due to Equipment

    SBB (Lot 8) Concrete

    Strip Edge Form / Bulkhead – Auditorium Steps

    NA

    NA

    SBB (Lot 8)

    Install Roofing Mechanical Equipment Pad

    NA

    NA

    SBB (Lot 8)

    Install Mechanical Duct / Pipe Supports - Roof

    Crane

    Noise due to Equipment

    SBB (Lot 8)

    MEP Stub-up Penetration - Roof

    NA

    NA

    SBB (Lot 8)

    Drainage Layer – EXT-L1

    NA

    NA

    SBB (Lot 8)

    Cement Board – EXT-L1

    NA

    NA

    SBB (Lot 8)

    Secondary Air Barrier – EXT-L1

    NA

    NA

    SBB (Lot 8)

    Electrical Rough-in Soffits – EXT-L1

    NA

    NA

    SBB (Lot 8)

    Soffit Sheathing – EXT-L1

    NA

    NA

    SBB (Lot 8)

    Misc In-Wall Steel for canopy-EXT-NE

    NA

    NA

    SBB (Lot 8)

    Exterior Framing – East Elevation L1

    NA

    NA

    SBB (Lot 8)

    Erect Stairs – EXT-NE

    NA

    NA

    SBB (Lot 8)

    Install Temp Roofing

    NA

    NA

    SBB (Lot 8)

    Erect Tube Steel Structure-EXT SW

    NA

    NA

    SBB (Lot 8)

    Install Metal Decking – EXT SW

    NA

    NA

    SBB (Lot 8) Concrete

    Pour Grand Stair – INT-L1

    Concrete Pump

    Noise due to Equipment

    SBB (Lot 8)

    Install O/H Waste and Vent – INT-L1

    NA

    NA

    SBB (Lot 8)

    Install Hot/Cold Domestic Water Lines and Seismic – INT-L1

    NA

    NA

    SBB (Lot 8)

    Install O/H Mechanical Equipment and Ductwork Mains and Seismic – INT-L1

    NA

    NA

    SBB (Lot 8)

    Install In-Wall Electrical – Elec-L1

    NA

    NA

    SBB (Lot 8)

    Install Backing – Elec-L1

    NA

    NA

    SBB (Lot 8)

    Install Insulation and Inspect – Elect-L1

    NA

    NA

    SBB (Lot 8)

    Layout Framing and Install Top Track – Auditorium

    NA

    NA

    SBB (Lot 8)

    Fire Tape – INT-L2

    NA

    NA

    SBB (Lot 8)

    Fire Caulk Head of Wall – INT-L2

    NA

    NA

    SBB (Lot 8)

    Frame Interference Walls and Install Door Framed – INT-L3

    NA

    NA

    SBB (Lot 8)

    Install Early MEP to Support Top Down Drywall – INT-L3

    NA

    NA

    Anderson Park

    Rough Grade / Cut Curbs – Anderson Park

    Loader

    Noise due to Equipment

     

    Week of January 15, 2023

    Construction Activities 

     

    Location

    Activity

    Equipment Used

    Anticipated Disturbance

    SBB (Lot 8)

    Install Roof Drains

    NA

    NA

    SBB (Lot 8)

    Set Mechanical Equipment

    NA

    NA

    SBB (Lot 8)

    Moisture Test Concrete Deck

    NA

    NA

    SBB (Lot 8)

    Secondary Air Barrier – EXT-L1

     

     

    SBB (Lot 8)

    Soffit Sheathing – EXT-L1

    NA

    NA

    SBB (Lot 8)

    F/R/P Stair Treads/Landings

    NA

    NA

    SBB (Lot 8)

    Rigid Insulation and Air Water Barrier – EXT NW

    NA

    NA

    SBB (Lot 8)

    Exterior Framing – EXT NW

    NA

    NA

    SBB (Lot 8)

    Erect Steel Structure for Stairs-EXT SW

    NA

    NA

    SBB (Lot 8)

    Install O/H Supply & Return Ductwork Branch & Seismic – INT-L1

    NA

    NA

    SBB (Lot 8)

    Hang Drywall and Inspect – Elec/BDF L1

    NA

    NA

    SBB (Lot 8)

    Tape Walls – Elec/BDF L1

    NA

    NA

    SBB (Lot 8)

    Frame Walls – INT Auditorium

    NA

    NA

    SBB (Lot 8)

    Install O/H Mechanical Equipment and Ductwork - INT-L2

    NA

    NA

    SBB (Lot 8)

    Install In-Wall Electrical – Elec L2

    NA

    NA

    SBB (Lot 8)

    Hang 1st Side Top Down Drywall – INT-L3

    NA

    NA

    SBB (Lot 8)

    Install Insulation and Inspect – INT-L3

     

     

    SBB (Lot 8)

    Hang 2nd Side Top Down Drywall and Inspect – INT-L3

    NA

    NA

    SBB (Lot 8)

    Fire Tape – INT-L3

    NA

    NA

    SBB (Lot 8)

    Layout Framing and Install Top Track – INT-L4

    NA

    NA

    SBB (Lot 8)

    Frame Interference Walls and Install Foor Frames

    NA

    NA

    SBB (Lot 8)

    Install Early MEP to Support Top Down Drywall

    NA

    NA

    SBB (Lot 8)

    Install Communications Ductbank and Vault from MH-14 to SBB POC

    NA

    NA

     

    Current and Upcoming Anticipated Closures

    The following shutdown(s)/ closures are anticipated as indicated below. Updates to this schedule will be released weekly in the Project Construction Advisories until the work is complete.  Please contact John Franklin with any specific questions or concerns at john.franklin@ucr.edu.

     

    Description

    Location

    Duration & Date

    Impacted Buildings/ Facilities

    Lot 8

    Lot 8

    Permanently

    Lot 8

    Lot 43

    Lot 43

    Indefinitely

    Lot 43

    Anderson Park

    Anderson Park

    Indefinitely

    Anderson Park

  • 950592 UCR SBB - Construction Alert #58

    Current Week

    Construction Activities

     

    Location

    Activity

    Equipment Used

    Anticipated Disturbance

    SBB (Lot 8)

    F/R/P Transformer Yard Footings

    NA

    NA

    SBB (Lot 8) Concrete

    Pour – Deck L5

    Concrete Pump

    Noise due to Equipment

    SBB (Lot 8) Concrete

    Strip Edge Form and Transfer Beams – Deck L5

    NA

    NA

    SBB (Lot 8) Concrete

    Cure for Stress – Deck L5

    NA

    NA

    SBB (Lot 8) Concrete

    Stress Transfer Beams – Deck L5

    NA

    NA

    SBB (Lot 8) Concrete

    One Side Form Walls and Columns – Vert L5

    NA

    NA

    SBB (Lot 8) Concrete

    Rebar – Vert L5

    Crane

    Noise due to Equipment

    SBB (Lot 8) Concrete

    Layout and Install MEPs – Vert L5

    NA

    NA

    SBB (Lot 8) Concrete

    Set Embeds – Vert L5

    NA

    NA

    SBB (Lot 8) Concrete

    QC / Inspection – Vert L5

    NA

    NA

    SBB (Lot 8) Concrete

    F/R/P Equipment Pads

    Concrete Pump

    Noise due to Equipment

    SBB (Lot 8) Concrete

    Roof Davits

    NA

    NA

    SBB (Lot 8)

    Soffit Framing – EXT L1

    NA

    NA

    SBB (Lot 8)

    Rigid Insulation and Air Water Barrier – EXT L1

    NA

    NA

    SBB (Lot 8)

    Electrical Rough-in Soffits – EXT L1

    NA

    NA

    SBB (Lot 8)

    Fire Sprinkler Rough-in Soffits – EXT L1

    NA

    NA

    SBB (Lot 8)

    Plumbing Rough-in Soffits – EXT L1

    NA

    NA

    SBB (Lot 8)

    Hang 2nd Side Top-Down Drywall and Inspect – INT L1

    NA

    NA

    SBB (Lot 8)

    Fire Tape – INT L1

    NA

    NA

    SBB (Lot 8)

    Fire Caulk Head of Wall– INT L1

    NA

    NA

    SBB (Lot 8)

    Install Elevator Guide Rail Support Steel – Level 3

    NA

    NA

    SBB (Lot 8)

    Concrete

    F/R/P Walls at Transformer Yard

    Concrete Pump

    Noise due to Equipment

     

    Week of December 25, 2023

    Construction Activities 

     

    Location

    Activity

    Equipment Used

    Anticipated Disturbance

    SBB (Lot 8) Concrete

    Edge Form / Bulkhead SOG North – Auditorium Steps

    NA

    NA

    SBB (Lot 8) Concrete

    Rebar – Auditorium Steps

    NA

    NA

    SBB (Lot 8) Concrete

    Underslab Electrical Rough-in - Auditorium Steps

    NA

    NA

    SBB (Lot 8) Concrete

    Form Steps - Auditorium

    NA

    NA

    SBB (Lot 8) Concrete

    Close Two Side Forms – Vert L5

    NA

    NA

    SBB (Lot 8) Concrete

    Pour – Vert L5

    Concrete Pump

    Noise due to Equipment

    SBB (Lot 8) Concrete

    Strip Walls and columns – Vert L5

    NA

    NA

    SBB (Lot 8) Concrete

    Cure for Steel Erection – Vert L5

    NA

    NA

    SBB (Lot 8) Concrete

    Strip and Haul off Form System – Deck L5

    Crane

    Noise due to Equipment

    SBB (Lot 8)

    Install Roof Drains

    NA

    NA

    SBB (Lot 8)

    Soffit Framing – EXT L1

    NA

    NA

    SBB (Lot 8)

    Flashing and Window Surrounds-EXT L1

    NA

    NA

    SBB (Lot 8)

    Rigid Insulation and Air Water Barrier – EXT L1

    NA

    NA

    SBB (Lot 8)

    Electrical Rough-in Soffits – EXT L1

    NA

    NA

    SBB (Lot 8) Concrete

    Form Grand Stair – INT L1

    NA

    NA

    SBB (Lot 8)

    Install Fire Sprinkler Mains, Branches, & Seismic

    NA

    NA

    SBB (Lot 8) Concrete

    Remove Re-Shore – INT L2

    NA

    NA

    SBB (Lot 8)

    Frame Interference Walls and Install Foor Frames – INT L2

    NA

    NA

    SBB (Lot 8)

    Install Early MEP to Support Top Drown Drywall – INT L2

    NA

    NA

    SBB (Lot 8) Concrete

    F/R/P Walls at Transformer Yard

    Concrete Pump

    Noise due to Equipment

    SBB (Lot 8)

    Install Fire Water College Place to SBB POC

    NA

    NA

     

    Week of January 1, 2023

    Construction Activities 

     

    Location

    Activity

    Equipment Used

    Anticipated Disturbance

    SBB (Lot 8) Concrete

    Underslab Electrical Rough-in - Auditorium Steps

    NA

    NA

    SBB (Lot 8) Concrete

    Form Steps - Auditorium

    NA

    NA

    SBB (Lot 8)

    QC / Inspection – Auditorium

    NA

    NA

    SBB (Lot 8)

    Strip and Haul Off Form system

    Crane

    Noise due to Equipment

    SBB (Lot 8)

    Install Roofing at Mechanical Equipment Pad

    NA

    NA

    SBB (Lot 8)

    Install Mechanical Duct Pipe Supports – Roof

    NA

    NA

    SBB (Lot 8)

    Set Scaffold to Roof

    NA

    NA

    SBB (Lot 8)

    Install Temp Roofing at Low Roof

    NA

    NA

    SBB (Lot 8)

    Set Scaffold for level 2

    NA

    NA

    SBB (Lot 8)

    Erect Tube Steel Structure

    Crane

    Noise due to Equipment

    SBB (Lot 8)

    Form Grand Stair

    NA

    NA

    SBB (Lot 8)

    Install Mechanical / FSD’s – Electrical/BDF Room

    NA

    NA

    SBB (Lot 8)

    Install In-Wall Electrical – Electrical/BDF Room

    NA

    NA

    SBB (Lot 8)

    Hang 1st Side Top Down Drywall – INT-L2

    NA

    NA

    SBB (Lot 8)

    Install Insulation & Inspect -INT-L2

    NA

    NA

    SBB (Lot 8)

    Layout Framing and Install Top Track

    NA

    NA

    SBB (Lot 8) Concrete

    F/R/P Walls at Transformer Yard Slab

    Concrete Pump

    Noise due to Equipment

    SBB (Lot 8) Concrete

    F/R/P Transformer Yard Slab

    Concrete Pump

    Noise due to Equipment

     

    Current and Upcoming Anticipated Closures

    The following shutdown(s)/ closures are anticipated as indicated below. Updates to this schedule will be released weekly in the Project Construction Advisories until the work is complete.  Please contact John Franklin with any specific questions or concerns at john.franklin@ucr.edu.

     

    Description

    Location

    Duration & Date

    Impacted Buildings/ Facilities

    Lot 8

    Lot 8

    Permanently

    Lot 8

    Lot 43

    Lot 43

    Indefinitely

    Lot 43

    Anderson Park

    Anderson Park

    Indefinitely

    Anderson Park

  • 950592 UCR SBB - Construction Alert #57

    Current Week

    Construction Activities

     

    Location

    Activity

    Equipment Used

    Anticipated Disturbance

    SBB (Lot 8) Concrete

    MEP Sleeves and Inserts – Deck L5

    NA

    NA

    SBB (Lot 8) Concrete

    Install Embeds – Deck L5

    NA

    NA

    SBB (Lot 8) Concrete

    Set Anchor Bolts – Deck L5

    NA

    NA

    SBB (Lot 8) Concrete

    Rebar / PT Cables – Deck L5

    Crane

    Noise due to Equipment

    SBB (Lot 8) Concrete

    Electrical Rough-in – Deck L5

    NA

    NA

    SBB (Lot 8)

    Install Early MEP To support Top Down Drywall – INT-L1

    NA

    NA

    SBB (Lot 8)

    Install Misc Metals Supports for Operable Partitions – INT-L1

    NA

    NA

    SBB (Lot 8)

    Hang 1st Side Top Down Drywall – INT-L1

    NA

    NA

    SBB (Lot 8)

    Install Insulation & Inspect – INT-L1

    NA

    NA

    SBB (Lot 8)

    Install Elevator Guide Rail Support Steel – Level 2

    NA

    NA

    SBB (Lot 8)

    F/R/P Transformer Yard Footings

    NA

    NA

     

    Week of December 18, 2023

    Construction Activities 

     

    Location

    Activity

    Equipment Used

    Anticipated Disturbance

    SBB (Lot 8) Concrete

    Electrical Rough-in – Deck L5

    NA

    NA

    SBB (Lot 8) Concrete

    Deck Depressions – Deck L5

    NA

    NA

    SBB (Lot 8) Concrete

    QC / Inspection – Deck L5

    NA

    NA

    SBB (Lot 8) Concrete

    Pour  – Deck L5

    Concrete Pump

    Noise due to Equipment

    SBB (Lot 8) Concrete

    Strip Edge Form and Transfer Beams  – Deck L5

    NA

    NA

    SBB (Lot 8) Concrete

    Cure for Stress  – Deck L5

    NA

    NA

    SBB (Lot 8) Concrete

    Stress Transfer Beams  – Deck L5

    NA

    NA

    SBB (Lot 8) Concrete

    One Side Form Walls and Columns – Vert L5

    NA

    NA

    SBB (Lot 8) Concrete

    Rebar – Vert L5

    Crane

    Noise due to Equipment

    SBB (Lot 8) Concrete

    Layout and Install MEPs – Vert L5

    NA

    NA

    SBB (Lot 8) Concrete

    Set Embeds – Vert L5

    NA

    NA

    SBB (Lot 8) Concrete

    QC / Inspection  – Vert L5

    NA

    NA

    SBB (Lot 8) Concrete

    F/R/P Equipment Pads

    Concrete Pump

    Noise due to Equipment

    SBB (Lot 8) Concrete

    Roof Davits

    NA

    NA

    SBB (Lot 8)

    Soffit Framing – EXT L1

    NA

    NA

    SBB (Lot 8)

    Rigid Insulation and Air Water Barrier – EXT L1

    NA

    NA

    SBB (Lot 8)

    Electrical Rough-in Soffits – EXT L1

    NA

    NA

    SBB (Lot 8)

    Fire Sprinkler Rough-in Soffits – EXT L1

    NA

    NA

    SBB (Lot 8)

    Plumbing Rough-in Soffits – EXT L1

    NA

    NA

    SBB (Lot 8)

    Hang 2nd Side Top Down Drywall and Inspect – INT L1

    NA

    NA

    SBB (Lot 8)

    Fire Tape – INT L1

    NA

    NA

    SBB (Lot 8)

    Fire Caulk Head of Wall– INT L1

    NA

    NA

    SBB (Lot 8)

    Install Elevator Guide Rail Support Steel – Level 3

    NA

    NA

    SBB (Lot 8)

    Concrete

    F/R/P Walls at Transformer Yard

    Concrete Pump

    Noise due to Equipment

     

    Week of December 25, 2023

    Construction Activities 

     

    Location

    Activity

    Equipment Used

    Anticipated Disturbance

    SBB (Lot 8) Concrete

    Close Tow Side Forms – Vert L5

    NA

    NA

    SBB (Lot 8) Concrete

    Pour – Vert L5

    Concrete Pump

    Noise due to Equipment

    SBB (Lot 8) Concrete

    Strip Walls and columns – Vert L5

    NA

    NA

    SBB (Lot 8) Concrete

    Cure for Steel Erection – Vert L5

    NA

    NA

    SBB (Lot 8)

    Soffit Framing – EXT L1

    NA

    NA

    SBB (Lot 8)

    Rigid Insulation and Air Water Barrier – EXT L1

    NA

    NA

    SBB (Lot 8)

    Electrical Rough-in Soffits – EXT L1

    NA

    NA

    SBB (Lot 8) Concrete

    Form Grand Stair – INT L1

    NA

    NA

    SBB (Lot 8)

    Install Storm, Overflow, Sewer Lines, and Seismic

    NA

    NA

    SBB (Lot 8)

    Install Mechanical / FSD’s

    NA

    NA

    SBB (Lot 8) Concrete

    Remove Re-Shore – INT L2

    NA

    NA

    SBB (Lot 8)

    Frame Interference Walls and Install Foor Frames – INT L2

    NA

    NA

    SBB (Lot 8)

    Install Early MEP to Support Top Drown Drywall – INT L2

    NA

    NA

    SBB (Lot 8) Concrete

    F/R/P Walls at Transformer Yard

    Concrete Pump

    Noise due to Equipment

    SBB (Lot 8)

    Install Fire Water College Place to SBB POC

    NA

    NA

    SBB (Lot 8) Concrete

    F/R/P Transformer Yard Slab

    Concrete Pump

    Noise due to Equipment

     

    Current and Upcoming Anticipated Closures

    The following shutdown(s)/ closures are anticipated as indicated below. Updates to this schedule will be released weekly in the Project Construction Advisories until the work is complete.  Please contact John Franklin with any specific questions or concerns at john.franklin@ucr.edu.

     

    Description

    Location

    Duration & Date

    Impacted Buildings/ Facilities

    Lot 8

    Lot 8

    Permanently

    Lot 8

    Lot 43

    Lot 43

    Indefinitely

    Lot 43

    Anderson Park

    Anderson Park

    Indefinitely

    Anderson Park

  • 950592 UCR SBB - Construction Alert #56

    Current Week

    Construction Activities

     

    Location

    Activity

    Equipment Used

    Anticipated Disturbance

    SBB (Lot 8) Concrete

    Pour Auditorium Steps – SOG1

    Concrete Pumps

    Noise due to Equipment

    SBB (Lot 8) Concrete

    Strip Edge Form / Bulkhead – SOG North – Auditorium Steps

    Crane

    Noise due to Equipment

    SBB (Lot 8) Concrete

    Strip & Re-Shore – Deck L4S

    NA

    NA

    SBB (Lot 8) Concrete

    Edge Form – Deck L5 Roof

    Crane

    Noise due to Equipment

    SBB (Lot 8)

    Install Early MEP to support Top Down Drywall

    NA

    NA

    SBB (Lot 8)

    Hang 1st Side Top Down Drywall – INT L1

    NA

    NA

    SBB (Lot 8)

    Install Insulation and Inspect – INT L1

    NA

    NA

    SBB (Lot 8)

    F/R/P Transformer Yard Slab

    NA

    NA

     

    Week of December 11, 2023

    Construction Activities 

     

    Location

    Activity

    Equipment Used

    Anticipated Disturbance

    SBB (Lot 8) Concrete

    MEP Sleeves and Inserts – Deck L5

    NA

    NA

    SBB (Lot 8) Concrete

    Set Anchor Bolts – Deck L5

    NA

    NA

    SBB (Lot 8) Concrete

    Rebar / PT Cables – Deck L5

    Crane

    Noise due to Equipment

    SBB (Lot 8) Concrete

    Electrical Rough-in – Deck L5

    NA

    NA

    SBB (Lot 8)

    Soffit Framing – EXT-L1

    NA

    NA

    SBB (Lot 8)

    Rigid Insulation and Air Water Barrier – EXT-L1

    NA

    NA

    SBB (Lot 8)

    Electrical Rough-in Soffits – EXT-L1

    NA

    NA

    SBB (Lot 8)

    Fire Sprinkler Rough-in Soffits – EXT-L1

    NA

    NA

    SBB (Lot 8)

    Plumbing Rough-in Soffits – EXT-L1

    NA

    NA

    SBB (Lot 8)

    Fire Tape – INT-L1

    NA

    NA

    SBB (Lot 8)

    Fire Caulk Head of Wall – INT-L1

    NA

    NA

     

    Week of December 18, 2023

    Construction Activities 

     

    Location

    Activity

    Equipment Used

    Anticipated Disturbance

    SBB (Lot 8) Concrete

    Deck Depression – Deck L5

    NA

    NA

    SBB (Lot 8) Concrete

    QC / Inspection – Deck L5

    NA

    NA

    SBB (Lot 8) Concrete

    Pour – Deck L5

    Concrete Pumps

    Noise due to Equipment

    SBB (Lot 8) Concrete

    Strip Edge Form and Transfer Beams – Deck L5

    NA

    NA

    SBB (Lot 8) Concrete

    Layout walls and Columns – VERT L5

    NA

    NA

    SBB (Lot 8)

    Soffit Sheathing – EXT L1

    NA

    NA

    SBB (Lot 8)

    Isntall Hot/Cold Domestic Water Lines and Seismic – INT L1

    NA

    NA

    SBB (Lot 8)

    Install Mechanical / FSD’s – Electrical / BDF Rooms

    NA

    NA

     

    Current and Upcoming Anticipated Closures

    The following shutdown(s)/ closures are anticipated as indicated below. Updates to this schedule will be released weekly in the Project Construction Advisories until the work is complete.  Please contact John Franklin with any specific questions or concerns at john.franklin@ucr.edu.

     

    Description

    Location

    Duration & Date

    Impacted Buildings/ Facilities

    Lot 8

    Lot 8

    Permanently

    Lot 8

    Lot 43

    Lot 43

    Indefinitely

    Lot 43

    Anderson Park

    Anderson Park

    Indefinitely

    Anderson Park

  • 950592 UCR SBB - Construction Alert #55

    Current Week

    Construction Activities

     

    Location

    Activity

    Equipment Used

    Anticipated Disturbance

    SBB (Lot 8) Concrete

    QC / Inspection – SOG North Auditorium Steps

    NA

    NA

    SBB (Lot 8) Concrete

    Strip Walls & Columns – Vert L4N

    NA

    NA

    SBB (Lot 8) Concrete

    Close Two Side Forms - Vert L4S

    Crane

    Noise due to Equipment

    SBB (Lot 8) Concrete

    Pour - Vert L4S

    Concrete Pumps

    Noise due to Equipment

    SBB (Lot 8) Concrete

    Strip Walls & Columns – Vert L4S

    Crane

    Noise due to Equipment

    SBB (Lot 8)

    Exterior Framing – EXT-L1

    NA

    NA

    SBB (Lot 8)

    Frame Interference Walls and Install door Frames - INT-L1

    NA

    NA

    SBB (Lot 8)

    Install Early MEP to Support Top Down Drywall

    NA

    NA

    SBB (Lot 8) Concrete

    F/R/P Transformer Yard Wall

    NA

    NA

    SBB (Lot 8) Concrete

    F/R/P Transformer Yard Slab

    NA

    NA

     

    Week of December 4, 2023

    Construction Activities 

     

    Location

    Activity

    Equipment Used

    Anticipated Disturbance

    SBB (Lot 8) Concrete

    Pour Auditorium Steps – SOG1

    Concrete Pumps

    Noise due to Equipment

    SBB (Lot 8) Concrete

    Strip Edge Form / Bulkhead – SOG North – Auditorium Steps

    Crane

    Noise due to Equipment

    SBB (Lot 8) Concrete

    Strip & Re-Shore – Deck L4S

    NA

    NA

    SBB (Lot 8) Concrete

    Edge Form – Deck L5 Roof

    NA

    NA

    SBB (Lot 8)

    Install Early MEP to support Top Down Drywall

    NA

    NA

    SBB (Lot 8)

    Hang 1st Side Top Down Drywall – INT L1

    NA

    NA

    SBB (Lot 8)

    Install Insulation and Inspect – INT L1

    NA

    NA

    SBB (Lot 8)

    F/R/P Transformer Yard Slab

    NA

    NA

     

    Week of December 11, 2023

    Construction Activities 

     

    Location

    Activity

    Equipment Used

    Anticipated Disturbance

    SBB (Lot 8) Concrete

    MEP Sleeves and Inserts – Deck L5

    NA

    NA

    SBB (Lot 8) Concrete

    Set Anchor Bolts – Deck L5

    NA

    NA

    SBB (Lot 8) Concrete

    Rebar / PT Cables – Deck L5

    Crane

    Noise due to Equipment

    SBB (Lot 8)

    Soffit Framing – EXT-L1

    NA

    NA

    SBB (Lot 8)

    Rigid Insulation and Air Water Barrier – EXT-L1

    NA

    NA

    SBB (Lot 8)

    Electrical Rough-in Soffits – EXT-L1

    NA

    NA

    SBB (Lot 8)

    Fire Sprinkler Rough-in Soffits – EXT-L1

    NA

    NA

    SBB (Lot 8)

    Plumbing Rough-in Soffits – EXT-L1

    NA

    NA

    SBB (Lot 8)

    Fire Tape – INT-L1

    NA

    NA

    SBB (Lot 8)

    Fire Caulk Head of Wall – INT-L1

    NA

    NA

     

    Current and Upcoming Anticipated Closures

    The following shutdown(s)/ closures are anticipated as indicated below. Updates to this schedule will be released weekly in the Project Construction Advisories until the work is complete.  Please contact John Franklin with any specific questions or concerns at john.franklin@ucr.edu.

     

    Description

    Location

    Duration & Date

    Impacted Buildings/ Facilities

    Lot 8

    Lot 8

    Permanently

    Lot 8

    Lot 43

    Lot 43

    Indefinitely

    Lot 43

    Anderson Park

    Anderson Park

    Indefinitely

    Anderson Park

  • 950592 UCR SBB - Construction Alert #54

    Current Week

    Construction Activities

     

    Location

    Activity

    Equipment Used

    Anticipated Disturbance

    BIO

    Punchlist Corrections

    NA

    NA

    SBB (Lot 8) Concrete

    Form Steps – Auditorium

    NA

    NA

    SBB (Lot 8) Concrete

    QC / Inspection – Vert L4N

    NA

    NA

    SBB (Lot 8) Concrete

    Close Two Side Forms  – Vert L4N

    Crane

    Noise due to Equipment

    SBB (Lot 8) Concrete

    Pour  – Vert L4N

    Concrete Pumps

    Noise due to Equipment

    SBB (Lot 8) Concrete

    Rebar  – Vert L4S

    Crane

    Noise due to Equipment

    SBB (Lot 8) Concrete

    Layout & Install MEP’s – Vert L4S

    NA

    NA

    SBB (Lot 8) Concrete

    Set Embeds – Vert L4S

    NA

    NA

    SBB (Lot 8) Concrete

    QC / Inspection – Vert L4S

    NA

    NA

    SBB (Lot 8)

    Exterior Framing – L1

    NA

    NA

    SBB (Lot 8)

    Frame Interference Walls & Install Door Frames

    NA

    NA

    SBB (Lot 8) Concrete

    F/R/P Transformer Yard Wall

    NA

    NA

     

    Week of November 27, 2023

    Construction Activities 

     

    Location

    Activity

    Equipment Used

    Anticipated Disturbance

    SBB (Lot 8) Concrete

    QC / Inspection – SOG North Auditorium Steps

    NA

    NA

    SBB (Lot 8) Concrete

    Strip Walls & Columns – Vert L4N

    NA

    NA

    SBB (Lot 8) Concrete

    Close Two Side Forms - Vert L4S

    Crane

    Noise due to Equipment

    SBB (Lot 8) Concrete

    Pour - Vert L4S

    Concrete Pumps

    Noise due to Equipment

    SBB (Lot 8) Concrete

    Strip Walls & Columns – Vert L4S

    Crane

    Noise due to Equipment

    SBB (Lot 8)

    Exterior Framing – EXT-L1

    NA

    NA

    SBB (Lot 8)

    Frame Interference Walls and Install door Frames - INT-L1

    NA

    NA

    SBB (Lot 8)

    Install Early MEP to Support Top Down Drywall

    NA

    NA

    SBB (Lot 8) Concrete

    F/R/P Transformer Yard Wall

    NA

    NA

    SBB (Lot 8) Concrete

    F/R/P Transformer Yard Slab

    NA

    NA

     

    Week of December 4, 2023

    Construction Activities 

     

    Location

    Activity

    Equipment Used

    Anticipated Disturbance

    SBB (Lot 8) Concrete

    Pour Auditorium Steps – SOG1

    Concrete Pumps

    Noise due to Equipment

    SBB (Lot 8) Concrete

    Strip Edge Form / Bulkhead – SOG North – Auditorium Steps

    Crane

    Noise due to Equipment

    SBB (Lot 8) Concrete

    Strip & Re-Shore – Deck L4S

    NA

    NA

    SBB (Lot 8) Concrete

    Edge Form – Deck L5 Roof

    NA

    NA

    SBB (Lot 8)

    Install Early MEP to support Top Down Drywall

    NA

    NA

    SBB (Lot 8)

    Hang 1st Side Top Down Drywall – INT L1

    NA

    NA

    SBB (Lot 8)

    Install Insulation and Inspect – INT L1

    NA

    NA

    SBB (Lot 8)

    F/R/P Transformer Yard Slab

    NA

    NA

     

    Current and Upcoming Anticipated Closures

    The following shutdown(s)/ closures are anticipated as indicated below. Updates to this schedule will be released weekly in the Project Construction Advisories until the work is complete.  Please contact John Franklin with any specific questions or concerns at john.franklin@ucr.edu.

     

    Description

    Location

    Duration & Date

    Impacted Buildings/ Facilities

    Lot 8

    Lot 8

    Permanently

    Lot 8

    Lot 43

    Lot 43

    Indefinitely

    Lot 43

    Anderson Park

    Anderson Park

    Indefinitely

    Anderson Park

  • 950592 UCR SBB - Construction Alert #53

    Current Week

    Construction Activities

    Location

    Activity

    Equipment Used

    Anticipated Disturbance

    BIO

    Punchlist Corrections

    NA

    NA

    SBB (Lot 8) Concrete

    Edge Form / Bulkhead - SOG North - Auditorium Steps

    NA

    NA

    SBB (Lot 8) Concrete

    Rebar - SOG North - Auditorium Steps

    Crane

    Noise due to Equipment

    SBB (Lot 8) Concrete

    Underslab Electrical Rough-in - SOG North - Auditorium Steps

    NA

    NA

    SBB (Lot 8) Concrete

    Underslab Fire Sprinkler Riser - SOG North

    NA

    NA

    SBB (Lot 8) Concrete

    QC / Inspection – Deck L4S

    NA

    NA

    SBB (Lot 8) Concrete

    Pour – Deck L4S

    Concrete Pumps

    Noise due to Equipment

    SBB (Lot 8) Concrete

    Strip Edge Form & Transfer Beams – Deck L4S

    NA

    NA

    SBB (Lot 8) Concrete

    Stress Transfer Beams – Deck L4S

    NA

    NA

    SBB (Lot 8) Concrete

    Layout Walls & Columns -Vert L4N

    Crane

    Noise due to Equipment

    SBB (Lot 8) Concrete

    One Side Form Walls & Columns -Vert L4N

    Crane

    Noise due to Equipment

    SBB (Lot 8) Concrete

    Rebar -Vert L4N

    Crane

    Noise due to Equipment

    SBB (Lot 8) Concrete

    Layout & Install MEP's -Vert L4N

    NA

    NA

    SBB (Lot 8) Concrete

    Set Embeds -Vert L4N

    NA

    NA

    SBB (Lot 8) Concrete

    Layout Walls & Columns – Vert L4S

    Crane

    Noise due to Equipment

    SBB (Lot 8) Concrete

    F/R/P Transformer Yard Wall

    NA

    NA

     

    Week of November 20, 2023

    Construction Activities 

     

    Location

    Activity

    Equipment Used

    Anticipated Disturbance

    BIO

    Building Complete

    NA

    NA

    SBB (Lot 8) Concrete

    Form Steps – Auditorium

    NA

    NA

    SBB (Lot 8) Concrete

    QC / Inspection – Vert L4N

    NA

    NA

    SBB (Lot 8) Concrete

    Close Two Side Forms  – Vert L4N

    Crane

    Noise due to Equipment

    SBB (Lot 8) Concrete

    Pour  – Vert L4N

    Concrete Pumps

    Noise due to Equipment

    SBB (Lot 8) Concrete

    Rebar  – Vert L4S

    Crane

    Noise due to Equipment

    SBB (Lot 8) Concrete

    Layout & Install MEP’s – Vert L4S

    NA

    NA

    SBB (Lot 8) Concrete

    Set Embeds – Vert L4S

    NA

    NA

    SBB (Lot 8) Concrete

    QC / Inspection – Vert L4S

    NA

    NA

    SBB (Lot 8)

    Exterior Framing – L1

    NA

    NA

    SBB (Lot 8)

    Frame Interference Walls & Install Door Frames

    NA

    NA

    SBB (Lot 8) Concrete

    F/R/P Transformer Yard Wall

    NA

    NA

     

    Week of November 27, 2023

    Construction Activities 

     

    Location

    Activity

    Equipment Used

    Anticipated Disturbance

    SBB (Lot 8) Concrete

    QC / Inspection – SOG North Auditorium Steps

    NA

    NA

    SBB (Lot 8) Concrete

    Strip Walls & Columns – Vert L4N

    NA

    NA

    SBB (Lot 8) Concrete

    Close Two Side Forms - Vert L4S

    Crane

    Noise due to Equipment

    SBB (Lot 8) Concrete

    Pour - Vert L4S

    Concrete Pumps

    Noise due to Equipment

    SBB (Lot 8) Concrete

    Strip Walls & Columns – Vert L4S

    Crane

    Noise due to Equipment

    SBB (Lot 8)

    Exterior Framing – EXT-L1

    NA

    NA

    SBB (Lot 8)

    Frame Interference Walls and Install door Frames - INT-L1

    NA

    NA

    SBB (Lot 8)

    Install Early MEP to Support Top Down Drywall

    NA

    NA

    SBB (Lot 8) Concrete

    F/R/P Transformer Yard Wall

    NA

    NA

    SBB (Lot 8) Concrete

    F/R/P Transformer Yard Slab

    NA

    NA

     

    Current and Upcoming Anticipated Closures

    The following shutdown(s)/ closures are anticipated as indicated below. Updates to this schedule will be released weekly in the Project Construction Advisories until the work is complete.  Please contact John Franklin with any specific questions or concerns at john.franklin@ucr.edu.

     

    Description

    Location

    Duration & Date

    Impacted Buildings/ Facilities

    Lot 8

    Lot 8

    Permanently

    Lot 8

    Lot 43

    Lot 43

    Indefinitely

    Lot 43

    Anderson Park

    Anderson Park

    Indefinitely

    Anderson Park

     

  • 950592 UCR SBB - Construction Alert #52

    Current Week

    Construction Activities

     

    Location

    Activity

    Equipment Used

    Anticipated Disturbance

    BIO

    Develop punch list

    NA

    NA

    BIO

    Startup and Test Fire Alarm System

    NA

    NA

    BIO

    Startup and Test Lighting

    NA

    NA

    BIO

    Startup and Test mechanical / Control Systems

    NA

    NA

    BIO

    Startup and Test Walk-in Cooler

    NA

    NA

    BIO

    Punchlist Corrections

    NA

    NA

    SBB (Lot 8) Concrete

    Rebar / PT Cables

    Crane

    Noise due to Equipment

    SBB (Lot 8) Concrete

    Electrical Rough-in

    NA

    NA

    SBB (Lot 8) Concrete

    F/R/P Transformer Yard Footings

    NA

    NA

    SBB (Lot 8) Concrete

    F/R/P Transformer Yard Walls

    NA

    NA

    SBB (Lot 8) Concrete

    Install Water Line – Campus Dr POC to SBB POC

    NA

    NA

    SBB (Lot 8) Concrete

    Rebar / PT Cables

    Crane

    Noise due to Equipment

    SBB (Lot 8) Concrete

    Electrical Rough-in

    NA

    NA

    SBB (Lot 8) Concrete

    Deck Depressions

    NA

    NA

    SBB (Lot 8) Util

    Shutdown and Tie-in Water Line to Pump House

    NA

    NA

     

    Week of November 13, 2023

    Construction Activities 

     

    Location

    Activity

    Equipment Used

    Anticipated Disturbance

    BIO

    Punchlist Corrections

    NA

    NA

    SBB (Lot 8) Concrete

    Edge Form / Bulkhead - SOG North - Auditorium Steps

    NA

    NA

    SBB (Lot 8) Concrete

    Rebar - SOG North - Auditorium Steps

    Crane

    Noise due to Equipment

    SBB (Lot 8) Concrete

    Underslab Electrical Rough-in - SOG North - Auditorium Steps

    NA

    NA

    SBB (Lot 8) Concrete

    Underslab Fire Sprinkler Riser - SOG North

    NA

    NA

    SBB (Lot 8) Concrete

    QC / Inspection – Deck L4S

    NA

    NA

    SBB (Lot 8) Concrete

    Pour – Deck L4S

    Concrete Pumps

    Noise due to Equipment

    SBB (Lot 8) Concrete

    Strip Edge Form & Transfer Beams – Deck L4S

    NA

    NA

    SBB (Lot 8) Concrete

    Stress Transfer Beams – Deck L4S

    NA

    NA

    SBB (Lot 8) Concrete

    Layout Walls & Columns -Vert L4N

    Crane

    Noise due to Equipment

    SBB (Lot 8) Concrete

    One Side Form Walls & Columns -Vert L4N

    Crane

    Noise due to Equipment

    SBB (Lot 8) Concrete

    Rebar -Vert L4N

    Crane

    Noise due to Equipment

    SBB (Lot 8) Concrete

    Layout & Install MEP's -Vert L4N

    NA

    NA

    SBB (Lot 8) Concrete

    Set Embeds -Vert L4N

    NA

    NA

    SBB (Lot 8) Concrete

    Layout Walls & Columns – Vert L4S

    Crane

    Noise due to Equipment

    SBB (Lot 8) Concrete

    F/R/P Transformer Yard Wall

    NA

    NA

     

    Week of November 20, 2023

    Construction Activities 

     

    Location

    Activity

    Equipment Used

    Anticipated Disturbance

    BIO

    Building Complete

    NA

    NA

    SBB (Lot 8) Concrete

    Form Steps – Auditorium

    NA

    NA

    SBB (Lot 8) Concrete

    QC / Inspection – Vert L4N

    NA

    NA

    SBB (Lot 8) Concrete

    Close Two Side Forms  – Vert L4N

    Crane

    Noise due to Equipment

    SBB (Lot 8) Concrete

    Pour  – Vert L4N

    Concrete Pumps

    Noise due to Equipment

    SBB (Lot 8) Concrete

    Rebar  – Vert L4S

    Crane

    Noise due to Equipment

    SBB (Lot 8) Concrete

    Layout & Install MEP’s – Vert L4S

    NA

    NA

    SBB (Lot 8) Concrete

    Set Embeds – Vert L4S

    NA

    NA

    SBB (Lot 8) Concrete

    QC / Inspection – Vert L4S

    NA

    NA

    SBB (Lot 8)

    Exterior Framing – L1

    NA

    NA

    SBB (Lot 8)

    Frame Interference Walls & Install Door Frames

    NA

    NA

    SBB (Lot 8) Concrete

    F/R/P Transformer Yard Wall

    NA

    NA

     

    Current and Upcoming Anticipated Closures

    The following shutdown(s)/ closures are anticipated as indicated below. Updates to this schedule will be released weekly in the Project Construction Advisories until the work is complete.  Please contact John Franklin with any specific questions or concerns at john.franklin@ucr.edu.

     

    Description

    Location

    Duration & Date

    Impacted Buildings/ Facilities

    Lot 8

    Lot 8

    Permanently

    Lot 8

    Lot 43

    Lot 43

    Indefinitely

    Lot 43

    Anderson Park

    Anderson Park

    Indefinitely

    Anderson Park

  • 950592 UCR SBB - Construction Alert #51

    Current Weeks

    Construction Activities

     

    Location

    Activity

    Equipment Used

    Anticipated Disturbance

    BIO

    Final Clean

    NA

    NA

    BIO

    Start-up & Test Mechanical / Controls System

    NA

    NA

    BIO

    Start-up & Test Fire Alarm Systems

    NA

    NA

    BIO

    Start-up & Test Lighting

    NA

    NA

    BIO

    Start-up & Test Plumbing

    NA

    NA

    BIO

    Start-up & Test Card Reader

    NA

    NA

    SBB (Lot 8) Concrete

    Strip and Re-Shore – Deck L3N

    Crane

    Noise due to Equipment

    SBB (Lot 8) Concrete

    Pour – Vert L3S

    Concrete Pump

    Noise due to Equipment

    SBB (Lot 8) Concrete

    Strip Walls & Columns – Vert L3S

    Crane

    Noise due to Equipment

    SBB (Lot 8) Concrete

    Install Water Line – Campus Dr POC to SBB POC

    NA

    NA

    SBB (Lot 8) Concrete

    F/R/P Transformer Yard Footings

    NA

    NA

    SBB (Lot 8) Concrete

    F/R/P Walls at Transformer Yard

    NA

    NA

    SBB (Lot 8) Concrete

    F/R/P Transformer Yard Slab

    NA

    NA

    SBB (Lot 8) Concrete

    Form Deck – Deck L4S

    NA

    NA

    SBB (Lot 8) Concrete

    Edge Form – Deck L4S

    NA

    NA

    SBB (Lot 8) Concrete

    Install Embeds – Deck L4S

    NA

    NA

    SBB (Lot 8) Concrete

    MEP Sleeves and Insert – Deck L4S

    NA

    NA

     

    Week of November 6, 2023

    Construction Activities 

     

    Location

    Activity

    Equipment Used

    Anticipated Disturbance

    BIO

    Develop punch list

    NA

    NA

    BIO

    Startup and Test Fire Alarm System

    NA

    NA

    BIO

    Startup and Test Lighting

    NA

    NA

    BIO

    Startup and Test mechanical / Control Systems

    NA

    NA

    BIO

    Startup and Test Walk-in Cooler

    NA

    NA

    BIO

    Punchlist Corrections

    NA

    NA

    SBB (Lot 8) Concrete

    Rebar / PT Cables

    Crane

    Noise due to Equipment

    SBB (Lot 8) Concrete

    Electrical Rough-in

    NA

    NA

    SBB (Lot 8) Concrete

    F/R/P Transformer Yard Footings

    NA

    NA

    SBB (Lot 8) Concrete

    F/R/P Transformer Yard Walls

    NA

    NA

    SBB (Lot 8) Concrete

    Install Water Line – Campus Dr POC to SBB POC

    NA

    NA

    SBB (Lot 8) Concrete

    Rebar / PT Cables

    Crane

    Noise due to Equipment

    SBB (Lot 8) Concrete

    Electrical Rough-in

    NA

    NA

    SBB (Lot 8) Concrete

    Deck Depressions

    NA

    NA

    SBB (Lot 8) Util

    Shutdown and Tie-in Water Line to Pump House

    NA

    NA

     

    Week of November 13, 2023

    Construction Activities 

     

    Location

    Activity

    Equipment Used

    Anticipated Disturbance

    BIO

    Punchlist Corrections

    NA

    NA

    SBB (Lot 8) Concrete

    Edge Form / Bulkhead - SOG North - Auditorium Steps

    NA

    NA

    SBB (Lot 8) Concrete

    Rebar - SOG North - Auditorium Steps

    Crane

    Noise due to Equipment

    SBB (Lot 8) Concrete

    Underslab Electrical Rough-in - SOG North - Auditorium Steps

    NA

    NA

    SBB (Lot 8) Concrete

    Underslab Fire Sprinkler Riser - SOG North

    NA

    NA

    SBB (Lot 8) Concrete

    QC / Inspection – Deck L4S

    NA

    NA

    SBB (Lot 8) Concrete

    Pour – Deck L4S

    NA

    NA

    SBB (Lot 8) Concrete

    Strip Edge Form & Transfer Beams – Deck L4S

    NA

    NA

    SBB (Lot 8) Concrete

    Stress Transfer Beams – Deck L4S

    NA

    NA

    SBB (Lot 8) Concrete

    Layout Walls & Columns -Vert L4N

    Crane

    Noise due to Equipment

    SBB (Lot 8) Concrete

    One Side Form Walls & Columns -Vert L4N

    NA

    NA

    SBB (Lot 8) Concrete

    Rebar -Vert L4N

    Crane

    Noise due to Equipment

    SBB (Lot 8) Concrete

    Layout & Install MEP's -Vert L4N

    NA

    NA

    SBB (Lot 8) Concrete

    Set Embeds -Vert L4N

    NA

    NA

    SBB (Lot 8) Concrete

    Layout Walls & Columns – Vert L4S

    Crane

    Noise due to Equipment

    SBB (Lot 8) Concrete

    F/R/P Transformer Yard Wall

    NA

    NA

     

    Current and Upcoming Anticipated Closures

    The following shutdown(s)/ closures are anticipated as indicated below. Updates to this schedule will be released weekly in the Project Construction Advisories until the work is complete.  Please contact John Franklin with any specific questions or concerns at john.franklin@ucr.edu.

     

    Description

    Location

    Duration & Date

    Impacted Buildings/ Facilities

    Lot 8

    Lot 8

    Permanently

    Lot 8

    Lot 43

    Lot 43

    Indefinitely

    Lot 43

    Anderson Park

    Anderson Park

    Indefinitely

    Anderson Park

     

  • 950592 UCR SBB - Construction Alert #50

    Current Weeks

    Construction Activities

    Location

    Activity

    Equipment Used

    Anticipated Disturbance

    BIO

    Landscape and Irrigation

    Mini-excavator

    Noise due to Equipment

    BIO

    Install Bio-Filtration Planter

    Mini-excavator

    Noise due to Equipment

    BIO

    Start-up & Test Walk-in Cooler

    NA

    NA

    BIO

    New Water Line to Pump House / POC’s

    NA

    NA

    BIO

    Shutdown and Tie-in Water Line to Pump House

    NA

    NA

    SBB (Lot 8) Concrete

    Pour – Vert L3N

    Concrete Pump

    Noise due to Equipment

    SBB (Lot 8) Concrete

    Strip Walls & Columns – Vert L3N

    Crane

    Noise due to Equipment

    SBB (Lot 8) Concrete

    Stress Transfer Beams – Deck L3S

    NA

    NA

    SBB (Lot 8) Concrete

    Layout & Install MEPs – Vert L3S

    NA

    NA

    SBB (Lot 8) Concrete

    Set Embeds – Vert L3S

    NA

    NA

    SBB (Lot 8) Concrete

    QC/Inspection – Vert L3S

    NA

    NA

    SBB (Lot 8) Concrete

    Close Two Side Forms – Vert L3S

    Crane

    Noise due to Equipment

    SBB (Lot 8) Concrete

    Form Deck – L4S

    NA

    NA

     

    Week of October 30, 2023

    Construction Activities 

     

    Location

    Activity

    Equipment Used

    Anticipated Disturbance

    BIO

    Start-up & Test Mechanical / Controls System

    NA

    NA

    BIO

    Start-up & Test Fire Alarm Systems

    NA

    NA

    BIO

    Start-up & Test Lighting

    NA

    NA

    SBB (Lot 8) Concrete

    Strip and Re-Shore – Deck L3N

    Crane

    Noise due to Equipment

    SBB (Lot 8) Concrete

    Pour – Vert L3S

    Concrete Pump

    Noise due to Equipment

    SBB (Lot 8) Concrete

    Strip Walls & Columns – Vert L3S

    Crane

    Noise due to Equipment

    SBB (Lot 8) Concrete

    Install Water Line – Campus Dr POC to SBB POC

    NA

    NA

    SBB (Lot 8) Concrete

    F/R/P Transformer Yard Footings

    NA

    NA

    SBB (Lot 8) Concrete

    F/R/P Walls at Transformer Yard

    NA

    NA

    SBB (Lot 8) Concrete

    F/R/P Transformer Yard Slab

    NA

    NA

     

    Week of November 6, 2023

    Construction Activities 

     

    Location

    Activity

    Equipment Used

    Anticipated Disturbance

    BIO

    Develop punch list

    NA

    NA

    BIO

    Startup and Test Fire Alarm System

    NA

    NA

    BIO

    Startup and Test Lighting

    NA

    NA

    SBB (Lot 8) Concrete

    Rebar / PT Cables

    Crane

    Noise due to Equipment

    SBB (Lot 8) Concrete

    Electrical Rough-in

    NA

    NA

    SBB (Lot 8) Concrete

    F/R/P Transformer Yard Footings

    NA

    NA

    SBB (Lot 8) Concrete

    F/R/P Transformer Yard Walls

    NA

    NA

    SBB (Lot 8) Concrete

    Install Water Line – Campus Dr POC to SBB POC

    NA

    NA

     

    Current and Upcoming Anticipated Closures

    The following shutdown(s)/ closures are anticipated as indicated below. Updates to this schedule will be released weekly in the Project Construction Advisories until the work is complete.  Please contact John Franklin with any specific questions or concerns at john.franklin@ucr.edu.

     

    Description

    Location

    Duration & Date

    Impacted Buildings/ Facilities

    Lot 8

    Lot 8

    Permanently

    Lot 8

    Lot 43

    Lot 43

    Indefinitely

    Lot 43

    Anderson Park

    Anderson Park

    Indefinitely

    Anderson Park

  • 950592 UCR SBB - Construction Alert #49

    Current Weeks

    Construction Activities

     

    Location

    Activity

    Equipment Used

    Anticipated Disturbance

    BIO

    Install HVAC Trim

    NA

    NA

    BIO

    Install Fire Alarm Devices and Trim

    NA

    NA

    BIO

    Install Light Fixtures

    NA

    NA

    BIO

    Install Site Furnishings

    NA

    NA

    BIO

    Landscape and Irrigation

    Mini-excavator

    Noise due to Equipment

    BIO

    Install Bio-Filtration Planter

    Mini-excavator

    Noise due to Equipment

    BIO

    MEPT Startup and Testing

    NA

    NA

    BIO

    Install Walk-in Cooler

    NA

    NA

    SBB (Lot 8) Concrete

    Stress Transfer Beams – Deck L3N

    NA

    NA

    SBB (Lot 8) Concrete

    Rebar – Vert L3N

    Crane

    Noise due to Equipment

    SBB (Lot 8) Concrete

    Layout & Install MEP’s – Vert L3N

    NA

    NA

    SBB (Lot 8) Concrete

    Set Embeds – Vert L3N

    NA

    NA

    SBB (Lot 8) Concrete

    QC / Inspection – Vert L3N

    NA

    NA

    SBB (Lot 8) Concrete

    Close two side Forms – Vert L3N

    Crane

    Noise due to Equipment

    SBB (Lot 8) Concrete

    Deck Depressions – Deck L3S

    NA

    NA

    SBB (Lot 8) Concrete

    QC / Inspection – Deck L3S

    NA

    NA

    SBB (Lot 8) Concrete

    Pour – Deck L3S

    Concrete Pumps

    Noise due to Equipment

    SBB (Lot 8) Concrete

    Strip Edge Form – Deck L3S

    NA

    NA

     

    Week of October 23, 2023

    Construction Activities 

     

    Location

    Activity

    Equipment Used

    Anticipated Disturbance

    BIO

    Landscape and Irrigation

    Mini-excavator

    Noise due to Equipment

    BIO

    Install Bio-Filtration Planter

    Mini-excavator

    Noise due to Equipment

    BIO

    Start-up & Test Walk-in Cooler

    NA

    NA

    BIO

    New Water Line to Pump House / POC’s

    NA

    NA

    BIO

    Shutdown and Tie-in Water Line to Pump House

    NA

    NA

    SBB (Lot 8) Concrete

    Pour – Vert L3N

    Concrete Pump

    Noise due to Equipment

    SBB (Lot 8) Concrete

    Strip Walls & Columns – Vert L3N

    Crane

    Noise due to Equipment

    SBB (Lot 8) Concrete

    Stress Transfer Beams – Deck L3S

    NA

    NA

    SBB (Lot 8) Concrete

    Layout & Install MEPs – Vert L3S

    NA

    NA

    SBB (Lot 8) Concrete

    Set Embeds – Vert L3S

    NA

    NA

    SBB (Lot 8) Concrete

    QC/Inspection – Vert L3S

    NA

    NA

    SBB (Lot 8) Concrete

    Close Two Side Forms – Vert L3S

    Crane

    Noise due to Equipment

    SBB (Lot 8) Concrete

    Form Deck – L4S

    NA

    NA

     

    Week of October 30, 2023

    Construction Activities 

     

    Location

    Activity

    Equipment Used

    Anticipated Disturbance

    BIO

    Start-up & Test Mechanical / Controls System

    NA

    NA

    BIO

    Start-up & Test Fire Alarm Systems

    NA

    NA

    BIO

    Start-up & Test Lighting

    NA

    NA

    SBB (Lot 8) Concrete

    Strip and Re-Shore – Deck L3N

    Crane

    Noise due to Equipment

    SBB (Lot 8) Concrete

    Pour – Vert L3S

    Concrete Pump

    Noise due to Equipment

    SBB (Lot 8) Concrete

    Strip Walls & Columns – Vert L3S

    Crane

    Noise due to Equipment

    SBB (Lot 8) Concrete

    Install Water Line – Campus Dr POC to SBB POC

    NA

    NA

    SBB (Lot 8) Concrete

    F/R/P Walls at Transformer Yard

    NA

    NA

    SBB (Lot 8) Concrete

    F/R/P Transformer Yard Slab

    NA

    NA

     

    Current and Upcoming Anticipated Closures

    The following shutdown(s)/ closures are anticipated as indicated below. Updates to this schedule will be released weekly in the Project Construction Advisories until the work is complete.  Please contact John Franklin with any specific questions or concerns at john.franklin@ucr.edu.

     

    Description

    Location

    Duration & Date

    Impacted Buildings/ Facilities

    Lot 8

    Lot 8

    Permanently

    Lot 8

    Lot 43

    Lot 43

    Indefinitely

    Lot 43

    Anderson Park

    Anderson Park

    Indefinitely

    Anderson Park

  • 950592 UCR SBB - Construction Alert #48

    Current Weeks

    Construction Activities

     

    Location

    Activity

    Equipment Used

    Anticipated Disturbance

    BIO

    Parapet Coping / Flashing / Louvers

    NA

    NA

    BIO

    Pull Wire from transformer to Panels

    NA

    NA

    BIO

    Hook-up and Terminate Transformer

    NA

    NA

    BIO

    Hook-up and Terminate Condensing Units

    NA

    NA

    BIO

    Install Walk-in Cooler

    NA

    NA

    BIO

    Install Casework

    NA

    NA

    BIO

    Install Plumbing Fixtures

    NA

    NA

    SBB (Lot 8) Concrete

    Deck Depressions – Deck L3N

    NA

    NA

    SBB (Lot 8) Concrete

    QC / Inspection – Deck L3N

    NA

    NA

    SBB (Lot 8) Concrete

    Pour – Deck L3N

    Concrete Pumps

    Noise Due to Equipment

    SBB (Lot 8) Concrete

    Strip Edge Form and Transfer Beams – Deck L3N

    Crane

    Noise due to Equipment

    SBB (Lot 8) Concrete

    Cure for Stress – Deck L3N

    NA

    NA

    SBB (Lot 8) Concrete

    Install Embeds – Deck L3S

    NA

    NA

    SBB (Lot 8) Concrete

    MEP Sleeves and Inserts – Deck L3S

    NA

    NA

    SBB (Lot 8) Concrete

    Layout Walls and Columns – Vert L3N

    NA

    NA

    SBB (Lot 8) Concrete

    One Side Form Walls and Columns – Vert L3N

    NA

    NA

    SBB (Lot 8) Concrete

    Rebar / PT Cables – Deck L3S

    Crane

    Noise due to Equipment

     

    Week of October 16, 2023

    Construction Activities 

     

    Location

    Activity

    Equipment Used

    Anticipated Disturbance

    BIO

    Install HVAC Trim

    NA

    NA

    BIO

    Install Fire Alarm Devices and Trim

    NA

    NA

    BIO

    Install Light Fixtures

    NA

    NA

    BIO

    Install Site Furnishings

    NA

    NA

    BIO

    Landscape and Irrigation

    Mini-excavator

    Noise due to Equipment

    BIO

    Install Bio-Filtration Planter

    Mini-excavator

    Noise due to Equipment

    BIO

    MEPT Startup and Testing

    NA

    NA

    BIO

    Install Walk-in Cooler

    NA

    NA

    SBB (Lot 8) Concrete

    Stress Transfer Beams – Deck L3N

    NA

    NA

    SBB (Lot 8) Concrete

    Rebar – Vert L3N

    Crane

    Noise due to Equipment

    SBB (Lot 8) Concrete

    Layout & Install MEP’s – Vert L3N

    NA

    NA

    SBB (Lot 8) Concrete

    Set Embeds – Vert L3N

    NA

    NA

    SBB (Lot 8) Concrete

    QC / Inspection – Vert L3N

    NA

    NA

    SBB (Lot 8) Concrete

    Close two side Forms – Vert L3N

    Crane

    Noise due to Equipment

    SBB (Lot 8) Concrete

    Deck Depressions – Deck L3S

    NA

    NA

    SBB (Lot 8) Concrete

    QC / Inspection – Deck L3S

    NA

    NA

    SBB (Lot 8) Concrete

    Pour – Deck L3S

    Concrete Pumps

    Noise due to Equipment

    SBB (Lot 8) Concrete

    Strip Edge Form – Deck L3S

    NA

    NA

     

     

     

     

     

    Week of October 23, 2023

    Construction Activities 

     

    Location

    Activity

    Equipment Used

    Anticipated Disturbance

    BIO

    Landscape and Irrigation

    Mini-excavator

    Noise due to Equipment

    BIO

    Install Bio-Filtration Planter

    Mini-excavator

    Noise due to Equipment

    BIO

    Start-up & Test Walk-in Cooler

    NA

    NA

    BIO

    New Water Line to Pump House / POC’s

    NA

    NA

    BIO

    Shutdown and Tie-in Water Line to Pump House

    NA

    NA

    SBB (Lot 8) Concrete

    Pour – Vert L3N

    Concrete Pump

    Noise due to Equipment

    SBB (Lot 8) Concrete

    Strip Walls & Columns – Vert L3N

    Crane

    Noise due to Equipment

    SBB (Lot 8) Concrete

    Stress Transfer Beams – Deck L3S

    NA

    NA

    SBB (Lot 8) Concrete

    Layout & Install MEPs – Vert L3S

    NA

    NA

    SBB (Lot 8) Concrete

    Set Embeds – Vert L3S

    NA

    NA

    SBB (Lot 8) Concrete

    QC/Inspection – Vert L3S

    NA

    NA

    SBB (Lot 8) Concrete

    Close Two Side Forms – Vert L3S

    Crane

    Noise due to Equipment

    SBB (Lot 8) Concrete

    Form Deck – L4S

    NA

    NA

     

    Current and Upcoming Anticipated Closures

    The following shutdown(s)/ closures are anticipated as indicated below. Updates to this schedule will be released weekly in the Project Construction Advisories until the work is complete.  Please contact John Franklin with any specific questions or concerns at john.franklin@ucr.edu.

     

    Description

    Location

    Duration & Date

    Impacted Buildings/ Facilities

    Lot 8

    Lot 8

    Permanently

    Lot 8

    Lot 43

    Lot 43

    Indefinitely

    Lot 43

    Anderson Park

    Anderson Park

    Indefinitely

    Anderson Park

  • 950592 UCR SBB - Construction Alert #47

    Current Weeks

    Construction Activities

    Location

    Activity

    Equipment Used

    Anticipated Disturbance

    BIO

    H/T/F Drywall

    NA

    NA

    BIO

    Set Transformer

    NA

    NA

    BIO

    Set Condensing Units

    NA

    NA

    BIO

    Hook-up and Terminate Transformer

    NA

    NA

    BIO

    Hook-up and Terminate Condensing Units

    NA

    NA

    SBB (Lot 8) Concrete

    Install Embed – Deck L3N

    NA

    NA

    SBB (Lot 8) Concrete

    MEP Sleeves and Inserts - Deck L3N

    NA

    NA

    SBB (Lot 8) Concrete

    Rebar / PT Cables - Deck L3N

    NA

    NA

    SBB (Lot 8) Concrete

    Electrical Rough-in - Deck L3N

    NA

    NA

    SBB (Lot 8) Concrete

    Form Deck - Deck L3S

    Crane

    Noise due to Equipment

    SBB (Lot 8) Concrete

    Edge Form - Deck L3S

    NA

    NA

    SBB (Lot 8)

    F/R/P Manlift Pad

    NA

    NA

    SBB (Lot 8)

    Storm drain

    Backhoe

    Noise due to equipment

     

    Week of October 9, 2023

    Construction Activities 

     

    Location

    Activity

    Equipment Used

    Anticipated Disturbance

    BIO

    Parapet Coping / Flashing / Louvers

    NA

    NA

    BIO

    Pull Wire from transformer to Panels

    NA

    NA

    BIO

    Hook-up and Terminate Transformer

    NA

    NA

    BIO

    Hook-up and Terminate Condensing Units

    NA

    NA

    SBB (Lot 8) Concrete

    Deck Depressions – Deck L3N

    NA

    NA

    SBB (Lot 8) Concrete

    QC / Inspection – Deck L3N

    NA

    NA

    SBB (Lot 8) Concrete

    Pour – Deck L3N

    Concrete Pumps

    Noise Due to Equipment

    SBB (Lot 8) Concrete

    Strip Edge Form and Transfer Beams – Deck L3N

    Crane

    Noise due to Equipment

    SBB (Lot 8) Concrete

    Cure for Stress – Deck L3N

    NA

    NA

    SBB (Lot 8) Concrete

    Install Embeds – Deck L3S

    NA

    NA

    SBB (Lot 8) Concrete

    MEP Sleeves and Inserts – Deck L3S

    NA

    NA

    SBB (Lot 8) Concrete

    Layout Walls and Columns – Vert L3N

    NA

    NA

    SBB (Lot 8) Concrete

    One Side Form Walls and Columns – Vert L3N

    NA

    NA

    SBB (Lot 8) Concrete

    Rebar / PT Cables – Deck L3S

    Crane

    Noise due to Equipment

     

    Week of October 16, 2023

    Construction Activities 

     

    Location

    Activity

    Equipment Used

    Anticipated Disturbance

    BIO

    Install HVAC Trim

    NA

    NA

    BIO

    Install Fire Alarm Devices and Trim

    NA

    NA

    BIO

    Install Light Fixtures

    NA

    NA

    BIO

    Install Site Furnishings

    NA

    NA

    BIO

    Landscape and Irrigation

    NA

    NA

    BIO

    Install Bio-Filtration Planter

    NA

    NA

    BIO

    MEPT Startup and Testing

    NA

    NA

    SBB (Lot 8) Concrete

    Stress Transfer Beams – Deck L3N

    NA

    NA

    SBB (Lot 8) Concrete

    Rebar – Vert L3N

    Crane

    Noise due to Equipment

    SBB (Lot 8) Concrete

    Layout & Install MEP’s – Vert L3N

    NA

    NA

    SBB (Lot 8) Concrete

    Set Embeds – Vert L3N

    NA

    NA

    SBB (Lot 8) Concrete

    QC / Inspection – Vert L3N

    NA

    NA

    SBB (Lot 8) Concrete

    Close two side Forms – Vert L3N

    Crane

    Noise due to Equipment

    SBB (Lot 8) Concrete

    Deck Depressions – Deck L3S

    NA

    NA

    SBB (Lot 8) Concrete

    QC / Inspection – Deck L3S

    NA

    NA

    SBB (Lot 8) Concrete

    Pour – Deck L3S

    Concrete Pumps

    Noise due to Equipment

    SBB (Lot 8) Concrete

    Strip Edge Form – Deck L3S

    NA

    NA

     

    Current and Upcoming Anticipated Closures

    The following shutdown(s)/ closures are anticipated as indicated below. Updates to this schedule will be released weekly in the Project Construction Advisories until the work is complete.  Please contact John Franklin with any specific questions or concerns at john.franklin@ucr.edu.

     

    Description

    Location

    Duration & Date

    Impacted Buildings/ Facilities

    Lot 8

    Lot 8

    Permanently

    Lot 8

    Lot 43

    Lot 43

    Indefinitely

    Lot 43

    Anderson Park

    Anderson Park

    Indefinitely

    Anderson Park

  • 950592 UCR SBB - Construction Alert #46

    Current Weeks

    Construction Activities

     

    Location

    Activity

    Equipment Used

    Anticipated Disturbance

    BIO

    In-Wall & Overhead Electrical Rough-in

    NA

    NA

    BIO

    Pull Electrical and Low Voltage Wire

    NA

    NA

    BIO

    Fine Grade for Finish Site Work

    Heavy Equipment

    Noise due to Equipment

    BIO

    F/R/P Equipment Pads

    NA

    NA

    BIO

    F/R/P New Flatwork to Tie Into Existing

    NA

    NA

    SBB (Lot 8) Concrete

    Strip Walls and Columns – Vertical L2N

    NA

    NA

    SBB (Lot 8) Concrete

    Set Embeds - Vertical L2S

    NA

    NA

    SBB (Lot 8) Concrete

    QC Inspection - Vertical L2S

    NA

    NA

    SBB (Lot 8) Concrete

    Close two side forms - Vertical L2S

    Crane

    Noise due to Equipment

    SBB (Lot 8) Concrete

    Pour  - Vertical L2S

    Concrete Pump

    Noise due to Equipment

    SBB (Lot 8) Concrete

    Strip walls & Columns  - Vertical L2S

    Crane

    Noise due to Equipment

    SBB (Lot 8) Concrete

    Form Deck – Deck L3N

    Crane

    Noise due to Equipment

    SBB (Lot 8) Concrete

    Edge Form – Deck L3N

    NA

    NA

     

    Week of October 2, 2023

    Construction Activities 

     

    Location

    Activity

    Equipment Used

    Anticipated Disturbance

    BIO

    H/T/F Drywall

    NA

    NA

    BIO

    Set Transformer

    NA

    NA

    BIO

    Set Condensing Units

    NA

    NA

    BIO

    Hook-up and Terminate Transformer

    NA

    NA

    BIO

    Hook-up and Terminate Condensing Units

    NA

    NA

    SBB (Lot 8) Concrete

    Install Embed – Deck L3N

    NA

    NA

    SBB (Lot 8) Concrete

    MEP Sleeves and Inserts - Deck L3N

    NA

    NA

    SBB (Lot 8) Concrete

    Rebar / PT Cables - Deck L3N

    NA

    NA

    SBB (Lot 8) Concrete

    Electrical Rough-in - Deck L3N

    NA

    NA

    SBB (Lot 8) Concrete

    Form Deck - Deck L3S

    Crane

    Noise due to Equipment

    SBB (Lot 8) Concrete

    Edge Form - Deck L3S

    NA

    NA

    SBB (Lot 8)

    F/R/P Manlift Pad

    NA

    NA

     

    Week of October 9, 2023

    Construction Activities 

     

    Location

    Activity

    Equipment Used

    Anticipated Disturbance

    BIO

    Parapet Coping / Flashing / Louvers

    NA

    NA

    BIO

    Pull Wire from transformer to Panels

    NA

    NA

    BIO

    Hook-up and Terminate Transformer

    NA

    NA

    BIO

    Hook-up and Terminate Condensing Units

    NA

    NA

    SBB (Lot 8) Concrete

    Deck Depressions – Deck L3N

    NA

    NA

    SBB (Lot 8) Concrete

    QC / Inspection – Deck L3N

    NA

    NA

    SBB (Lot 8) Concrete

    Pour – Deck L3N

    Concrete Pumps

    Noise Due to Equipment

    SBB (Lot 8) Concrete

    Strip Edge Form and Transfer Beams – Deck L3N

    Crane

    Noise due to Equipment

    SBB (Lot 8) Concrete

    Cure for Stress – Deck L3N

    NA

    NA

    SBB (Lot 8) Concrete

    Instll Embeds – Deck L3S

    NA

    NA

    SBB (Lot 8) Concrete

    MEP Sleeves and Inserts – Deck L3S

    NA

    NA

    SBB (Lot 8) Concrete

    Rebar / PT Cables – Deck L3S

    Crane

    Noise due to Equipment

     

    Current and Upcoming Anticipated Closures

    The following shutdown(s)/ closures are anticipated as indicated below. Updates to this schedule will be released weekly in the Project Construction Advisories until the work is complete.  Please contact John Franklin with any specific questions or concerns at john.franklin@ucr.edu.

     

    Description

    Location

    Duration & Date

    Impacted Buildings/ Facilities

    Lot 8

    Lot 8

    Permanently

    Lot 8

    Lot 43

    Lot 43

    Indefinitely

    Lot 43

    Anderson Park

    Anderson Park

    Indefinitely

    Anderson Park

  • 950592 UCR SBB - Construction Alert #45

    Current Weeks

    Construction Activities

    Location

    Activity

    Equipment Used

    Anticipated Disturbance

    BIO

    Parapet Coping/Flashing/Louvers

    NA

    NA

    BIO

    Downspouts

    NA

    NA

    BIO

    In-Wall and overhead plumbing work

    NA

    NA

    BIO

    Set fan coil units

    NA

    NA

    SBB (Lot 8) Concrete

    Strip & Re-Shore – Deck L2N

    Crane

    Noise due to Equipment

    SBB (Lot 8) Concrete

    Layout and Install MEP’s – Vertical L2N

    NA

    NA

    SBB (Lot 8) Concrete

    Set Embeds – Vertical L2N

    NA

    NA

    SBB (Lot 8) Concrete

    QC / Inspection– Vertical L2N

    NA

    NA

    SBB (Lot 8) Concrete

    Close Two Side Forms– Vertical L2N

    Crane

    Noise due to Equipment

    SBB (Lot 8) Concrete

    Pour– Vertical L2N

    Concrete Pumps

    Noise due to equipment

    SBB (Lot 8) Concrete

    Pour – Deck L2S

    Concrete Pumps

    Noise due to equipment

    SBB (Lot 8) Concrete

    Strip Edge Form – Deck L2S

    NA

    NA

    SBB (Lot 8) Concrete

    Stress Transfer Beams– Deck L2S

    NA

    NA

    SBB (Lot 8) Concrete

    Layout Walls and Columns – Vert L2S

    NA

    NA

    SBB (Lot 8) Concrete

    One side form walls and columns – Vert L2S

    Crane

    Noise due to Equipment

    SBB (Lot 8) Concrete

    Rebar – Vert L2S

    NA

    NA

    SBB (Lot 8) Concrete

    Layout and Install MEP’s – Vert L2S

    NA

    NA

     

    Week of September 25, 2023

    Construction Activities 

     

    Location

    Activity

    Equipment Used

    Anticipated Disturbance

    BIO

    In-Wall & Overhead Electrical Rough-in

    NA

    NA

    BIO

    Pull Electrical and Low Voltage Wire

    NA

    NA

    BIO

    Fine Grade for Finish Site Work

    Heavy Equipment

    Noise due to Equipment

    BIO

    F/R/P Equipment Pads

    NA

    NA

    BIO

    F/R/P New Flatwork to Tie Into Existing

    NA

    NA

    SBB (Lot 8) Concrete

    Strip Walls and Columns – Vertical L2N

    NA

    NA

    SBB (Lot 8) Concrete

    Set Embeds - Vertical L2S

    NA

    NA

    SBB (Lot 8) Concrete

    QC Inspection - Vertical L2S

    NA

    NA

    SBB (Lot 8) Concrete

    Close two side forms - Vertical L2S

    Crane

    Noise due to Equipment

    SBB (Lot 8) Concrete

    Pour  - Vertical L2S

    Concrete Pump

    Noise due to Equipment

    SBB (Lot 8) Concrete

    Strip walls & Columns  - Vertical L2S

    Crane

    Noise due to Equipment

    SBB (Lot 8) Concrete

    Form Deck – Deck L3N

    Crane

    Noise due to Equipment

    SBB (Lot 8) Concrete

    Edge Form – Deck L3N

    NA

    NA

     

    Week of October 2, 2023

    Construction Activities 

     

    Location

    Activity

    Equipment Used

    Anticipated Disturbance

    BIO

    H/T/F Drywall

    NA

    NA

    BIO

    Set Transformer

    NA

    NA

    BIO

    Set Condensing Units

    NA

    NA

    BIO

    Hook-up and Terminate Transformer

    NA

    NA

    BIO

    Hook-up and Terminate Condensing Units

    NA

    NA

    SBB (Lot 8) Concrete

    Install Embed – Deck L3N

    NA

    NA

    SBB (Lot 8) Concrete

    MEP Sleeves and Inserts - Deck L3N

    NA

    NA

    SBB (Lot 8) Concrete

    Rebar / PT Cables - Deck L3N

    NA

    NA

    SBB (Lot 8) Concrete

    Electrical Rough-in - Deck L3N

    NA

    NA

    SBB (Lot 8) Concrete

    Form Deck - Deck L3S

    Crane

    Noise due to Equipment

    SBB (Lot 8) Concrete

    Edge Form - Deck L3S

    NA

    NA

    SBB (Lot 8)

    F/R/P Manlift Pad

    NA

    NA

     

    Current and Upcoming Anticipated Closures

    The following shutdown(s)/ closures are anticipated as indicated below. Updates to this schedule will be released weekly in the Project Construction Advisories until the work is complete.  Please contact John Franklin with any specific questions or concerns at john.franklin@ucr.edu.

     

    Description

    Location

    Duration & Date

    Impacted Buildings/ Facilities

    Lot 8

    Lot 8

    Permanently

    Lot 8

    Lot 43

    Lot 43

    Indefinitely

    Lot 43

    Anderson Park

    Anderson Park

    Indefinitely

    Anderson Park

  • 950592 UCR SBB - Construction Alert #44

    Current Weeks

    Construction Activities

    Location

    Activity

    Equipment Used

    Anticipated Disturbance

    BIO

    Install Metal Decking

    Gradall

    Noise due to equipment

    BIO

    Framing and Insulation

    Gradall

    Noise due to equipment

    SBB (Lot 8) Concrete

    Deck Pour – L2N

    Concrete Pumps

    Noise due to equipment

    SBB (Lot 8) Concrete

    Strip Edge Form – L2N

    NA

    NA

    SBB (Lot 8) Concrete

    Layout Walls and Columns – L2N

    NA

    NA

    SBB (Lot 8) Concrete

    Rebar – L2N

    Crane

    Noise due to Equipment

    SBB (Lot 8) Concrete

    Layout and Install MEPs – L2N

    NA

    NA

    SBB (Lot 8) Concrete

    Set Embeds – L2N

    NA

    NA

    SBB (Lot 8) Concrete

    Electrical Rough-in – L2S

    NA

    NA

    SBB (Lot 8) Concrete

    Deck Pour – L2S

    Concrete Pumps

    Noise due to equipment

    SBB (Lot 8) Concrete

    Deck Depressions – L2S

    NA

    NA

    SBB (Lot 8) Concrete

    Install Embeds – L2S

    N/A

    N/A

    SBB (Lot 8) Concrete

    Install Embeds – L2S

    N/A

    N/A

    SBB (Lot 8) Concrete

    Rebar / PT Cables – L2S

    Crane

    Noise due to Equipment

     

    Week of September 18, 2023

    Construction Activities 

    Location

    Activity

    Equipment Used

    Anticipated Disturbance

    BIO

    Parapet Coping/Flashing/Louvers

    NA

    NA

    BIO

    Downspouts

    NA

    NA

    BIO

    In-Wall and overhead plumbing work

    NA

    NA

    BIO

    Set fan coil units

    NA

    NA

    SBB (Lot 8) Concrete

    Strip & Re-Shore – Deck L2N

    Crane

    Noise due to Equipment

    SBB (Lot 8) Concrete

    Layout and Install MEP’s – Vertical L2N

    NA

    NA

    SBB (Lot 8) Concrete

    Set Embeds – Vertical L2N

    NA

    NA

    SBB (Lot 8) Concrete

    QC / Inspection– Vertical L2N

    NA

    NA

    SBB (Lot 8) Concrete

    Close Two Side Forms– Vertical L2N

    Crane

    Noise due to Equipment

    SBB (Lot 8) Concrete

    Pour– Vertical L2N

    Concrete Pumps

    Noise due to equipment

    SBB (Lot 8) Concrete

    Pour – Deck L2S

    Concrete Pumps

    Noise due to equipment

    SBB (Lot 8) Concrete

    Strip Edge Form – Deck L2S

    NA

    NA

    SBB (Lot 8) Concrete

    Stress Transfer Beams– Deck L2S

    NA

    NA

    SBB (Lot 8) Concrete

    Layout Walls and Columns – Vert L2S

    NA

    NA

    SBB (Lot 8) Concrete

    One side form walls and columns – Vert L2S

    Crane

    Noise due to Equipment

    SBB (Lot 8) Concrete

    Rebar – Vert L2S

    NA

    NA

    SBB (Lot 8) Concrete

    Layout and Install MEP’s – Vert L2S

    NA

    NA

     

    Week of September 25, 2023

    Construction Activities 

    Location

    Activity

    Equipment Used

    Anticipated Disturbance

    BIO

    In-Wall & Overhead Electrical Rough-in

    NA

    NA

    BIO

    Pull Electrical and Low Voltage Wire

    NA

    NA

    BIO

    Fine Grade for Finish Site Work

    Heavy Equipment

    Noise due to Equipment

    BIO

    F/R/P Equipment Pads

    NA

    NA

    BIO

    F/R/P New Flatwork to Tie Into Existing

    NA

    NA

    SBB (Lot 8) Concrete

    Strip Walls and Columns – Vertical L2N

    NA

    NA

    SBB (Lot 8) Concrete

    Set Embeds - Vertical L2S

    NA

    NA

    SBB (Lot 8) Concrete

    QC Inspection - Vertical L2S

    NA

    NA

    SBB (Lot 8) Concrete

    Close two side forms - Vertical L2S

    Crane

    Noise due to Equipment

    SBB (Lot 8) Concrete

    Pour  - Vertical L2S

    Concrete Pump

    Noise due to Equipment

    SBB (Lot 8) Concrete

    Strip walls & Columns  - Vertical L2S

    Crane

    Noise due to Equipment

    SBB (Lot 8) Concrete

    Form Deck – Deck L3N

    Crane

    Noise due to Equipment

    SBB (Lot 8) Concrete

    Edge Form – Deck L3N

    NA

    NA

     

    Current and Upcoming Anticipated Closures

    The following shutdown(s)/ closures are anticipated as indicated below. Updates to this schedule will be released weekly in the Project Construction Advisories until the work is complete.  Please contact John Franklin with any specific questions or concerns at john.franklin@ucr.edu.

    Description

    Location

    Duration & Date

    Impacted Buildings/ Facilities

    Lot 8

    Lot 8

    Permanently

    Lot 8

    Lot 43

    Lot 43

    Indefinitely

    Lot 43

    Anderson Park

    Anderson Park

    Indefinitely

    Anderson Park

  • 950592 UCR SBB - Construction Alert #43

    Current Weeks

    Construction Activities

    Location

    Activity

    Equipment Used

    Anticipated Disturbance

    BIO

    Concrete

    Pour SOG

    Concrete Pump

    Noise due to Equipment

    BIO

    Backfill

    Mini-Excavator

    Noise due to Equipment

    BIO

    Erect Steel Roof Structure

    N/A

    N/A

    SBB (Lot 8) Concrete

    MEP Sleeves and Inserts – L2N

    N/A

    N/A

    SBB (Lot 8) Concrete

    Rebar / PT Cables – L2N

    Crane

    Noise due to Equipment

    SBB (Lot 8) Concrete

    Electrical Rough-in – L2N

    N/A

    N/A

    SBB (Lot 8) Concrete

    Deck Depressions – L2N

    N/A

    N/A

    SBB (Lot 8) Concrete

    Edge Form – L2S

    N/A

    N/A

    SBB (Lot 8) Concrete

    QC / Inspection – L2N

    N/A

    N/A

    SBB (Lot 8) Concrete

    Edge Form L2S

    N/A

    N/A

    SBB (Lot 8) Concrete

    Install Embeds – L2S

    N/A

    N/A

    SBB (Lot 8) Concrete

    MEP Sleeves and Inserts – L2S

    N/A

    N/A

    SBB (Lot 8) Concrete

    Rebar / PT Cables – L2S

    Crane

    Noise due to Equipment

     

    Week of September 11, 2023

    Construction Activities 

    Location

    Activity

    Equipment Used

    Anticipated Disturbance

    BIO

    Install Metal Decking

    Gradall

    Noise due to equipment

    SBB (Lot 8) Concrete

    Deck Pour – L2N

    Concrete Pumps

    Noise due to equipment

    SBB (Lot 8) Concrete

    Strip Edge Form – L2N

    NA

    NA

    SBB (Lot 8) Concrete

    Layout Walls and Columns – L2N

    NA

    NA

    SBB (Lot 8) Concrete

    Rebar – L2N

    Crane

    Noise due to Equipment

    SBB (Lot 8) Concrete

    Layout and Install MEPs – L2N

    NA

    NA

    SBB (Lot 8) Concrete

    Set Embeds – L2N

    NA

    NA

    SBB (Lot 8) Concrete

    Electrical Rough-in – L2S

    NA

    NA

    SBB (Lot 8) Concrete

    Deck Pour – L2S

    Concrete Pumps

    Noise due to equipment

    SBB (Lot 8) Concrete

    Deck Depressions – L2S

    NA

    NA

     

    Week of September 18, 2023

    Construction Activities 

    Location

    Activity

    Equipment Used

    Anticipated Disturbance

    BIO

    Install Door Frames

    NA

    NA

    BIO

    Install Doors and Hardware

    NA

    NA

    BIO

    Install Roofing System

    Gradall

    Noise due to equipment

    BIO

    Install Electrical Panels

    NA

    NA

    SBB (Lot 8) Concrete

    Strip & Re-Shore – L2N

    Crane

    Noise due to Equipment

    SBB (Lot 8) Concrete

    Vertical Pour – L2N

    Concrete Pumps

    Noise due to equipment

    SBB (Lot 8) Concrete

    Strip Walls and Columns – L2N

    Crane

    Noise due to Equipment

    SBB (Lot 8) Concrete

    Rebar – L2S

    Crane

    Noise due to Equipment

    SBB (Lot 8) Concrete

    Layout and Install MEPs – L2S

    NA

    NA

    SBB (Lot 8) Concrete

    Set Embeds – L2S

    NA

    NA

    SBB (Lot 8) Concrete

    Form Deck – L3N

    NA

    NA

     

     

    Current and Upcoming Anticipated Closures

    The following shutdown(s)/ closures are anticipated as indicated below. Updates to this schedule will be released weekly in the Project Construction Advisories until the work is complete.  Please contact John Franklin with any specific questions or concerns at john.franklin@ucr.edu.

    Description

    Location

    Duration & Date

    Impacted Buildings/ Facilities

    Lot 8

    Lot 8

    Permanently

    Lot 8

    Lot 43

    Lot 43

    Indefinitely

    Lot 43

    Anderson Park

    Anderson Park

    Indefinitely

    Anderson Park

  • 950592 UCR SBB - Construction Alert #42

    Current Weeks

    Construction Activities

     

    Location

    Activity

    Equipment Used

    Anticipated Disturbance

    BIO

    Concrete

    Fine Grade – SOG

    N/A

    N/A

    BIO

    Concrete

    Vapor Barrier – SOG

    N/A

    N/A

    BIO

    Concrete

    Rebar – SOG

    Gradall

    Noise due to Equipment

    BIO

    Concrete

    QC/ Inspection – SOG

    N/A

    N/A

    SBB (Lot 8) Concrete

    Pour SOG 2 – L1S

    Concrete Pump

    Noise due to Equipment

    SBB (Lot 8) Sitework

    Chilled Water

    Mini-excavator

    Noise due to Equipment

    SBB (Lot 8) Concrete

    Edge Form

    N/A

    N/A

     

    SBB (Lot 8) Concrete

    Install Embeds

    N/A

    N/A

    SBB (Lot 8) Concrete

    MEP Sleeves & Inserts

    N/A

    N/A

    SBB (Lot 8) Concrete

    Rebar / PT Cables

    Crane

    Noise due to Equipment

    SBB (Lot 8) Concrete

    Electrical Rough-in

    N/A

    N/A

    SBB (Lot 8) Concrete

    Deck Depressions

    N/A

    N/A

     

    Week of September 4, 2023

    Construction Activities 

     

    Location

    Activity

    Equipment Used

    Anticipated Disturbance

    BIO

    Concrete

    Pour SOG

    Concrete Pump

    Noise due to Equipment

    BIO

    Backfill

    Mini-Excavator

    Noise due to Equipment

    BIO

    Erect Steel Roof Structure

    N/A

    N/A

    SBB (Lot 8) Concrete

    MEP Sleeves and Inserts – L2N

    N/A

    N/A

    SBB (Lot 8) Concrete

    Rebar / PT Cables – L2N

    Crane

    Noise due to Equipment

    SBB (Lot 8) Concrete

    Electrical Rough-in – L2N

    N/A

    N/A

    SBB (Lot 8) Concrete

    Deck Depressions – L2N

    N/A

    N/A

    SBB (Lot 8) Concrete

    Edge Form – L2S

    N/A

    N/A

    SBB (Lot 8) Concrete

    QC / Inspection – L2N

    N/A

    N/A

    SBB (Lot 8) Concrete

    Edge Form L2S

    N/A

    N/A

    SBB (Lot 8) Concrete

    Install Embeds – L2S

    N/A

    N/A

    SBB (Lot 8) Concrete

    MEP Sleeves and Inserts – L2S

    N/A

    N/A

    SBB (Lot 8) Concrete

    Rebar / PT Cables – L2S

    Crane

    Noise due to Equipment

     

    Week of September 11, 2023

    Construction Activities 

     

    Location

    Activity

    Equipment Used

    Anticipated Disturbance

    Bio

    Install Metal Decking

    NA

    NA

    SBB (Lot 8) Concrete

    Pour – L2N

    Concrete Pumps

    Noise due to equipment

    SBB (Lot 8) Concrete

    Strip Edge Form – L2N

    NA

    NA

    SBB (Lot 8) Concrete

    Layout Walls and Columns – L2N

    NA

    NA

    SBB (Lot 8) Concrete

    Rebar – L2N

    NA

    NA

    SBB (Lot 8) Concrete

    Layout and Install MEPs – L2N

    NA

    NA

    SBB (Lot 8) Concrete

    Set Embeds – L2N

    NA

    NA

    SBB (Lot 8) Concrete

    Electrical Rough-in – L2S

    NA

    NA

    SBB (Lot 8) Concrete

    Deck Depressions – L2S

    NA

    NA

     

    Current and Upcoming Anticipated Closures

    The following shutdown(s)/ closures are anticipated as indicated below. Updates to this schedule will be released weekly in the Project Construction Advisories until the work is complete.  Please contact John Franklin with any specific questions or concerns at john.franklin@ucr.edu.

     

    Description

    Location

    Duration & Date

    Impacted Buildings/ Facilities

    Lot 8

    Lot 8

    Permanently

    Lot 8

    Lot 43

    Lot 43

    Indefinitely

    Lot 43

    Anderson Park

    Anderson Park

    Indefinitely

    Anderson Park

  • 950592 UCR SBB - Construction Alert #41

    Current Weeks

    Construction Activities

     

    Location

    Activity

    Equipment Used

    Anticipated Disturbance

    BIO

    Underslab Utilities

    Install Underslab Plumbing Rough-in

    N/A

    N/A

    BIO

    Underslab Utilities

    Install Underslab Electrical Rough-in

    N/A

    N/A

    SBB (Lot 8)

    Sitework

    Chilled Water

    Excavator

    Noise due to Equipment

    SBB (Lot 8) Concrete

    Set Screeds – SOG North

    N/A

    N/A

     

    SBB (Lot 8) Concrete

    Q/C Inspection – SOG North

    N/A

    N/A

    SBB (Lot 8) Concrete

    Rebar – SOG North

    Crane

    Noise due to Equipment

    SBB (Lot 8) Concrete

    Pour – SOG North

    Concrete Pumps and Trucks

    Noise due to Equipment

    SBB (Lot 8) Concrete

    Edge Form / Bulkhead – SOG South

    N/A

    N/A

    SBB (Lot 8) Concrete

    Rebar – SOG South

    Crane

    Noise due to Equipment

    SBB (Lot 8) Concrete

    QC/ Inspection – SOG South

    N/A

    N/A

    SBB (Lot 8) Concrete

    Pour – SOG South

    Concrete Pumps and Trucks

    Noise due to Equipment

    SBB (Lot 8) Concrete

    Strip Edge Form / Bulkhead – SOG South

    N/A

    N/A

    SBB (Lot 8) Concrete

    Form Deck

    N/A

    N/A

    SBB (Lot 8) Concrete

    Edge Form

    N/A

    N/A

     

    Week of August 28, 2023

    Construction Activities 

     

    Location

    Activity

    Equipment Used

    Anticipated Disturbance

    BIO

    Concrete

    Fine Grade – SOG

    N/A

    N/A

    BIO

    Concrete

    Vapor Barrier – SOG

    N/A

    N/A

    BIO

    Concrete

    Rebar – SOG

    Gradall

    Noise due to Equipment

    BIO

    Concrete

    QC/ Inspection – SOG

    N/A

    N/A

    SBB (Lot 8) Concrete

    Pour SOG 2 – L1S

    Concrete Pump

    Noise due to Equipment

    SBB (Lot 8) Sitework

    Chilled Water

    Mini-excavator

    Noise due to Equipment

    SBB (Lot 8) Concrete

    Edge Form

    N/A

    N/A

     

    SBB (Lot 8) Concrete

    Install Embeds

    N/A

    N/A

    SBB (Lot 8) Concrete

    MEP Sleeves & Inserts

    N/A

    N/A

    SBB (Lot 8) Concrete

    Rebar / PT Cables

    Crane

    Noise due to Equipment

    SBB (Lot 8) Concrete

    Electrical Rough-in

    N/A

    N/A

    SBB (Lot 8) Concrete

    Deck Depressions

    N/A

    N/A

     

    Week of September 4, 2023

    Construction Activities 

     

    Location

    Activity

    Equipment Used

    Anticipated Disturbance

    BIO

    Concrete

    Pour SOG

    Concrete Pump

    Noise due to Equipment

    BIO

    Erect Steel Roof Structure

    N/A

    N/A

    SBB (Lot 8) Concrete

    MEP Sleeves and Inserts – L2N

    N/A

    N/A

    SBB (Lot 8) Concrete

    Rebar / PT Cables – L2N

    Crane

    Noise due to Equipment

    SBB (Lot 8) Concrete

    Electrical Rough-in – L2N

    N/A

    N/A

    SBB (Lot 8) Concrete

    Deck Depressions – L2N

    N/A

    N/A

    SBB (Lot 8) Concrete

    Edge Form – L2S

    N/A

    N/A

     

    Current and Upcoming Anticipated Closures

    The following shutdown(s)/ closures are anticipated as indicated below. Updates to this schedule will be released weekly in the Project Construction Advisories until the work is complete.  Please contact John Franklin with any specific questions or concerns at john.franklin@ucr.edu.

     

    Description

    Location

    Duration & Date

    Impacted Buildings/ Facilities

    Lot 8

    Lot 8

    Permanently

    Lot 8

    Lot 43

    Lot 43

    Indefinitely

    Lot 43

    Anderson Park

    Anderson Park

    Indefinitely

    Anderson Park

  • 950592 UCR SBB - Construction Alert #40

    Current Weeks

    Construction Activities

     

    Location

    Activity

    Equipment Used

    Anticipated Disturbance

    BIO

    CMU Walls

    Set Scaffold and Erect CMU Block Structure

    Gradall

    Noise due to Equipment

    BIO

    CMU Walls

    Set Anchor Bolts

    N/A

    N/A

    BIO

    CMU Walls

    Grout/Clean-Up/Remove Scaffold

    N/A

    N/A

    SBB (Lot 8)

    Concrete

    Install Vapor Barrier – SOG North

    N/A

    N/A

     

    SBB (Lot 8) Concrete

    Install Electrical Rough-in – SOG North

    N/A

    N/A

    SBB (Lot 8) Concrete

    Rebar – SOG North

    Crane

    Noise due to Equipment

    SBB (Lot 8)

    Concrete

    Underslab Plumbing Rough-In – SOG South

    N/A

    N/A

    SBB (Lot 8)

    Concrete

    Underslab Electrical Rough-In – SOG South

    N/A       

    N/A

    SBB (Lot 8)

    Concrete

    Fine Grade – SOG South

    N/A

    N/A

    SBB (Lot 8)

    Concrete

    Install Vapor Barrier – SOG South

    N/A

    N/A

     

    Week of August 21, 2023

    Construction Activities 

     

    Location

    Activity

    Equipment Used

    Anticipated Disturbance

    BIO

    Underslab Utilities

    Install Underslab Plumbing Rough-in

    N/A

    N/A

    BIO

    Underslab Utilities

    Install Underslab Electrical Rough-in

    N/A

    N/A

    SBB (Lot 8)

    Sitework

    Chilled Water

    Excavator

    Noise due to Equipment

    SBB (Lot 8) Concrete

    Set Screeds – SOG North

    N/A

    N/A

     

    SBB (Lot 8) Concrete

    Q/C Inspection – SOG North

    N/A

    N/A

    SBB (Lot 8) Concrete

    Rebar – SOG North

    Crane

    Noise due to Equipment

    SBB (Lot 8) Concrete

    Pour – SOG North

    Concrete Pumps and Trucks

    Noise due to Equipment

    SBB (Lot 8) Concrete

    Edge Form / Bulkhead – SOG South

    N/A

    N/A

    SBB (Lot 8) Concrete

    Rebar – SOG South

    Crane

    Noise due to Equipment

    SBB (Lot 8) Concrete

    QC/ Inspection – SOG South

    N/A

    N/A

    SBB (Lot 8) Concrete

    Pour – SOG South

    Concrete Pumps and Trucks

    Noise due to Equipment

    SBB (Lot 8) Concrete

    Strip Edge Form / Bulkhead – SOG South

    N/A

    N/A

    SBB (Lot 8) Concrete

    Form Deck

    N/A

    N/A

    SBB (Lot 8) Concrete

    Edge Form

    N/A

    N/A

     

    Week of August 28, 2023

    Construction Activities 

     

    Location

    Activity

    Equipment Used

    Anticipated Disturbance

    BIO

    Concrete

    Fine Grade – SOG

    N/A

    N/A

    BIO

    Concrete

    Vapor Barrier – SOG

    N/A

    N/A

    BIO

    Concrete

    Rebar – SOG

    Gradall

    Noise due to Equipment

    BIO

    Concrete

    QC/ Inspection – SOG

    N/A

    N/A

    SBB (Lot 8) Sitework

    Chilled Water

    Mini-excavator

    Noise due to Equipment

    SBB (Lot 8) Concrete

    Edge Form

    N/A

    N/A

     

    SBB (Lot 8) Concrete

    Install Embeds

    N/A

    N/A

    SBB (Lot 8) Concrete

    MEP Sleeves & Inserts

    N/A

    N/A

    SBB (Lot 8) Concrete

    Rebar / PT Cables

    Crane

    Noise due to Equipment

    SBB (Lot 8) Concrete

    Electrical Rough-in

    N/A

    N/A

    SBB (Lot 8) Concrete

    Deck Depressions

    N/A

    N/A

     

     

    Current and Upcoming Anticipated Closures

    The following shutdown(s)/ closures are anticipated as indicated below. Updates to this schedule will be released weekly in the Project Construction Advisories until the work is complete.  Please contact John Franklin with any specific questions or concerns at john.franklin@ucr.edu.

     

    Description

    Location

    Duration & Date

    Impacted Buildings/ Facilities

    Lot 8

    Lot 8

    Permanently

    Lot 8

    Lot 43

    Lot 43

    Indefinitely

    Lot 43

    Anderson Park

    Anderson Park

    Indefinitely

    Anderson Park

  • 950592 UCR SBB - Construction Alert #39

    Current Weeks

    Construction Activities

    Location

    Activity

    Equipment Used

    Anticipated Disturbance

    BIO

    Underslab Utilities

    Install Underslab Plumbing Rough-In

    N/A

    N/A

    BIO

    Underslab Utilities

    Install Underslab Electrical Rough-In

    N/A

    N/A

    SBB (Lot 8) Concrete

    Install Vapor Barrier – SOG North

    N/A

    N/A

     

    SBB (Lot 8) Concrete

    Edge Form / Bulkhead – SOG North

    N/A

    N/A

    SBB (Lot 8) Concrete

    Rebar – SOG North

    Crane

    Noise due to Equipment

    SBB (Lot 8) Concrete

    Set Screeds – SOG North

    N/A

    N/A

     

    SBB (Lot 8) Concrete

    QC / Inspection – SOG North

     

    N/A

    N/A

    SBB (Lot 8) Concrete

    Pour – SOG North

    Concrete Pumps and Trucks

    Noise due to Equipment

    SBB (Lot 8)

    Concrete

    Underslab Plumbing Rough-In – SOG South

    N/A

    N/A

    SBB (Lot 8)

    Concrete

    Underslab Electrical Rough-In

    N/A       

    N/A

    SBB (Lot 8)

    Concrete

    Backfill Footings, Walls & Columns – SOG South

    Dump Truck

    Noise due to Equipment

     

    Week of August 14, 2023

    Construction Activities 

     

    Location

    Activity

    Equipment Used

    Anticipated Disturbance

    BIO

    CMU Walls

    Set Scaffold & Erect CMU Block Structure

    Forklift

    Noise due to Equipment

    SBB (Lot 8)

    Sitework

    Chilled Water

    Excavator

    Noise due to Equipment

    SBB (Lot 8) Concrete

    Fine Grade – SOG South

    Skid Steer

    Noise due to Equipment

     

    SBB (Lot 8) Concrete

    Install Vapor Barrier – SOG South

    N/A

    N/A

    SBB (Lot 8) Concrete

    Deliver/ Shake Out Elevated Deck Form Work

    Delivery Trucks

    Noise due to Equipment

     

    Week of August 21, 2023

    Construction Activities 

     

    Location

    Activity

    Equipment Used

    Anticipated Disturbance

    BIO

    CMU Walls

    Set Anchor Bolts

    N/A

    N/A

    BIO

    CMU Walls

    Grout / Clean-up / Remove Scaffold CMU Walls

    N/A

    N/A

    SBB (Lot 8) Sitework

    Chilled Water

    Excavator

    Noise due to Equipment

    SBB (Lot 8) Concrete

    Edge Form / Bulkhead – SOG South

    Concrete Pumps and Trucks

    Noise due to Equipment

     

    SBB (Lot 8) Concrete

    Rebar – SOG South

    Crane

    Noise due to Equipment

    SBB (Lot 8) Concrete

    QC/ Inspection – SOG South

    N/A

    N/A

    SBB (Lot 8) Concrete

    Pour – SOG South

    Concrete Pumps and Trucks

    Noise due to Equipment

    SBB (Lot 8) Concrete

    Strip Edge Form / Bulkhead – SOG South

    N/A

    N/A

    SBB (Lot 8) Concrete

    Form Deck

    Crane

    Noise Due to Equipment

    SBB (Lot 8) Concrete

    Edge Form

    N/A

    N/A

     

     

    Current and Upcoming Anticipated Closures

    The following shutdown(s)/ closures are anticipated as indicated below. Updates to this schedule will be released weekly in the Project Construction Advisories until the work is complete.  Please contact John Franklin with any specific questions or concerns at john.franklin@ucr.edu.

     

    Description

    Location

    Duration & Date

    Impacted Buildings/ Facilities

    Lot 8

    Lot 8

    Permanently

    Lot 8

    Lot 43

    Lot 43

    Indefinitely

    Lot 43

    Anderson Park

    Anderson Park

    Indefinitely

    Anderson Park

  • 950592 UCR SBB - Construction Alert #38

    Current Weeks

    Construction Activities

     

    Location

    Activity

    Equipment Used

    Anticipated Disturbance

    BIO

    Foundations

    Excavate Foundations

    Mini-Excavator and Skid Steer

    Noise due to Equipment

    BIO

    Foundations

    Rebar Foundations

    N/A

    N/A

    BIO

    Foundations

    QC/ Inspection Foundations

    N/A

    N/A

    BIO

    Foundations

    Pour Foundations

    Concrete Pumps and Trucks

    Noise due to Equipment

    SBB (Lot 8) Concrete

    Close Two Side Form – Core Wall – Pour 2

    Crane

    Noise due to Equipment

    SBB (Lot 8) Concrete

    Pour – Core Wall – Pour 2

    Concrete Pumps and Trucks

    Noise due to Equipment

     

    SBB (Lot 8) Concrete

    Strip Walls – Core Walls – Pour 2

    Crane

    Noise due to Equipment

    SBB (Lot 8) Concrete

    Shotcrete – Retaining Wall

    Concrete Pumps and Trucks

    Noise due to Equipment

    SBB (Lot 8) Concrete

    Removed Rebound – Retaining Wall

    Crane

    Noise due to Equipment

     

    SBB (Lot 8) Concrete

    Remove Scaffold

     

    N/A

    N/A

    SBB (Lot 8) Concrete

    Backfill Footings, Walls & Columns – SOG North

    Dump Trucks

    Noise due to Equipment

    SBB (Lot 8) Concrete

    Fine Grade – SOG North

    Skid Steer

    Noise due to Equipment

    SBB (Lot 8) Concrete

    Underslab Plumbing Rough-In – SOG South

    N/A

    N/A

    SBB (Lot 8)

    Concrete

    Underslab Electrical Rough-In

    N/A

    N/A

     

    Week of August 7, 2023

    Construction Activities 

     

    Location

    Activity

    Equipment Used

    Anticipated Disturbance

    BIO

    Underslab Utilities

    Install Underslab Plumbing Rough-In

    N/A

    N/A

    BIO

    Underslab Utilities

    Install Underslab Electrical Rough-In

    N/A

    N/A

    SBB (Lot 8) Concrete

    Install Vapor Barrier – SOG North

    N/A

    N/A

     

    SBB (Lot 8) Concrete

    Edge Form / Bulkhead – SOG North

    N/A

    N/A

    SBB (Lot 8) Concrete

    Rebar – SOG North

    Crane

    Noise due to Equipment

    SBB (Lot 8) Concrete

    Set Screeds – SOG North

    N/A

    N/A

     

    SBB (Lot 8) Concrete

    QC / Inspection – SOG North

     

    N/A

    N/A

    SBB (Lot 8) Concrete

    Pour – SOG North

    Concrete Pumps and Trucks

    Noise due to Equipment

    SBB (Lot 8)

    Concrete

    Underslab Plumbing Rough-In – SOG South

    N/A

    N/A

    SBB (Lot 8)

    Concrete

    Underslab Electrical Rough-In

    N/A            

    N/A

    SBB (Lot 8)

    Concrete

    Backfill Footings, Walls & Columns – SOG South

    Dump Truck

    Noise due to Equipment

     

    Week of August 14, 2023

    Construction Activities 

     

    Location

    Activity

    Equipment Used

    Anticipated Disturbance

    BIO

    CMU Walls

    Set Scaffold & Erect CMU Block Structure

    N/A

    N/A

    SBB (Lot 8) Concrete

    Fine Grade – SOG South

    Skid Steer

    Noise due to Equipment

     

    SBB (Lot 8) Concrete

    Install Vapor Barrier – SOG South

    N/A

    N/A

    SBB (Lot 8) Concrete

    Deliver/ Shake Out Elevated Deck Form Work

    Delivery Trucks

    Noise due to Equipment

     

     

    Current and Upcoming Anticipated Closures

    The following shutdown(s)/ closures are anticipated as indicated below. Updates to this schedule will be released weekly in the Project Construction Advisories until the work is complete.  Please contact John Franklin with any specific questions or concerns at john.franklin@ucr.edu.

     

    Description

    Location

    Duration & Date

    Impacted Buildings/ Facilities

    Lot 8

    Lot 8

    Indefinitely

    Lot 8

    Lot 43

    Lot 43

    Indefinitely

    Lot 43

    Anderson Park

    Anderson Park

    Indefinitely

    Anderson Park

  • 950592 UCR SBB - Construction Alert #37

    Current Weeks

    Construction Activities

    Location

    Activity

    Equipment Used

    Anticipated Disturbance

    BIO

    Sitework

    Remove (E) Electrical

    Mini-Excavator and Skid Steer

    Noise due to Equipment

    BIO

    Sitework

    Grade Site & Building Pad

    Mini-Excavator and Skid Steer

    Noise due to Equipment

    BIO

    Sitework

    Building Pad Certification

    N/A

    N/A

    SBB (Lot 8) Sitework

    Pothole Chilled Water

    Excavator

    Noise due to Equipment

     

    SBB (Lot 8) Concrete

    Rebar – Core Walls – Pour 2

    Crane

    Noise due to Equipment

    SBB (Lot 8) Concrete

    One Side Form Walls – Core Wall – Pour 2

    Crane

    Noise due to Equipment

     

    SBB (Lot 8) Concrete

    Layout & Install MEP’s – Core Walls – Pour 2

    N/A

    N/A

    SBB (Lot 8) Concrete

    QC/ Inspection – Core Walls – Pour 2

    N/A

    N/A

    SBB (Lot 8) Concrete

    Set Embeds – Core Wall – Pour 2

    N/A

    N/A

     

    SBB (Lot 8) Concrete

    Close Two Side Forms – Shear Walls & Columns – Pour 3

    Crane

    Noise due to Equipment

    SBB (Lot 8) Concrete

    Pour – Shear Walls & Columns – Pour 3

    Concrete Pumps and Trucks

    Noise due to Equipment

    SBB (Lot 8) Concrete

    Strip Walls – Shear Walls & Columns – Pour 3

    Crane

    Noise due to Equipment

    SBB (Lot 8)

    Concrete

    Set Scaffold – Retaining Wall

    N/A

    N/A

    SBB (Lot 8)

    Concrete

    Underslab Electrical Stub-Up

    N/A

    N/A

     

    Week of July 31, 2023

    Construction Activities 

     

    Location

    Activity

    Equipment Used

    Anticipated Disturbance

    BIO

    Foundation

    Layout Foundation

    N/A

    N/A

    BIO

    Foundation

    Excavate Foundations

    Excavator

    Noise due to Equipment

    BIO

    Foundation

    Rebar Foundations

    N/A

    N/A

    BIO Foundations

    QC/ Inspection Foundations

    N/A

    N/A

     

    BIO Foundations

    Pour Foundations

    Concrete Pumps and Trucks

    Noise due to Equipment

    SBB (Lot 8) Sitework

    Install Chilled Water

    Excavator

    Noise due to Equipment

    SBB (Lot 8) Concrete

    Pour – Core Walls – Pour 2

    Concrete Pumps and Trucks

    Noise due to Equipment

     

    SBB (Lot 8) Concrete

    Strip Walls – Core Walls – Pour 2

    Crane

    Noise due to Equipment

    SBB (Lot 8) Concrete

    Shotcrete Wires – Retaining Wall

    N/A

    N/A

    SBB (Lot 8) Concrete

    Shotcrete – Retaining Wall

    Concrete Pump and Trucks

    Noise due to Equipment

     

    SBB (Lot 8) Concrete

    Remove Rebound – Retaining Wall

     

    Crane

    Noise due to Equipment

    SBB (Lot 8) Concrete

    Remove Scaffold – Retaining Wall

    N/A

    N/A

    SBB (Lot 8)

    Concrete

    Backfill Footings, Walls, & Columns – SOG North

    Dump Trucks

    Noise due to Equipment

    SBB (Lot 8)

    Concrete

    Fine Grade – SOG North

    Skid Steer

    Noise due to Equipment

    SBB (Lot 8)

    Concrete

    Underslab Plumbing Rough-in – SOG South

    N/A

    N/A

    SBB (Lot 8)

    Concrete

    Backfill Footings, Walls, & Columns – SOG South

    Dump Trucks

    Noise due to Equipment

     

    Week of August 07, 2023

    Construction Activities 

     

    Location

    Activity

    Equipment Used

    Anticipated Disturbance

    BIO

    Underslab Utilities

    Install Underslab Utilities Plumbing Rough-In

    N/A

    N/A

    BIO

    Underslab Utilities

    Install Underslab Utilities Electrical Rough-In

    N/A

    N/A

    SBB (Lot 8) Sitework

    Install Chilled Water

    Excavator

    Noise due to Equipment

     

    SBB (Lot 8) Concrete

    Install Vapor Barrier – SOG North

    N/A

    N/A

     

    SBB (Lot 8) Concrete

    Edge Form / Bulkhead – SOG North

    N/A

    N/A

    SBB (Lot 8) Concrete

    Rebar - SOG North

    Crane

    Noise due to Equipment

    SBB (Lot 8) Concrete

    Set Screeds – SOG North

    N/A

    N/A

     

    SBB (Lot 8) Concrete

    QC/ Inspection – SOG North

     

    N/A

    N/A

    SBB (Lot 8) Concrete

    Pour – SOG North

    Concrete pumps and Trucks

    Noise due to Equipment

    SBB (Lot 8)

    Concrete

    Underslab Plumbing Rough-In

    N/A

    N/A

    SBB (Lot 8)

    Concrete

    Underslab Electrical Rough-In – SOG South

    N/A

    N/A

     

    Current and Upcoming Anticipated Closures

    The following shutdown(s)/ closures are anticipated as indicated below. Updates to this schedule will be released weekly in the Project Construction Advisories until the work is complete.  Please contact John Franklin with any specific questions or concerns at john.franklin@ucr.edu.

     

    Description

    Location

    Duration & Date

    Impacted Buildings/ Facilities

    Lot 8

    Lot 8

    Indefinitely

    Lot 8

    Lot 43

    Lot 43

    Indefinitely

    Lot 43

    College Pl

    College Pl

    7/10 – 7/28

    The College Pl loop is a one-way (single lane) road that branches off S Campus Dr. The Southern College Pl Road contains two traffic control operators helping direct traffic both to and from Parking Lot 3. The Northern College Pl Road has been closed.

    Anderson Park

    Anderson Park

    Indefinitely

    Anderson Park

  • 950592 UCR SBB - Construction Alert #36

    Current Weeks

    Construction Activities

     

    Location

    Activity

    Equipment Used

    Anticipated Disturbance

    BIO

    Sitework

    Relocate (E) Steam Line

    Mini-Excavator and Skid Steer

    Noise due to Equipment

     

    BIO

    Sitework

    Test & Backfill Steam Line

    Skid Steer

    Noise due to Equipment

     

    BIO

    Sitework

    Remove (E) Electrical Line

    N/A

    N/A

    SBB (Lot 8) Sitework

    Install Sewer

    Excavator

    Noise due to Equipment

    Partial Lane Closure of South Campus Drive

    SBB (Lot 8) Sitework

    Install Chilled Water

    Excavator

    Noise due to Equipment

     

    SBB (Lot 8) Sitework

    Strip – Column Pour 1

    Crane

    Noise due to Equipment

     

    SBB (Lot 8) Sitework

    Waterblast – Column Pour 1

    Concrete Pressure Washer

    Noise due to Equipment

    SBB (Lot 8) Sitework

    Strip Walls – Shear Walls & Columns – Pour 2

    Crane

    Noise due to Equipment

     

    SBB (Lot 8) Sitework

    Rebar – Shear Walls & Columns – Pour 3

    N/A

    N/A

    SBB (Lot 8) Sitework

    Layout & Install MEP’s – Shear Walls & Columns – Pour 3

    N/A

    N/A

    SBB (Lot 8) Sitework

    Set Embeds – Shear Walls & Columns – Pour 3

    N/A

    N/A

    SBB (Lot 8) Sitework

    QC / Inspection – Shear Walls & Columns – Pour 3

    N/A

    N/A

    SBB (Lot 8) Sitework

    Close Two Side Forms – Shear Walls & Columns – Pour 3

    Crane

    Noise due to Equipment

     

    SBB (Lot 8) Concrete

    Shotcrete – Retaining Wall

    Concrete Pumps and Trucks

    Noise due to equipment

    SBB (Lot 8) Concrete

    Remove Rebound – Retaining Wall

    Skid Steer

    Noise due to Equipment

     

    SBB (Lot 8) Concrete

    Remove Scaffolding – Retaining Wall North

    N/A

    N/A

    SBB (Lot 8) Concrete

    Backfill – Retaining Wall

    Trucks and Excavator

    Noise due to Equipment

    SBB (Lot 8) Sitework

    MEP Layout & Block outs – Retaining Wall

    N/A

    N/A

    SBB (Lot 8) Sitework

    Rebar – Retaining Wall

    N/A

    N/A

    SBB (Lot 8)

    Sitework

    Set Scaffolding – Retaining Wall South

    N/A

    N/A

    SBB (Lot 8)

    Concrete

    Backfill Footings, Walls & Columns – SOG North

    Excavator

    Noise due to Equipment

    SBB (Lot 8)

    Bio-Retention Planter

    Backfill Bio-Retention Planter for Steam Lines

    Excavator

     

    Noise due to Equipment

     

    Week of July 24, 2023

    Construction Activities 

     

    Location

    Activity

    Equipment Used

    Anticipated Disturbance

    BIO

    Sitework

    Remove (E) Electrical

    Mini-Excavator and Skid Steer

    Noise due to Equipment

    BIO

    Sitework

    Grade Site & Building Pad

    N/A

    N/A

    BIO

    Sitework

    Building Pad Certification

    N/A

    N/A

    SBB (Lot 8) Sitework

    Install Chilled Water

    Excavator

    Noise due to Equipment

     

    SBB (Lot 8) Concrete

    Pour – Shear Walls & Columns – Pour 3

    Concrete pumps and Trucks

    Noise due to Equipment

    SBB (Lot 8) Concrete

    Strip Walls – Shear Walls & Columns – Pour 3

    Crane

    Noise due to Equipment

     

    SBB (Lot 8) Concrete

    Shotcrete – Wires

    Concrete pumps and Trucks

    Noise due to Equipment

    SBB (Lot 8) Concrete

    Shotcrete -Retaining Wall

    Shotcrete Pump

    Noise due to Equipment

    SBB (Lot 8) Concrete

    Remove Rebound – Retaining Wall

    Skid Steer

    Noise due to Equipment

     

    SBB (Lot 8) Concrete

    Remove Scaffolding – Retaining Wall

     

    N/A

    N/A

    SBB (Lot 8) Concrete

    Fine Grade – SOG North

    N/A

    N/A

    SBB (Lot 8)

    Concrete

    Install Vapor Barrier – SOG North

    N/A

    N/A

    SBB (Lot 8)

    Concrete

    Edge Form / Bulkhead – SOG North

    N/A

    N/A

    SBB (Lot 8) Concrete

    Rebar – SOG North

    N/A

    N/A

    SBB (Lot 8)

    Concrete

    Underslab Plumbing Rough-in – SOG South

    N/A

    N/A

    SBB (Lot 8)

    Concrete

    Underslab Electrical Rough-in – SOG South

    N/A

    N/A

     

    Week of July 31, 2023

    Construction Activities 

     

    Location

    Activity

    Equipment Used

    Anticipated Disturbance

    BIO

    Foundations

    Layout Foundations

    N/A

    N/A

    BIO

    Foundations

    Excavate Foundations

    Excavator

    Noise due to Equipment

    BIO

    Foundations

    Rebar Foundations

    N/A

    N/A

    BIO

    Foundations

    QC/Inspection Foundations

    N/A

    N/A

    BIO

    Foundations

    Pour Foundations

    Concrete pumps and Trucks

    Noise due to Equipment

    SBB (Lot 8) Sitework

    Install Chilled Water

    Excavator

    Noise due to Equipment

     

    SBB (Lot 8) Concrete

    Backfill - Retaining Wall

    Dump Truck(s)

    Noise due to Equipment

     

    SBB (Lot 8) Concrete

    Edge Form / Bulkhead – SOG North

    N/A

    N/A

    SBB (Lot 8) Concrete

    Rebar – SOG North

    N/A

    N/A

    SBB (Lot 8) Concrete

    Set Screeds – SOG North

    N/A

    N/A

     

    SBB (Lot 8) Concrete

    QC/ Inspection – SOG North

     

    N/A

    N/A

    SBB (Lot 8) Concrete

    Pour – SOG North

    Concrete pumps and Trucks

    Noise due to Equipment

    SBB (Lot 8)

    Concrete

    Underslab Plumbing Rough-In – SOG South

    N/A

    N/A

    SBB (Lot 8)

    Concrete

    Underslab Electrical Rough-In – SOG South

    N/A

    N/A

    SBB (Lot 8) Concrete

    Fine Grade – SOG South

    skip loader

    Noise due to Equipment

     

    Current and Upcoming Anticipated Closures

    The following shutdown(s)/ closures are anticipated as indicated below. Updates to this schedule will be released weekly in the Project Construction Advisories until the work is complete.  Please contact John Franklin with any specific questions or concerns at john.franklin@ucr.edu.

     

    Description

    Location

    Duration & Date

    Impacted Buildings/ Facilities

    Lot 8

    Lot 8

    Indefinitely

    Lot 8

    Lot 43

    Lot 43

    Indefinitely

    Lot 43

    College Pl

    College Pl

    7/10 – 7/28

    The College Pl loop is a one-way (single lane) road that branches off S Campus Dr. The Southern College Pl Road contains two traffic control operators helping direct traffic both to and from Parking Lot 3. The Northern College Pl Road has been closed.

  • 950592 UCR SBB - Construction Alert #35

    Current Weeks

    Construction Activities

     

    Location

    Activity

    Equipment Used

    Anticipated Disturbance

    BIO

    Sitework

    Relocate (E) Steam Line

    Mini-Excavator and Skid Steer

    Noise due to Equipment

     

    SBB (Lot 8) Sitework

    Install Sewer

    Excavator

    Noise due to Equipment

    Partial Lane Closure of South Campus Drive

    SBB (Lot 8) Sitework

    Install Chilled Water

    Excavator

    Noise due to Equipment

     

    SBB (Lot 8) Sitework

    Close Two Side Forms – Shear Walls & Columns – Pour 2

    Crane

    Noise due to Equipment

     

    SBB (Lot 8) Concrete

    Pour – Shear Walls & Columns – Pour 2

    Concrete Pumps and Trucks

    Noise due to Equipment

    SBB (Lot 8) Concrete

    Strip Walls – Shear Walls & Columns – Pour 2

    Crane

    Noise due to Equipment

     

    SBB (Lot 8) Sitework

    One Side Form Walls – Shear Walls & Columns – Pour 3

    Crane

    Noise due to Equipment

     

    SBB (Lot 8)

    Concrete

    Electrical Rough-in – Column Pour 1

    N/A

    N/A

    SBB (Lot 8) Concrete

    Set Embeds – Column Pour 1

    N/A

    N/A

    SBB (Lot 8) Concrete

    QC/Inspection – Column Pour 1

    N/A

    N/A

    SBB (Lot 8) Concrete

    Form Columns – Columns – Column Pour 1

    Crane

    Noise due to Equipment

     

    SBB (Lot 8) Sitework

    Pour – Column Pour 1

    Concrete Pumps and Trucks

    Noise due to Equipment

    SBB (Lot 8) Sitework

    Set – Scaffolding – Retaining Wall North

    N/A

    N/A

    SBB (Lot 8) Sitework

    Shotcrete Wires – Retaining Wall

    N/A

    N/A

    SBB (Lot 8) Sitework

    Back Form – Retaining Wall

    Excavator

    Noise due to Equipment

     

    SBB (Lot 8) Sitework

    Waterproofing – Retaining Wall – at Mat Pour 2

    N/A

    N/A

    SBB (Lot 8)

    Concrete

    Underslab Electrical Stub-up – SOG North

    N/A

    N/A

    SBB (Lot 8)

    Bio-Retention Planter

    Excavate Bio-retention planter for steam lines

    Excavator

    Noise due to Equipment

     

    Week of July 17, 2023

    Construction Activities 

     

    Location

    Activity

    Equipment Used

    Anticipated Disturbance

    BIO

    Sitework

    Relocate (E) Steam Line

    Mini-Excavator and Skid Steer

    Noise due to Equipment

     

    BIO

    Sitework

    Test & Backfill Steam Line

    Skid Steer

    Noise due to Equipment

     

    BIO

    Sitework

    Remove (E) Electrical Line

    N/A

    N/A

    SBB (Lot 8) Sitework

    Install Sewer

    Excavator

    Noise due to Equipment

    Partial Lane Closure of South Campus Drive

    SBB (Lot 8) Sitework

    Install Chilled Water

    Excavator

    Noise due to Equipment

     

    SBB (Lot 8) Sitework

    Strip – Column Pour 1

    Crane

    Noise due to Equipment

     

    SBB (Lot 8) Sitework

    Waterblast – Column Pour 1

    Concrete Pressure Washer

    Noise due to Equipment

    SBB (Lot 8) Sitework

    Strip Walls – Shear Walls & Columns – Pour 2

    Crane

    Noise due to Equipment

     

    SBB (Lot 8) Sitework

    Rebar – Shear Walls & Columns – Pour 3

    N/A

    N/A

    SBB (Lot 8) Sitework

    Layout & Install MEP’s – Shear Walls & Columns – Pour 3

    N/A

    N/A

    SBB (Lot 8) Sitework

    Set Embeds – Shear Walls & Columns – Pour 3

    N/A

    N/A

    SBB (Lot 8) Sitework

    QC / Inspection – Shear Walls & Columns – Pour 3

    N/A

    N/A

    SBB (Lot 8) Sitework

    Close Two Side Forms – Shear Walls & Columns – Pour 3

    Crane

    Noise due to Equipment

     

    SBB (Lot 8) Concrete

    Shotcrete – Retaining Wall

    Concrete Pumps and Trucks

    Noise due to equipment

    SBB (Lot 8) Concrete

    Remove Rebound – Retaining Wall

    Skid Steer

    Noise due to Equipment

     

    SBB (Lot 8) Concrete

    Remove Scaffolding – Retaining Wall North

    N/A

    N/A

    SBB (Lot 8) Concrete

    Backfill – Retaining Wall

    Trucks and Excavator

    Noise due to Equipment

    SBB (Lot 8) Sitework

    MEP Layout & Block outs – Retaining Wall

    N/A

    N/A

    SBB (Lot 8) Sitework

    Rebar – Retaining Wall

    N/A

    N/A

    SBB (Lot 8)

    Sitework

    Set Scaffolding – Retaining Wall South

    N/A

    N/A

    SBB (Lot 8)

    Concrete

    Backfill Footings, Walls & Columns – SOG North

    Excavator

    Noise due to Equipment

    SBB (Lot 8)

    Bio-Retention Planter

    Backfill Bio-Retention Planter for Steam Lines

    Excavator

     

    Noise due to Equipment

     

    Week of July 24, 2023

    Construction Activities 

     

    Location

    Activity

    Equipment Used

    Anticipated Disturbance

    SBB (Lot 8) Sitework

    Install Sewer

    Excavator

    Noise due to Equipment

    Partial Lane Closure of South Campus Drive

    SBB (Lot 8) Sitework

    Install Chilled Water

    Excavator

    Noise due to Equipment

     

    SBB (Lot 8) Concrete

    Pour – Shear Walls & Columns – Pour 3

    Concrete pumps and Trucks

    Noise due to Equipment

    SBB (Lot 8) Concrete

    Strip Walls – Shear Walls & Columns – Pour 3

    Crane

    Noise due to Equipment

     

    SBB (Lot 8) Concrete

    Shotcrete – Wires

    Concrete pumps and Trucks

    Noise due to Equipment

    SBB (Lot 8) Concrete

    Shotcrete -Retaining Wall

    Shotcrete Pump

    Noise due to Equipment

    SBB (Lot 8) Concrete

    Remove Rebound – Retaining Wall

    Skid Steer

    Noise due to Equipment

     

    SBB (Lot 8) Concrete

    Remove Scaffolding – Retaining Wall

     

    N/A

    N/A

    SBB (Lot 8) Concrete

    Fine Grade – SOG North

    N/A

    N/A

    SBB (Lot 8)

    Concrete

    Install Vapor Barrier – SOG North

    N/A

    N/A

    SBB (Lot 8)

    Concrete

    Edge Form / Bulkhead – SOG North

    N/A

    N/A

    SBB (Lot 8) Concrete

    Rebar – SOG North

    N/A

    N/A

    SBB (Lot 8)

    Concrete

    Underslab Plumbing Rough-in – SOG South

    N/A

    N/A

    SBB (Lot 8)

    Concrete

    Underslab Electrical Rough-in – SOG South

    N/A

    N/A

     

    Current and Upcoming Anticipated Closures

    The following shutdown(s)/ closures are anticipated as indicated below. Updates to this schedule will be released weekly in the Project Construction Advisories until the work is complete.  Please contact John Franklin with any specific questions or concerns at john.franklin@ucr.edu.

     

    Description

    Location

    Duration & Date

    Impacted Buildings/ Facilities

    Lot 8

    Lot 8

    Permanently

    Lot 8

    Lot 43

    Lot 43

    Indefinitely

    Lot 43

    Anderson Park

    Anderson Park

    Indefinitely

    Anderson Park

  • 950592 UCR SBB - Construction Alert #22

    Current Weeks

    Construction Activities

     

    Location

    Activity

    Equipment Used

    Anticipated Disturbance

    SBB (Lot 8) Earthwork

    Grade and Bench

    Loader and Excavator

    Noise due to equipment

    Genomics

    MEP Rough-in

    N/A

    N/A

    Genomics

    Site Wall

    Skid steer / Mini Excavator

    Noise due to equipment

    SBB (Lot 8) Earthwork

    Soil Nail Wall

    Loader, Drill Rig, and Trucks

    Noise due to equipment

    Genomics

    Grading for Flatwork

    Skid steer / Mini Excavator

    Noise due to equipment

     

    Week of April 17, 2023

    Construction Activities 

     

    Location

    Activity

    Equipment Used

    Anticipated Disturbance

    SBB (Lot 8) Earthwork

    Grade and Bench

    Loader and Excavator

    Noise due to equipment

    Genomics

    MEP Finishes

    N/A

    N/A

    Genomics

    Asphalt

    Skid steer/ Mini Excavator

    Noise due to equipment

    SBB (Lot 8) Earthwork

    Soil Nail Wall

    Loader, Drill Rig, and Trucks

    Noise due to equipment

     

    Week of April 24, 2023

    Construction Activities

     

    Location

    Activity

    Equipment Used

    Anticipated Disturbance

    SBB (Lot 8) Earthwork

    Grade and Bench

    Loader and Excavator

    Noise due to equipment

    Genomics

    MEP Finishes

    N/A

    N/A

    SBB (Lot 8) Earthwork

    Soil Nail Wall

    Loader, Drill Rig, and Trucks

    Noise due to equipment

    Genomics

    Fencing

    N/A

    N/A

     

    Current and Upcoming Anticipated Closures

    The following shutdown(s)/ closures are anticipated as indicated below. Updates to this schedule will be released weekly in the Project Construction Advisories until the work is complete.  Please contact John Franklin with any specific questions or concerns at john.franklin@ucr.edu.

     

    Description

    Location

    Duration & Date

    Impacted Buildings/ Facilities

    Lot 8

    Lot 8

    Permanently

    Lot 8

    Lot 43

    Lot 43

    Indefinitely

    Lot 43

  • 950592 UCR SBB - Construction Alert #34

    Current Weeks

    Construction Activities

     

    Location

    Activity

    Equipment Used

    Anticipated Disturbance

    SBB (Lot 8) Sitework

    Install Sewer

    Excavator

    Noise due to Equipment

    Partial Lane Closure of South Campus Drive

    SBB (Lot 8) Sitework

    Install Chilled Water

    Excavator

    Noise due to Equipment

     

    SBB (Lot 8) Concrete

    Pour Mat Footing 2

    Concrete Pumps and Trucks

    Noise due to Equipment

    SBB (Lot 8) Concrete

    Pour – Shear Walls & Columns – Pour 1

    Concrete Pumps and Trucks

    Noise due to Equipment

    SBB (Lot 8)

    Concrete

    Strip Walls – Shear Walls & Columns – Pour 1

    N/A

    N/A

    SBB (Lot 8) Concrete

    Rebar – Shear Walls & Columns – Pour 2

    Crane

    Noise due to Equipment

    SBB (Lot 8) Concrete

    Layout and Install MEP’s – Shear Walls & Columns – Pour 2

    N/A

    N/A

    SBB (Lot 8) Concrete

    Set Embeds – Shear Walls & Columns – Pour 2

    N/A

    N/A

    SBB (Lot 8)

    Concrete

    QC Inspection Shear Walls & Columns – Pour 2

    N/A

    N/A

    SBB (Lot 8)

    Concrete

    Close Two-Side Forms – Shear Walls & Columns – Pour 2

    N/A

    N/A

    SBB (Lot 8)

    Concrete

    Set Rebar Column Cages – Column Pour 1

    Crane

    Noise due to Equipment

    SBB (Lot 8)

    Concrete

    Electrical Rough-In – Column Pour 1

    N/A

    N/A

    SBB (Lot 8)

    Concrete

    Form Columns – Column Pour 1

    N/A

    N/A

    SBB (Lot 8)

    Concrete

    Waterproofing – Retaining Wall – at Mat Pour 2

    Boom Lift

    Noise due to Equipment

    SBB (Lot 8)

    Concrete

    Back Form – Retaining Wall

    N/A

    N/A

    SBB (Lot 8) Concrete

    MEP Layouts & Blockouts – Retaining Wall

    N/A

    N/A

    SBB (Lot 8) Bio-Retention Planter

    Excavate Bio-retention planter for steam lines

    Excavator

    Noise due to Equipment

     

    Week of July 10, 2023

    Construction Activities 

     

    Location

    Activity

    Equipment Used

    Anticipated Disturbance

    SBB (Lot 8) Sitework

    Install Sewer

    Excavator

    Noise due to Equipment

    Partial Lane Closure of South Campus Drive

    SBB (Lot 8) Sitework

    Install Chilled Water

    Excavator

    Noise due to Equipment

     

    SBB (Lot 8) Concrete

    Pour – Shear Walls & Columns – Pour 2

    Concrete Pumps and Trucks

    Noise due to equipment

    SBB (Lot 8) Concrete

    Strip Walls – Shear Walls & Columns – Pour 2

    N/A

    N/A

    SBB (Lot 8) Concrete

    Strip – Columns Pour 1

    N/A

    N/A

    SBB (Lot 8) Concrete

    Waterblast – Column Pour 1

    Concrete Pressure Washer

    Noise due to equipment

    SBB (Lot 8) Concrete

    Set Scaffolding – Retaining Wall

    N/A

    N/A

    SBB (Lot 8) Concrete

    Shotcrete Wires – Retaining Wall

    N/A

    N/A

    SBB (Lot 8) Concrete

    Backfill Footings, Walls & Columns – SOG North

    N/A

    N/A

    SBB (Lot 8) Concrete

    Install Storm Drain at Auditorium

    Excavator

    Noise due to Equipment

    SBB (Lot 8) Concrete

    Underslab Electrical Stub-up – SOG North

    N/A

    N/A

    SBB (Lot 8) Concrete

    Backfill Footing, Walls, & Columns – SOG South

    Excavator

    Noise due to Equipment

    SBB (Lot 8) Bio-Retention Planter

    Excavate Bio-retention planter for steam lines

    Excavator

    Noise due to Equipment

     

    Week of July 17, 2023

    Construction Activities 

     

    Location

    Activity

    Equipment Used

    Anticipated Disturbance

    SBB (Lot 8) Sitework

    Install Sewer

    Excavator

    Noise due to Equipment

    Partial Lane Closure of South Campus Drive

    SBB (Lot 8) Sitework

    Install Chilled Water

    Excavator

    Noise due to Equipment

     

    SBB (Lot 8) Concrete

    Shotcrete – Retaining Wall

    Concrete pumps and Trucks

    Noise due to equipment

    SBB (Lot 8) Concrete

    Remove Rebound – Retaining Wall

    N/A

    N/A

    SBB (Lot 8) Concrete

    Remove Scaffold – Retaining Wall

    N/A

    N/A

    SBB (Lot 8) Concrete

    Backfill – Retaining Wall

     

    Trucks

    Noise due to equipment

    SBB (Lot 8) Bio-Retention Planter

    Excavate Bio-retention planter for steam lines

    Excavator

    Noise due to Equipment

     

    Current and Upcoming Anticipated Closures

    The following shutdown(s)/ closures are anticipated as indicated below. Updates to this schedule will be released weekly in the Project Construction Advisories until the work is complete.  Please contact John Franklin with any specific questions or concerns at john.franklin@ucr.edu.

     

    Description

    Location

    Duration & Date

    Impacted Buildings/ Facilities

    Lot 8

    Lot 8

    Permanently

    Lot 8

    Lot 43

    Lot 43

    Indefinitely

    Lot 43

    Anderson Park

    Anderson Park

    Indefinitely

    Anderson Park

  • 950592 UCR SBB - Construction Alert #33

    Current Weeks

    Construction Activities

     

    Location

    Activity

    Equipment Used

    Anticipated Disturbance

    SBB (Lot 8) Sitework

    Install Sewer

    N/A

    N/A

    SBB (Lot 8) Sitework

    Install Chilled Water

    N/A

    N/A

    SBB (Lot 8) Concrete

    QC Inspection Mat Footing 2

    N/A

    N/A

    SBB (Lot 8) Concrete

    Strip and Waterblast Mat Footing 2

    N/A

    N/A

    SBB (Lot 8)

    Concrete

    Wall & Column Templates and Dowels – Spread Footings

    N/A

    N/A

    SBB (Lot 8) Concrete

    QC Inspection at Spread Footings

    N/A

    N/A

    SBB (Lot 8) Concrete

    Pour Spread Continuous Footings

    Concrete Pumps and Trucks

    Noise due to equipment

    SBB (Lot 8) Concrete

    Strip Wall and Column Templates – Spread Footings

    N/A

    N/A

    SBB (Lot 8)

    Concrete

    Waterblast Dowels – Spread Footings

    N/A

    N/A

    SBB (Lot 8)

    Concrete

    Rebar Shear Walls and Columns – For Pour 1

    N/A

    N/A

    SBB (Lot 8)

    Concrete

    Electrical Rough-in – Shear Walls and Columns – For Pour 1

    N/A

    N/A

    SBB (Lot 8)

    Concrete

    Set Embeds – Shear Walls and Columns – For Pour 1

    N/A

    N/A

    SBB (Lot 8)

    Concrete

    QC Inspection Shear Walls and Columns – For Pour 1

    N/A

    N/A

    SBB (Lot 8)

    Concrete

    Close up Wall Forms – Shear Walls and Columns – For Pour 1

    N/A

    N/A

    SBB (Lot 8)

    Concrete

    Layout Walls – Shear Walls and Columns – For Pour 2

    N/A

    N/A

    SBB (Lot 8) Concrete

    Waterproofing – Retaining Wall at Mat Pour 1

    N/A

    N/A

     

    Week of July 3, 2023

    Construction Activities 

     

    Location

    Activity

    Equipment Used

    Anticipated Disturbance

    SBB (Lot 8) Sitework

    Install Sewer

    N/A

    N/A

    SBB (Lot 8) Sitework

    Install Chilled Water

    N/A

    N/A

    SBB (Lot 8) Concrete

    Pour Mat Footing 2

    Concrete Pumps and Trucks

    Noise due to equipment

    SBB (Lot 8) Concrete

    Pour – Shear Walls & Columns – Pour 1

    Concrete Pumps and Trucks

    Noise due to equipment

    SBB (Lot 8) Concrete

    Strip Walls – Shear Walls & Columns – Pour 1

    N/A

    N/A

    SBB (Lot 8) Concrete

    Rebar – Shear Walls & Columns – Pour 2

    N/A

    N/A

    SBB (Lot 8) Concrete

    Layout and Install MEP’s – Shear Walls & Columns – Pour 2

    N/A

    N/A

    SBB (Lot 8) Concrete

    Set Embeds – Shear Walls & Columns – Pour 2

    N/A

    N/A

    SBB (Lot 8) Concrete

    QC Inspection Shear Walls & Columns – Pour 2

    Concrete Pumps and Trucks

    Noise due to equipment

    SBB (Lot 8) Concrete

    Close Two-Side Forms – Shear Walls & Columns – Pour 2

    N/A

    N/A

    SBB (Lot 8) Concrete

    Set Rebar Column Cages – Column Pour 1

    N/A

    N/A

    SBB (Lot 8) Concrete

    Electrical Rough-in – Column Pour 1

    N/A

    N/A

    SBB (Lot 8) Concrete

    Form Columns – Column Pour 1

    N/A

    N/A

    SBB (Lot 8) Concrete

    Waterproofing – Retaining Wall – at Mat Pour 2

    N/A

    N/A

    SBB (Lot 8) Concrete

    Back Form – Retaining Wall

    N/A

    N/A

    SBB (Lot 8) Concrete

    MEP Layouts & Blockouts – Retaining Wall

    N/A

    N/A

     

    Week of July 10, 2023

    Construction Activities 

     

    Location

    Activity

    Equipment Used

    Anticipated Disturbance

    SBB (Lot 8) Sitework

    Install Sewer

    N/A

    N/A

    SBB (Lot 8) Sitework

    Install Chilled Water

    N/A

    N/A

    SBB (Lot 8) Concrete

    Pour – Shear Walls & Columns – Pour 2

    Concrete Pumps and Trucks

    Noise due to equipment

    SBB (Lot 8) Concrete

    Strip Walls - Shear Walls & Columns – Pour 2

    N/A

    N/A

    SBB (Lot 8) Concrete

    Strip – Column Pour 1

    N/A

    N/A

    SBB (Lot 8) Concrete

    Waterblast – Column Pour 1

     

    N/A

    N/A

    SBB (Lot 8) Concrete

    Set Scaffolding – Retaining Wall

    N/A

    N/A

    SBB (Lot 8) Concrete

    Shotcrete Wires – Retaining Wall

    N/A

    N/A

    SBB (Lot 8) Concrete

    Backfill Footing, Walls & Columns – SOG North

    N/A

    N/A

    SBB (Lot 8) Concrete

    Install Storm Drain at Auditorium

    N/A

    N/A

    SBB (Lot 8) Concrete

    Underslab Electrical Stub-up – SOG North

    N/A

    N/A

    SBB (Lot 8) Concrete

    Backfill Footing, Walls, & Columns – SOG South

    N/A

    N/A

     

    Current and Upcoming Anticipated Closures

    The following shutdown(s)/ closures are anticipated as indicated below. Updates to this schedule will be released weekly in the Project Construction Advisories until the work is complete.  Please contact John Franklin with any specific questions or concerns at john.franklin@ucr.edu.

     

    Description

    Location

    Duration & Date

    Impacted Buildings/ Facilities

    Lot 8

    Lot 8

    Permanently

    Lot 8

    Lot 43

    Lot 43

    Indefinitely

    Lot 43

    Anderson Park

    Anderson Park

    Indefinitely

    Anderson Park

  • 950592 UCR SBB - Construction Alert #32

    Current Weeks

    Construction Activities

     

    Location

    Activity

    Equipment Used

    Anticipated Disturbance

    Genomics

    Fire Alarm Testing (MEP testing and startup)

    N/A

    N/A

    SBB (Lot 8) Sitework

    Install Sewer

    N/A

    N/A

    SBB (Lot 8) Sitework

    Install Chilled Water

    N/A

    N/A

    SBB (Lot 8) Concrete

    Qc Inspection Mat Footing 1

    N/A

    N/A

    SBB (Lot 8) Concrete

    Pour Mat Footing 1

    Concrete Pumps and Trucks

    Noise due to equipment

    SBB (Lot 8) Concrete

    Strip and Waterblast Mat Footing 1

    N/A

    N/A

    SBB (Lot 8) Concrete

    Install Storm Drain at Auditorium

    N/A

    N/A

    SBB (Lot 8) Concrete

    Rebar Mat Footing 2

    N/A

    N/A

    SBB (Lot 8) Concrete

    Wall & Column Templates and Dowels Mat Footing 2

    N/A

    N/A

    SBB (Lot 8) Concrete

    Excavate Spread Footings

    N/A

    N/A

     

    Week of June 26, 2023

    Construction Activities 

     

    Location

    Activity

    Equipment Used

    Anticipated Disturbance

    SBB (Lot 8) Sitework

    Install Sewer

    N/A

    N/A

    SBB (Lot 8) Sitework

    Install Chilled Water

    N/A

    N/A

    SBB (Lot 8) Concrete

    QC inspection at Mat Footing 2

    N/A

    N/A

    SBB (Lot 8) Concrete

    Pour Mat Footing 2

    Concrete Pumps and Trucks

    Noise due to equipment

    SBB (Lot 8) Concrete

    Strip and Waterblast Mat Footing 2

    N/A

    N/A

    SBB (Lot 8) Concrete

    Wall & Column Templates and Dowels - Spread Footings

    N/A

    N/A

    SBB (Lot 8) Concrete

    QC inspection at Spread Footings

    N/A

    N/A

    SBB (Lot 8) Concrete

    Pour Spread Continuous Footings

    Concrete Pumps and Trucks

    Noise due to equipment

    SBB (Lot 8) Concrete

    Strip Wall and Column Templates – Spread Footings

    N/A

    N/A

    SBB (Lot 8) Concrete

    Waterblast Dowels – Spread Footings

    N/A

    N/A

    SBB (Lot 8) Concrete

    Rebar Shear Walls and Columns  - For Pour 1

    N/A

    N/A

    SBB (Lot 8) Concrete

    Electrical Rough-in - Shear Walls and Columns - For Pour 1

    N/A

    N/A

    SBB (Lot 8) Concrete

    Set Embeds - Shear Walls and Columns – For Pour 1

    N/A

    N/A

    SBB (Lot 8) Concrete

    QC inspection Shear Walls and Columns – For Pour 1

    N/A

    N/A

    SBB (Lot 8) Concrete

    Close Up Wall Forms – Shear Walls and Columns – For Pour 1

    N/A

    N/A

    SBB (Lot 8) Concrete

    Layout Walls – Shear Walls and Columns – For Pour 2

    N/A

    N/A

    SBB (Lot 8) Shotcrete Retaining Wall

    Waterproofing – retaining Wall – at Mat Pour 1

    N/A

    N/A

     

    Week of July 3, 2023

    Construction Activities 

     

    Location

    Activity

    Equipment Used

    Anticipated Disturbance

    SBB (Lot 8) Sitework

    Install Sewer

    N/A

    N/A

    SBB (Lot 8) Sitework

    Install Chilled Water

    N/A

    N/A

    SBB (Lot 8) Concrete

    Pour - Shear Walls & Columns – Pour 1

    Concrete Pumps and Trucks

    Noise due to equipment

    SBB (Lot 8) Concrete

    Strip Walls - Shear Walls & Columns – Pour 1

    N/A

    N/A

    SBB (Lot 8) Concrete

    Rebar - Shear Walls & Columns – Pour 2

    N/A

    N/A

    SBB (Lot 8) Concrete

    Layout and install MEPs - Shear Walls & Columns – Pour 2

    N/A

    N/A

    SBB (Lot 8) Concrete

    Set Embeds - Shear Walls & Columns – Pour 2

    N/A

    N/A

    SBB (Lot 8) Concrete

    QC Inspection Shear Walls & Columns – Pour 2

    N/A

    N/A

    SBB (Lot 8) Concrete

    Close Two Side Forms - Shear Walls & Columns – Pour 2

    N/A

    N/A

    SBB (Lot 8) Concrete

    Set Rebar Column Cages – Column Pour 1

    N/A

    N/A

    SBB (Lot 8) Concrete

    Electrical Rough-in – Column Pour 1

    N/A

    N/A

    SBB (Lot 8) Concrete

    QC Inspection – Column Pour 1

    N/A

    N/A

    SBB (Lot 8) Concrete

    Form Columns - Column Pour 1

    N/A

    N/A

    SBB (Lot 8) Shotcrete Retaining Wall

    Waterproofing – retaining Wall – at Mat Pour 2

    N/A

    N/A

    SBB (Lot 8) Shotcrete Retaining Wall

    Back Form – Retaining wall

    N/A

    N/A

    SBB (Lot 8) Concrete

    MEP Layouts & Blockouts – Retaining Wall

    N/A

    N/A

     

    Current and Upcoming Anticipated Closures

    The following shutdown(s)/ closures are anticipated as indicated below. Updates to this schedule will be released weekly in the Project Construction Advisories until the work is complete.  Please contact John Franklin with any specific questions or concerns at john.franklin@ucr.edu.

     

    Description

    Location

    Duration & Date

    Impacted Buildings/ Facilities

    Lot 8

    Lot 8

    Permanently

    Lot 8

    Lot 43

    Lot 43

    Indefinitely

    Lot 43

    Anderson Park

    Anderson Park

    Indefinitely

    Anderson Park

  • 950592 UCR SBB - Construction Alert #31

    Current Weeks

    Construction Activities

     

    Location

    Activity

    Equipment Used

    Anticipated Disturbance

    Genomics

    Fire Alarm Testing (MEP testing and startup)

    N/A

    N/A

    SBB (Lot 8) Sitework

    Install Sewer

    N/A

    N/A

    SBB (Lot 8) Concrete

    Walls and Columns dowels template

    N/A

    N/A

    SBB (Lot 8) Concrete

    Rebar Top Mat and Electrical Rough in for Mat Footing 1

    N/A

    N/A

    SBB (Lot 8) Concrete

    Excavate Footing for Mat Footing 2

    Loader, Excavator, and trucks

    Noise due to equipment

    SBB (Lot 8) Concrete

    Excavate Spread Footings

    Loader, Excavator, and trucks

    Noise due to equipment

    SBB (Lot 8) Concrete

    QC & Inspection Mat Footing 1

    N/A

    N/A

    SBB (Lot 8) Concrete

    Waterproofing Mat Footing 2

    N/A

    N/A

     

    Week of June 19, 2023

    Construction Activities 

     

    Location

    Activity

    Equipment Used

    Anticipated Disturbance

    SBB (Lot 8) Sitework

    Install Sewer

    N/A

    N/A

    SBB (Lot 8) Sitework

    Install Chilled Water

    N/A

    N/A

    SBB (Lot 8) Concrete

    Install Storm Drain At Auditorium

    N/A

    N/A

    SBB (Lot 8) Concrete

    Wall & Column Templates/Dowels at Mat Footing 2

    N/A

    N/A

    SBB (Lot 8) Concrete

    Pour Mat – Mat Footing 2

    Concrete pumps

    Noise due to equipment

    SBB (Lot 8) Concrete

    Strip & Waterblast – Mat Footing 2

    Concrete pumps

    Noise due to equipment

    SBB (Lot 8) Concrete

    QC & Inspection Mat Footing 2

    N/A

    N/A

    SBB (Lot 8) Concrete

    Waterproofing Retaining Wall Mat Pour 1

    N/A

    N/A

    SBB (Lot 8) Concrete

    Layout Shear Walls & Columns

    N/A

    N/A

     

    Week of June 26, 2023

    Construction Activities 

     

    Location

    Activity

    Equipment Used

    Anticipated Disturbance

    SBB (Lot 8) Sitework

    Install Sewer

    N/A

    N/A

    SBB (Lot 8) Sitework

    Install Chilled Water

    N/A

    N/A

    SBB (Lot 8) Concrete

    Mat Footing Pour 2

    Concrete pump

    Noise due to equipment

    SBB (Lot 8) Concrete

    Rebar - Shear Walls & Columns

    N/A

    N/A

    SBB (Lot 8) Concrete

    Electrical Rough-in - Shear Walls & Columns

    N/A

    N/A

    SBB (Lot 8) Concrete

    Set Embers

    N/A

    N/A

    SBB (Lot 8) Concrete

    QC Inspection - Shear Walls & Columns

    N/A

    N/A

    SBB (Lot 8) Concrete

    Close Up Wall Forms – Shear Walls & Columns

    N/A

    N/A

    SBB (Lot 8) Concrete

    Set Rebar Column Cages

    N/A

    N/A

     

    Current and Upcoming Anticipated Closures

    The following shutdown(s)/ closures are anticipated as indicated below. Updates to this schedule will be released weekly in the Project Construction Advisories until the work is complete.  Please contact John Franklin with any specific questions or concerns at john.franklin@ucr.edu.

     

    Description

    Location

    Duration & Date

    Impacted Buildings/ Facilities

    Lot 8

    Lot 8

    Permanently

    Lot 8

    Lot 43

    Lot 43

    Indefinitely

    Lot 43

    Anderson Park

    Anderson Park

    Indefinitely

    Anderson Park

  • 950592 UCR SBB - Construction Alert #30

    Current Weeks

    Construction Activities

     

    Location

    Activity

    Equipment Used

    Anticipated Disturbance

    Genomics

    MEP Finishes

    N/A

    N/A

    SBB (Lot 8) Sitework

    Install Sewer

    N/A

    N/A

    SBB (Lot 8) Concrete

    Layout Mat Footing 2

    N/A

    N/A

    SBB (Lot 8) Concrete

    Rebar Bottom / Mid Mat – Mat Footing 1

    N/A

    N/A

    SBB (Lot 8) Concrete

    Excavate Footing for Mat Footing 1

    Loader, Excavator, and trucks

    Noise due to equipment

    SBB (Lot 8) Concrete

    Excavate Footing for Mat Footing 2

    Loader, Excavator, and trucks

    Noise due to equipment

    SBB (Lot 8) Concrete

    Waterproofing Mat Footing 1

    N/A

    N/A

     

    Week of June 12, 2023

    Construction Activities 

     

    Location

    Activity

    Equipment Used

    Anticipated Disturbance

    Genomics

    Fire Alarm Testing (MEP testing and startup)

    N/A

    N/A

    SBB (Lot 8) Sitework

    Install Sewer

    N/A

    N/A

    SBB (Lot 8) Concrete

    Walls and Columns dowels template

    N/A

    N/A

    SBB (Lot 8) Concrete

    Rebar Top Mat and Electrical Rough in for Mat Footing 1

    N/A

    N/A

    SBB (Lot 8) Concrete

    Excavate Footing for Mat Footing 2

    Loader, Excavator, and trucks

    Noise due to equipment

    SBB (Lot 8) Concrete

    Excavate Spread Footings

    Loader, Excavator, and trucks

    Noise due to equipment

    SBB (Lot 8) Concrete

    QC & Inspection Mat Footing 1

    N/A

    N/A

    SBB (Lot 8) Concrete

    Waterproofing Mat Footing 2

    N/A

    N/A

     

    Week of June 19, 2023

    Construction Activities 

     

    Location

    Activity

    Equipment Used

    Anticipated Disturbance

    SBB (Lot 8) Sitework

    Install Sewer

    N/A

    N/A

    SBB (Lot 8) Sitework

    Install Chilled Water

    N/A

    N/A

    SBB (Lot 8) Concrete

    Install Storm Drain At Auditorium

    N/A

    N/A

    SBB (Lot 8) Concrete

    Wall & Column Templates/Dowels at Mat Footing 2

    N/A

    N/A

    SBB (Lot 8) Concrete

    Pour Mat – Mat Footing 2

    Concrete pumps

    Noise due to equipment

    SBB (Lot 8) Concrete

    Strip & Waterblast – Mat Footing 2

    Concrete pumps

    Noise due to equipment

    SBB (Lot 8) Concrete

    QC & Inspection Mat Footing 2

    N/A

    N/A

    SBB (Lot 8) Concrete

    Waterproofing Retaining Wall Mat Pour 1

    N/A

    N/A

     

     

    Current and Upcoming Anticipated Closures

    The following shutdown(s)/ closures are anticipated as indicated below. Updates to this schedule will be released weekly in the Project Construction Advisories until the work is complete.  Please contact John Franklin with any specific questions or concerns at john.franklin@ucr.edu.

     

    Description

    Location

    Duration & Date

    Impacted Buildings/ Facilities

    Lot 8

    Lot 8

    Permanently

    Lot 8

    Lot 43

    Lot 43

    Indefinitely

    Lot 43

    Anderson Park

    Anderson Park

    Indefinitely

    Anderson Park

  • 950592 UCR SBB - Construction Alert #29

    Current Weeks

    Construction Activities

     

    Location

    Activity

    Equipment Used

    Anticipated Disturbance

    Genomics

    MEP Finishes

    N/A

    N/A

    SBB (Lot 8) Earthwork

    Grade and Bench

    Loader and Excavator

    Noise due to equipment

    SBB (Lot 8) Earthwork

    Soil Nail Wall

    Loader, Drill Rig, and Trucks

    Noise due to equipment

    SBB (Lot 8) Concrete

    Layout Mat footing 1

    N/A

    N/A

    SBB (Lot 8) Concrete

    Excavate Footing for Mat Footing 1

    Loader, Excavator, and trucks

    Noise due to equipment

     

    Week of June 5, 2023

    Construction Activities 

     

    Location

    Activity

    Equipment Used

    Anticipated Disturbance

    Genomics

    MEP Finishes

    N/A

    N/A

    SBB (Lot 8) Sitework

    Install Sewer

    N/A

    N/A

    SBB (Lot 8) Concrete

    Layout Mat Footing 2

    N/A

    N/A

    SBB (Lot 8) Concrete

    Rebar Bottom / Mid Mat – Mat Footing 1

    N/A

    N/A

    SBB (Lot 8) Concrete

    Excavate Footing for Mat Footing 1

    Loader, Excavator, and trucks

    Noise due to equipment

    SBB (Lot 8) Concrete

    Excavate Footing for Mat Footing 2

    Loader, Excavator, and trucks

    Noise due to equipment

    SBB (Lot 8) Concrete

    Waterproofing Mat Footing 1

    N/A

    N/A

     

    Week of June 12, 2023

    Construction Activities 

     

    Location

    Activity

    Equipment Used

    Anticipated Disturbance

    Genomics

    Fire Alarm Testing (MEP testing and startup)

    N/A

    N/A

    SBB (Lot 8) Sitework

    Install Sewer

    N/A

    N/A

    SBB (Lot 8) Concrete

    Walls and Columns dowels template

    N/A

    N/A

    SBB (Lot 8) Concrete

    Rebar Top Mat and Electrical Rough in for Mat Footing 1

    N/A

    N/A

    SBB (Lot 8) Concrete

    Excavate Footing for Mat Footing 2

    Loader, Excavator, and trucks

    Noise due to equipment

    SBB (Lot 8) Concrete

    Excavate Spread Footings

    Loader, Excavator, and trucks

    Noise due to equipment

    SBB (Lot 8) Concrete

    QC & Inspection Mat Footing 1

    N/A

    N/A

    SBB (Lot 8) Concrete

    Waterproofing Mat Footing 2

    N/A

    N/A

     

    Current and Upcoming Anticipated Closures

    The following shutdown(s)/ closures are anticipated as indicated below. Updates to this schedule will be released weekly in the Project Construction Advisories until the work is complete.  Please contact John Franklin with any specific questions or concerns at john.franklin@ucr.edu.

     

    Description

    Location

    Duration & Date

    Impacted Buildings/ Facilities

    Lot 8

    Lot 8

    Permanently

    Lot 8

    Lot 43

    Lot 43

    Indefinitely

    Lot 43

    Anderson Park

    Anderson Park

    Indefinitely

    Anderson Park

  • 950592 UCR SBB - Construction Alert #28

    Current Weeks

    Construction Activities

     

    Location

    Activity

    Equipment Used

    Anticipated Disturbance

    Genomics

    MEP Finishes

    N/A

    N/A

    SBB (Lot 8) Earthwork

    Grade and Bench

    Loader and Excavator

    Noise due to equipment

    SBB (Lot 8) Earthwork

    Soil Nail Wall

    Loader, Drill Rig, and Trucks

    Noise due to equipment

     

    Week of May 29, 2023

    Construction Activities 

     

    Location

    Activity

    Equipment Used

    Anticipated Disturbance

    Genomics

    MEP Finishes

    N/A

    N/A

    SBB (Lot 8) Earthwork

    Grade and Bench

    Loader and Excavator

    Noise due to equipment

    SBB (Lot 8) Earthwork

    Soil Nail Wall

    Loader, Drill Rig, and Trucks

    Noise due to equipment

    SBB (Lot 8) Concrete

    Layout Mat footing 1

    N/A

    N/A

    SBB (Lot 8) Concrete

    Excavate Footing for Mat Footing 1

    Loader, Excavator, and trucks

    Noise due to equipment

     

    Week of June 5, 2023

    Construction Activities

     

    Location

    Activity

    Equipment Used

    Anticipated Disturbance

    Genomics

    Fire Alarm Testing (MEP testing and startup)

    N/A

    N/A

    SBB (Lot 8) Concrete

    Layout Mat Footing 2

    N/A

    N/A

    SBB (Lot 8) Concrete

    Excavate Footing for Mat Footing 1

    Loader, Excavator, and trucks

    Noise due to equipment

    SBB (Lot 8) Concrete

    Excavate Footing for Mat Footing 2

    Loader, Excavator, and trucks

    Noise due to equipment

    SBB (Lot 8) Concrete

    Waterproofing Mat Footing 1

    N/A

    N/A

     

    Current and Upcoming Anticipated Closures

    The following shutdown(s)/ closures are anticipated as indicated below. Updates to this schedule will be released weekly in the Project Construction Advisories until the work is complete.  Please contact John Franklin with any specific questions or concerns at john.franklin@ucr.edu.

     

    Description

    Location

    Duration & Date

    Impacted Buildings/ Facilities

    Lot 8

    Lot 8

    Permanently

    Lot 8

    Lot 43

    Lot 43

    Indefinitely

    Lot 43

    Anderson Park

    Anderson Park

    Indefinitely

    Anderson Park

  • 950592 UCR SBB - Construction Alert #27

    Current Weeks

    Construction Activities

     

    Location

    Activity

    Equipment Used

    Anticipated Disturbance

    SBB (Lot 8) Earthwork

    Grade and Bench

    Loader and Excavator

    Noise due to equipment

    SBB (Lot 8) Earthwork

    Soil Nail Wall

    Loader, Drill Rig, and Trucks

    Noise due to equipment

    Genomics

    MEP Finishes

    N/A

    N/A

     

    Week of May 22, 2023

    Construction Activities 

     

    Location

    Activity

    Equipment Used

    Anticipated Disturbance

    SBB (Lot 8) Earthwork

    Grade and Bench

    Loader and Excavator

    Noise due to equipment

    Genomics

    MEP Finishes

    N/A

    N/A

    SBB (Lot 8) Earthwork

    Soil Nail Wall

    Loader, Drill Rig, and Trucks

    Noise due to equipment

     

    Week of May 29, 2023

    Construction Activities

     

    Location

    Activity

    Equipment Used

    Anticipated Disturbance

    SBB (Lot 8) Earthwork

    Grade and Bench

    Loader and Excavator

    Noise due to equipment

    SBB (Lot 8) Earthwork

    Soil Nail Wall

    Loader, Drill Rig, and Trucks

    Noise due to equipment

    Genomics

    Fire Alarm Testing (MEP testing and startup)

    N/A

    N/A

    SBB (Lot 8) Foundations

    Layout Mat Foundation 1

    N/A

    N/A

     

    Current and Upcoming Anticipated Closures

    The following shutdown(s)/ closures are anticipated as indicated below. Updates to this schedule will be released weekly in the Project Construction Advisories until the work is complete.  Please contact John Franklin with any specific questions or concerns at john.franklin@ucr.edu.

     

    Description

    Location

    Duration & Date

    Impacted Buildings/ Facilities

    Lot 8

    Lot 8

    Permanently

    Lot 8

    Lot 43

    Lot 43

    Indefinitely

    Lot 43

  • 950592 UCR SBB - Construction Alert #26

    Current Weeks

    Construction Activities

     

    Location

    Activity

    Equipment Used

    Anticipated Disturbance

    SBB (Lot 8) Earthwork

    Grade and Bench

    Loader and Excavator

    Noise due to equipment

    SBB (Lot 8) Earthwork

    Soil Nail Wall

    Loader, Drill Rig, and Trucks

    Noise due to equipment

    Genomics

    Finish DG Install

    N/A

    N/A

     

    Week of May 15, 2023

    Construction Activities 

     

    Location

    Activity

    Equipment Used

    Anticipated Disturbance

    SBB (Lot 8) Earthwork

    Grade and Bench

    Loader and Excavator

    Noise due to equipment

    Genomics

    MEP Finishes

    N/A

    N/A

    SBB (Lot 8) Earthwork

    Soil Nail Wall

    Loader, Drill Rig, and Trucks

    Noise due to equipment

     

    Week of May 22, 2023

    Construction Activities

     

    Location

    Activity

    Equipment Used

    Anticipated Disturbance

    SBB (Lot 8) Earthwork

    Grade and Bench

    Loader and Excavator

    Noise due to equipment

    SBB (Lot 8) Earthwork

    Soil Nail Wall

    Loader, Drill Rig, and Trucks

    Noise due to equipment

    Genomics

    Fire Alarm Testing (MEP testing and startup)

    N/A

    N/A

     

    Current and Upcoming Anticipated Closures

    The following shutdown(s)/ closures are anticipated as indicated below. Updates to this schedule will be released weekly in the Project Construction Advisories until the work is complete.  Please contact John Franklin with any specific questions or concerns at john.franklin@ucr.edu.

     

    Description

    Location

    Duration & Date

    Impacted Buildings/ Facilities

    Lot 8

    Lot 8

    Permanently

    Lot 8

    Lot 43

    Lot 43

    Indefinitely

    Lot 43

  • 950592 UCR SBB - Construction Alert #25

    Current Weeks

    Construction Activities

     

    Location

    Activity

    Equipment Used

    Anticipated Disturbance

    SBB (Lot 8) Earthwork

    Grade and Bench

    Loader and Excavator

    Noise due to equipment

    SBB (Lot 8) Earthwork

    Soil Nail Wall

    Loader, Drill Rig, and Trucks

    Noise due to equipment

    Genomics

    Fencing

    N/A

    N/A

    Genomics

    Striping & Signage Post Install

    N/A

    N/A

     

    Week of May 8, 2023

    Construction Activities 

     

    Location

    Activity

    Equipment Used

    Anticipated Disturbance

    SBB (Lot 8) Earthwork

    Grade and Bench

    Loader and Excavator

    Noise due to equipment

    Genomics

    MEP Finishes

    N/A

    N/A

    SBB (Lot 8) Earthwork

    Soil Nail Wall

    Loader, Drill Rig, and Trucks

    Noise due to equipment

     

    Week of May 15, 2023

    Construction Activities

     

    Location

    Activity

    Equipment Used

    Anticipated Disturbance

    SBB (Lot 8) Earthwork

    Grade and Bench

    Loader and Excavator

    Noise due to equipment

    SBB (Lot 8) Earthwork

    Soil Nail Wall

    Loader, Drill Rig, and Trucks

    Noise due to equipment

    Genomics

    Fire Alarm Testing (MEP testing and startup)

    N/A

    N/A

     

    Current and Upcoming Anticipated Closures

    The following shutdown(s)/ closures are anticipated as indicated below. Updates to this schedule will be released weekly in the Project Construction Advisories until the work is complete.  Please contact John Franklin with any specific questions or concerns at john.franklin@ucr.edu.

     

    Description

    Location

    Duration & Date

    Impacted Buildings/ Facilities

    Lot 8

    Lot 8

    Permanently

    Lot 8

    Lot 43

    Lot 43

    Indefinitely

    Lot 43

  • 950592 UCR SBB - Construction Alert #24

    Current Weeks

    Construction Activities

     

    Location

    Activity

    Equipment Used

    Anticipated Disturbance

    SBB (Lot 8) Earthwork

    Grade and Bench

    Loader and Excavator

    Noise due to equipment

    Genomics

    MEP Finishes

    N/A

    N/A

    SBB (Lot 8) Earthwork

    Soil Nail Wall

    Loader, Drill Rig, and Trucks

    Noise due to equipment

    Genomics

    Fencing

    N/A

    N/A

     

    Week of May 1, 2023

    Construction Activities 

     

    Location

    Activity

    Equipment Used

    Anticipated Disturbance

    SBB (Lot 8) Earthwork

    Grade and Bench

    Loader and Excavator

    Noise due to equipment

    Genomics

    MEP Finishes

    N/A

    N/A

    Genomics

    Asphalt

    Skid steer/ Mini Excavator

    Noise due to equipment

    SBB (Lot 8) Earthwork

    Soil Nail Wall

    Loader, Drill Rig, and Trucks

    Noise due to equipment

     

    Week of May 8, 2023

    Construction Activities

     

    Location

    Activity

    Equipment Used

    Anticipated Disturbance

    SBB (Lot 8) Earthwork

    Grade and Bench

    Loader and Excavator

    Noise due to equipment

    SBB (Lot 8) Earthwork

    Soil Nail Wall

    Loader, Drill Rig, and Trucks

    Noise due to equipment

    Genomics

    Fire Alarm Testing (MEP testing and startup)

    N/A

    N/A

     

    Current and Upcoming Anticipated Closures

    The following shutdown(s)/ closures are anticipated as indicated below. Updates to this schedule will be released weekly in the Project Construction Advisories until the work is complete.  Please contact John Franklin with any specific questions or concerns at john.franklin@ucr.edu.

     

    Description

    Location

    Duration & Date

    Impacted Buildings/ Facilities

    Lot 8

    Lot 8

    Permanently

    Lot 8

    Lot 43

    Lot 43

    Indefinitely

    Lot 43

  • 950592 UCR SBB - Construction Alert #23

    Current Weeks

    Construction Activities

     

    Location

    Activity

    Equipment Used

    Anticipated Disturbance

    SBB (Lot 8) Earthwork

    Grade and Bench

    Loader and Excavator

    Noise due to equipment

    Genomics

    MEP Finishes

    N/A

    N/A

    SBB (Lot 8) Earthwork

    Soil Nail Wall

    Loader, Drill Rig, and Trucks

    Noise due to equipment

    Genomics

    Grading/Pouring Flatwork

    Skid steer / Mini Excavator

    Noise due to equipment

     

    Week of April 24, 2023

    Construction Activities 

     

    Location

    Activity

    Equipment Used

    Anticipated Disturbance

    SBB (Lot 8) Earthwork

    Grade and Bench

    Loader and Excavator

    Noise due to equipment

    Genomics

    MEP Finishes

    N/A

    N/A

    Genomics

    Asphalt

    Skid steer/ Mini Excavator

    Noise due to equipment

    SBB (Lot 8) Earthwork

    Soil Nail Wall

    Loader, Drill Rig, and Trucks

    Noise due to equipment

    Genomics

    Fencing

    N/A

    N/A

     

    Week of May 1, 2023

    Construction Activities

     

    Location

    Activity

    Equipment Used

    Anticipated Disturbance

    SBB (Lot 8) Earthwork

    Grade and Bench

    Loader and Excavator

    Noise due to equipment

    SBB (Lot 8) Earthwork

    Soil Nail Wall

    Loader, Drill Rig, and Trucks

    Noise due to equipment

    Genomics

    Fire Alarm Testing (MEP testing and startup)

    N/A

    N/A

     

    Current and Upcoming Anticipated Closures

    The following shutdown(s)/ closures are anticipated as indicated below. Updates to this schedule will be released weekly in the Project Construction Advisories until the work is complete.  Please contact John Franklin with any specific questions or concerns at john.franklin@ucr.edu.

     

    Description

    Location

    Duration & Date

    Impacted Buildings/ Facilities

    Lot 8

    Lot 8

    Permanently

    Lot 8

    Lot 43

    Lot 43

    Indefinitely

    Lot 43

  • 950592 - UCR SBB - Construction Alert #8 Week 01/2/2023

    Current Weeks

    Construction Activities

     

    Location

    Activity

    Equipment Used

    Anticipated Disturbance

    Lot 43

    Trailer Interior/Exterior Build-out

    Small hand tools

    Noise due to hand tools

    Genomics

    Grading

    N/A

    N/A

    Bio-Control

    Relocate Existing Lines (Water, Telecom, and electrical)

    N/A

    N/A

     

    Week of January 09, 2023

    Construction Activities

     

    Location

    Activity

    Equipment Used

    Anticipated Disturbance

    Genomics

    Footing excavation

    Back Hoe, mini-ex, dump truck

    Noise due to equipment

    Bio-Control

    Relocate Existing Lines (Water, Telecom, and electrical)

    N/A

    N/A

     

    Week of January 16, 2023

    Construction Activities

     

    Location

    Activity

    Equipment Used

    Anticipated Disturbance

    Genomics

    Rebar Install

    N/A

    N/A

    SBB (Lot 8)

    Site Utilities Excavation

    Mini-Ex and Asphalt Removal

    N/A

     

    Current and Upcoming Anticipated Closures

    The following shutdown(s)/ closures are anticipated as indicated below. Updates to this schedule will be released weekly in the Project Construction Advisories until the work is complete.  Please contact John Franklin with any specific questions or concerns at john.franklin@ucr.edu.

     

    Description

    Location

    Duration & Date

    Impacted Buildings/ Facilities

    Lot 8

    Lot 8

    Indefinitely

    Lot 8

    Lot 43

    Lot 43

    Indefinitely

    Lot 43

  • 950592 UCR SBB - Construction Alert #21

    Current Weeks

    Construction Activities

     

    Location

    Activity

    Equipment Used

    Anticipated Disturbance

    SBB (Lot 8) Earthwork

    Soil Nail Wall Mob

    Loader, Drill Rig, and Trucks

    Noise due to equipment

    Genomics

    Install Metal Building (PEMB)

    N/A

    N/A

    SBB (Lot 8) Earthwork

    Clear & Grub for SBB and Export Dirt

    Loader and Excavator

    Noise due to equipment

    Genomics

    Site Wall

    Skid Steer/Mini Excavator

    Noise due to equipment

    Genomics

    MEP Rough-in

    N/A

    N/A

     

    Week of April 10, 2023

    Construction Activities 

     

    Location

    Activity

    Equipment Used

    Anticipated Disturbance

    SBB (Lot 8) Earthwork

    Clear & Grub for SBB and Misc. Export

    Loader and Excavator

    Noise due to equipment

    Genomics

    MEP Rough-in

    N/A

    N/A

    Genomics

    Site Wall

    Skid steer / Mini Excavator

    Noise due to equipment

    SBB (Lot 8) Earthwork

    Soil Nail Wall

    Loader, Drill Rig, and Trucks

    Noise due to equipment

     

    Week of April 17, 2023

    Construction Activities

     

    Location

    Activity

    Equipment Used

    Anticipated Disturbance

    SBB (Lot 8)

    Site Utilities

    Backhoe, excavator, trucks

    Noise due to equipment

    SBB (Lot 8) Earthwork

    Grade and Bench

    Loader and Excavator

    Noise due to equipment

    Genomics

    MEP Finishes

    N/A

    N/A

    Genomics

    Site Wall

    Skid steer/ Mini Excavator

    Noise due to equipment

    SBB (Lot 8) Earthwork

    Soil Nail Wall

    Loader, Drill Rig, and Trucks

    Noise due to equipment

     

    Current and Upcoming Anticipated Closures

    The following shutdown(s)/ closures are anticipated as indicated below. Updates to this schedule will be released weekly in the Project Construction Advisories until the work is complete.  Please contact John Franklin with any specific questions or concerns at john.franklin@ucr.edu.

     

    Description

    Location

    Duration & Date

    Impacted Buildings/ Facilities

    Lot 8

    Lot 8

    Permanently

    Lot 8

    Lot 43

    Lot 43

    Indefinitely

    Lot 43

  • 950592 UCR SBB - Construction Alert #20

    Current Weeks

    Construction Activities

     

    Location

    Activity

    Equipment Used

    Anticipated Disturbance

    SBB (Lot 8) Earthwork

    Soil Nail Wall

    Loader, Drill Rig, and Trucks

    Noise due to equipment

    Genomics

    Install Metal Building (PEMB)

    N/A

    N/A

    SBB (Lot 8) Earthwork

    Clear & Grub for SBB

    Loader and Excavator

    Noise due to equipment

    Genomics

    Site Wall

    Skid Steer

    Noise due to equipment

     

    Week of April 3, 2023

    Construction Activities 

     

    Location

    Activity

    Equipment Used

    Anticipated Disturbance

    SBB (Lot 8)

    Site Utilities

    Backhoe, excavator, trucks

    Noise due to equipment

    SBB (Lot 8) Earthwork

    Clear & Grub for SBB

    Loader and Excavator

    Noise due to equipment

    Genomics

    MEP Rough-in

    N/A

    N/A

    Genomics

    Site Wall

    Skid steer

    Noise due to equipment

    SBB (Lot 8) Earthwork

    Soil Nail Wall

    Loader, Drill Rig, and Trucks

    Noise due to equipment

     

    Week of April 10, 2023

    Construction Activities

     

    Location

    Activity

    Equipment Used

    Anticipated Disturbance

    SBB (Lot 8)

    Site Utilities

    Backhoe, excavator, trucks

    Noise due to equipment

    SBB (Lot 8) Earthwork

    Grade and Bench

    Loader and Excavator

    Noise due to equipment

    Genomics

    MEP Finishes

    N/A

    N/A

    Genomics

    Site Wall

    Skid steer

    Noise due to equipment

    SBB (Lot 8) Earthwork

    Soil Nail Wall

    Loader, Drill Rig, and Trucks

    Noise due to equipment

     

    Current and Upcoming Anticipated Closures

    The following shutdown(s)/ closures are anticipated as indicated below. Updates to this schedule will be released weekly in the Project Construction Advisories until the work is complete.  Please contact John Franklin with any specific questions or concerns at john.franklin@ucr.edu.

     

    Description

    Location

    Duration & Date

    Impacted Buildings/ Facilities

    Lot 8

    Lot 8

    Permanently

    Lot 8

    Lot 43

    Lot 43

    Indefinitely

    Lot 43

  • 950592 UCR SBB - Construction Alert #19

    Current Weeks

    Construction Activities

     

    Location

    Activity

    Equipment Used

    Anticipated Disturbance

    SBB (Lot 8)

    Locate and Cap Existing Utilities

    N/A

    N/A

    Genomics

    Install Metal Building (PEMB)

    N/A

    N/A

    SBB (Site)

    Street Paving

    Trucks and Rollers

    Noise due to equipment

    SBB (Lot 8) Earthwork

    Clear & Grub for SBB

    Loader and Excavator

    Noise due to equipment

     

    Week of March 27, 2023

    Construction Activities 

     

    Location

    Activity

    Equipment Used

    Anticipated Disturbance

    SBB (Lot 8) Earthwork

    Soil Nail Wall

    Loader, Drill Rig, and Trucks

    Noise due to equipment

    Genomics

    Install Metal Building (PEMB)

    N/A

    N/A

    SBB (Lot 8) Earthwork

    Clear & Grub for SBB

    Loader and Excavator

    Noise due to equipment

    Genomics

    Site Wall

    Skid Steer

    Noise due to equipment

     

    Week of April 3, 2023

    Construction Activities

     

    Location

    Activity

    Equipment Used

    Anticipated Disturbance

    SBB (Lot 8)

    Site Utilities

    Backhoe, excavator, trucks

    Noise due to equipment

    SBB (Lot 8) Earthwork

    Clear & Grub for SBB

    Loader and Excavator

    Noise due to equipment

    Genomics

    MEP Rough-in

    N/A

    N/A

    Genomics

    Site Wall

    Skid steer

    Noise due to equipment

    SBB (Lot 8) Earthwork

    Soil Nail Wall

    Loader, Drill Rig, and Trucks

    Noise due to equipment

     

    Current and Upcoming Anticipated Closures

    The following shutdown(s)/ closures are anticipated as indicated below. Updates to this schedule will be released weekly in the Project Construction Advisories until the work is complete.  Please contact John Franklin with any specific questions or concerns at john.franklin@ucr.edu.

     

    Description

    Location

    Duration & Date

    Impacted Buildings/ Facilities

    Lot 8

    Lot 8

    Permanently

    Lot 8

    Lot 43

    Lot 43

    Indefinitely

    Lot 43

  • 950592 UCR SBB - Construction Alert #18 - Week 03/13/2023

    Current Weeks

    Construction Activities

     

    Location

    Activity

    Equipment Used

    Anticipated Disturbance

    SBB (Lot 8)

    Locate and Cap Existing Utilities

    N/A

    N/A

    SBB (Lot 8)

    Site Utilities

    Backhoe, excavator, trucks

    Noise due to equipment

    Genomics

    Install Metal Building (PEMB)

    N/A

    N/A

    SBB (site electrical)

    Concrete backfill of medium voltage trench

    Concrete pump and trucks

    Noise due to equipment

    SBB (Lot 8)

    Electrical Shutdown

    N/A

    N/A

     

    Week of March 20, 2023

    Construction Activities 

     

    Location

    Activity

    Equipment Used

    Anticipated Disturbance

    SBB (Lot 8)

    Locate and Cap Existing Utilities

    N/A

    N/A

    SBB (Lot 8)

    Site Utilities

    Backhoe, excavator, trucks

    Noise due to equipment

    Genomics

    Install Metal Building (PEMB)

    N/A

    N/A

    SBB (Lot 8) Earthwork

    Clear & Grub for Soil Nail Wall

    Loader and Excavator

    Noise due to equipment

    Genomics

    Site Wall

    Skid Steer

    Noise due to equipment

     

    Week of March 27, 2023

    Construction Activities

     

    Location

    Activity

    Equipment Used

    Anticipated Disturbance

    SBB (Lot 8)

    Site Utilities

    Backhoe, excavator, trucks

    Noise due to equipment

    Genomics

    Install Metal Building (PEMB)

    N/A

    N/A

    SBB (Lot 8) Earthwork

    Clear & Grub for Soil Nail Wall

    Loader and Excavator

    Noise due to equipment

    Genomics

    MEP Rough-in

    N/A

    N/A

    Genomics

    Site Wall

    Skid steer

    Noise due to equipment

     

    Current and Upcoming Anticipated Closures

    The following shutdown(s)/ closures are anticipated as indicated below. Updates to this schedule will be released weekly in the Project Construction Advisories until the work is complete.  Please contact John Franklin with any specific questions or concerns at john.franklin@ucr.edu.

     

    Description

    Location

    Duration & Date

    Impacted Buildings/ Facilities

    Lot 8

    Lot 8

    Permanently

    Lot 8

    Lot 43

    Lot 43

    Indefinitely

    Lot 43

  • UCR SBB - Construction Alert #17 - Week 03/06/2023

    Current Weeks

    Construction Activities

     

    Location

    Activity

    Equipment Used

    Anticipated Disturbance

    SBB (Lot 8)

    Locate and Cap Existing Utilities

    N/A

    N/A

    SBB (Lot 8)

    Site Utilities

    Backhoe, excavator, trucks

    Noise due to equipment

    SBB (site electrical)

    Pulling Medium Voltage cable

    N/A

    N/A

    SBB (site electrical)

    Setting new power pole

    N/A

    N/A

    Genomics

    Install Metal Building (PEMB)

    N/A

    N/A

    SBB (site electrical)

    Concrete backfill of medium voltage trench

    Concrete pump and trucks

    Noise due to equipment

    SBB (Lot 8)

    Domestic Water Shutdown

    N/A

    N/A

     

    Week of March 13, 2023

    Construction Activities 

     

    Location

    Activity

    Equipment Used

    Anticipated Disturbance

    SBB (Lot 8)

    Locate and Cap Existing Utilities

    N/A

    N/A

    SBB (Lot 8)

    Site Utilities

    Backhoe, excavator, trucks

    Noise due to equipment

    Genomics

    Install Metal Building (PEMB)

    N/A

    N/A

    SBB (Lot 8)

    Electrical Shutdown

    N/A

    N/A

     

    Week of March 20, 2023

    Construction Activities

     

    Location

    Activity

    Equipment Used

    Anticipated Disturbance

    SBB (Lot 8)

    Locate and Cap Existing Utilities

    N/A

    N/A

    SBB (Lot 8)

    Site Utilities

    Backhoe, excavator, trucks

    Noise due to equipment

    Genomics

    Install Metal Building (PEMB)

    N/A

    N/A

    SBB (Lot 8) Earthwork

    Clear & Grub for Soil Nail Wall

    Loader and Excavator

    Noise due to equipment

    Genomics

    MEP Rough-in

    N/A

    N/A

     

    Current and Upcoming Anticipated Closures

    The following shutdown(s)/ closures are anticipated as indicated below. Updates to this schedule will be released weekly in the Project Construction Advisories until the work is complete.  Please contact John Franklin with any specific questions or concerns at john.franklin@ucr.edu.

     

    Description

    Location

    Duration & Date

    Impacted Buildings/ Facilities

    Lot 8

    Lot 8

    Permanently

    Lot 8

    Lot 43

    Lot 43

    Indefinitely

    Lot 43

  • 950592 - UCR SBB - Construction Alert #16 - Week 02/27/2023

    Current Weeks

    Construction Activities

    Location

    Activity

    Equipment Used

    Anticipated Disturbance

    SBB (Lot 8)

    Locate and Cap Existing Utilities

    N/A

    N/A

    SBB (Lot 8)

    Site Utilities

    Backhoe, excavator, trucks

    Noise due to equipment

    Genomics

    Metal Building Arrives (PEMB)

    N/A

    N/A

    SBB (site electrical)

    Pulling Medium Voltage cable

    N/A

    N/A

    SBB (site electrical)

    Installing conduit

    N/A

    N/A

    Genomics

    Form and reinforce SOG

    N/A

    N/A

    Genomics

    Concrete Pour

    Concrete Pump

    Noise due to equipment

     

    Week of March 6, 2023

    Construction Activities 

    Location

    Activity

    Equipment Used

    Anticipated Disturbance

    SBB (Lot 8)

    Locate and Cap Existing Utilities

    N/A

    N/A

    SBB (Lot 8)

    Site Utilities

    Backhoe, excavator, trucks

    Noise due to equipment

    SBB (site electrical)

    Pulling Medium Voltage cable

    N/A

    N/A

    SBB (site electrical)

    Setting new power pole

    N/A

    N/A

    Genomics

    Install Metal Building (PEMB)

    N/A

    N/A

    SBB (Lot 8)

    Domestic Water Shutdown

    N/A

    N/A

     

    Week of March 13, 2023

    Construction Activities

    Location

    Activity

    Equipment Used

    Anticipated Disturbance

    SBB (Lot 8)

    Locate and Cap Existing Utilities

    N/A

    N/A

    SBB (Lot 8)

    Site Utilities

    Backhoe, excavator, trucks

    Noise due to equipment

    Genomics

    Install Metal Building (PEMB)

    N/A

    N/A

    SBB (site electrical)

    Pulling Medium Voltage cable

    N/A

    N/A

    SBB (Lot 8) Earthwork

    Clear & Grub for Soil Nail Wall

    Loader and Excavator

    Noise due to equipment

     

    Current and Upcoming Anticipated Closures

    The following shutdown(s)/ closures are anticipated as indicated below. Updates to this schedule will be released weekly in the Project Construction Advisories until the work is complete.  Please contact John Franklin with any specific questions or concerns at john.franklin@ucr.edu.

     

    Description

    Location

    Duration & Date

    Impacted Buildings/ Facilities

    Lot 8

    Lot 8

    Permanently

    Lot 8

    Lot 43

    Lot 43

    Indefinitely

    Lot 43

     

  • 950592 - UCR SBB - Construction Alert #15 - Week 02/20/2023

    Current Weeks

    Construction Activities

     

    Location

    Activity

    Equipment Used

    Anticipated Disturbance

    SBB (Lot 8)

    Locate and Cap Existing Utilities

    N/A

    N/A

    SBB (Lot 8)

    Site Utilities

    Backhoe, excavator, trucks

    Noise due to equipment

    Genomics

    Metal Building Arrives (PEMB)

    N/A

    N/A

    SBB (site electrical)

    Pulling Medium Voltage cable

    N/A

    N/A

    Genomics

    Back fill

    Bobcat or skid-steer

    Noise due to equipment

    SBB (site electrical)

    Installing conduit

    N/A

    N/A

    Genomics

    Form and reinforce SOG

    N/A

    N/A

     

    Week of February 27, 2023

    Construction Activities 

     

    Location

    Activity

    Equipment Used

    Anticipated Disturbance

    SBB (Lot 8)

    Locate and Cap Existing Utilities

    N/A

    N/A

    SBB (Lot 8)

    Site Utilities

    Backhoe, excavator, trucks

    Noise due to equipment

    SBB (site electrical)

    Pulling Medium Voltage cable

    N/A

    N/A

    SBB (site electrical)

    Setting new power pole

    N/A

    N/A

    SBB Earthwork

    Clear & Grub for Soil Nail Wall

    Loader and Excavator

    Noise due to equipment

    Genomics

    Concrete Pour

    Concrete Pump

    Noise due to equipment

     

    Week of March 6, 2023

    Construction Activities

     

    Location

    Activity

    Equipment Used

    Anticipated Disturbance

    SBB (Lot 8)

    Locate and Cap Existing Utilities

    N/A

    N/A

    SBB (Lot 8)

    Site Utilities

    Backhoe, excavator, trucks

    Noise due to equipment

    Genomics

    Install Metal Building (PEMB)

    N/A

    N/A

    SBB (site electrical)

    Pulling Medium Voltage cable

    N/A

    N/A

    SBB Earthwork

    Clear & Grub for Soil Nail Wall

    Loader and Excavator

    Noise due to equipment

     

    Current and Upcoming Anticipated Closures

    The following shutdown(s)/ closures are anticipated as indicated below. Updates to this schedule will be released weekly in the Project Construction Advisories until the work is complete.  Please contact John Franklin with any specific questions or concerns at john.franklin@ucr.edu.

     

    Description

    Location

    Duration & Date

    Impacted Buildings/ Facilities

    Lot 8

    Lot 8

    Permanently

    Lot 8

    Lot 43

    Lot 43

    Indefinitely

    Lot 43

  • 950592 - UCR SBB - Construction Alert #14- Week 02/13/2023

    Current Weeks

    Construction Activities

    Location

    Activity

    Equipment Used

    Anticipated Disturbance

    SBB (Lot 8)

    Locate and Cap Existing Utilities

    N/A

    N/A

    SBB (Lot 8)

    Domestic Water Shutdown Feb. 15th

    N/A

    Shutdown water to the greenhouses 

    SBB (Lot 8)

    Campus Drive Lane Closure

    N/A

    Single Lane Traffic

    SBB (Lot 8)

    Site Utilities

    Backhoe, excavator, trucks

    Noise due to equipment

    SBB (Lot 8)

    Electrical Trenching

    N/A

    Noise due to equipment (College Place)

    Genomics

    Under-slab plumbing and electrical

    N/A

    N/A

    SBB (Lot 8)

    College Place Closure

    N/A

    College Place Closure

    Genomics

    Anchor Bolt Installation

    N/A

    N/A

    Genomics

    Concrete Pour

    Concrete Pump

    Noise due to equipment

    Genomics

    Back fill

    Bobcat or skid-steer

    Noise due to equipment

    SBB (site electrical)

    Installing conduit

    N/A

    N/A

    Genomics

    Form and reinforce SOG

    N/A

    N/A

     

    Week of February 20, 2023

    Construction Activities 

    Location

    Activity

    Equipment Used

    Anticipated Disturbance

    SBB (Lot 8)

    Locate and Cap Existing Utilities

    N/A

    N/A

    SBB (Lot 8)

    Site Utilities

    Backhoe, excavator, trucks

    Noise due to equipment

    Genomics

    Install Metal Building (PEMB)

    N/A

    N/A

    SBB (site electrical)

    Pulling Medium Voltage cable

    N/A

    N/A

    SBB (site electrical)

    Setting new power pole

    N/A

    N/A

    Genomics

    Back fill

    Bobcat or skid-steer

    Noise due to equipment

     

    Week of February 27, 2023

    Construction Activities

     

    Location

    Activity

    Equipment Used

    Anticipated Disturbance

    SBB (Lot 8)

    Locate and Cap Existing Utilities

    N/A

    N/A

    SBB (Lot 8)

    Site Utilities

    Backhoe, excavator, trucks

    Noise due to equipment

    Genomics

    Install Metal Building (PEMB)

    N/A

    N/A

    SBB (site electrical)

    Pulling Medium Voltage cable

    N/A

    N/A

    SBB (site electrical)

    Setting new power pole

    N/A

    N/A

    SBB Earthwork

    Clear & Grub for Soil Nail Wall

    Loader and Excavator

    Noise due to equipment

     

    Current and Upcoming Anticipated Closures

    The following shutdown(s)/ closures are anticipated as indicated below. Updates to this schedule will be released weekly in the Project Construction Advisories until the work is complete.  Please contact John Franklin with any specific questions or concerns at john.franklin@ucr.edu.

     

    Description

    Location

    Duration & Date

    Impacted Buildings/ Facilities

    Lot 8

    Lot 8

    Permanently

    Lot 8

    Lot 43

    Lot 43

    Indefinitely

    Lot 43

  • 950592 - UCR SBB - Construction Alert #13- Week 02/06/2023

    Current Weeks

    Construction Activities

    Location

    Activity

    Equipment Used

    Anticipated Disturbance

    SBB (Lot 8)

    Locate and Cap Existing Utilities

    N/A

    N/A

    SBB (Lot 8)

    Campus Drive Lane Closure

    N/A

    Single Lane Traffic

    SBB (Lot 8)

    Site Utilities

    Back hoe, excavator, trucks

    Noise due to equipment

    SBB (Lot 8)

    Electrical Trenching

    N/A

    Noise due to equipment (College Place)

    SBB (Lot 8)

    College Place Closure

    N/A

    College Place Closure

    SBB (Lot 8)

    Gas Shutdown Feb. 10th

    N/A

    Shutdown gas to the greenhouses 

    Genomics

    Waterproofing

    N/A

    N/A

    Existing Sheds

    Demo Existing Sheds

    Excavator

    Noise due to equipment

     

    Week of February 13, 2023

    Construction Activities 

    Location

    Activity

    Equipment Used

    Anticipated Disturbance

    SBB (Lot 8)

    Locate and Cap Existing Utilities

    N/A

    N/A

    SBB (Lot 8)

    Domestic Water Shutdown Feb. 15th

    N/A

    Shutdown water to the greenhouses 

    SBB (Lot 8)

    Campus Drive Lane Closure

    N/A

    Single Lane Traffic

    SBB (Lot 8)

    Site Utilities

    Back hoe, excavator, trucks

    Noise due to equipment

    SBB (Lot 8)

    Electrical Trenching

    N/A

    Noise due to equipment (College Place)

    Genomics

    Underslab plumbing and electrical

    N/A

    N/A

    SBB (Lot 8)

    College Place Closure

    N/A

    College Place Closure

    Genomics

    Anchor Bolt Installation

    N/A

    N/A

    Genomics

    Concrete Pour

    Concrete Pump

    Noise due to equipment

    Genomics

    Back fill

    Bobcat or skid-steer

    Noise due to equipment

    SBB (site electrical)

    Installing conduit

    N/A

    N/A

    Genomics

    Form and reinforce SOG

    N/A

    N/A

     

    Week of February 20, 2023

    Construction Activities

     

    Location

    Activity

    Equipment Used

    Anticipated Disturbance

    SBB (Lot 8)

    Locate and Cap Existing Utilities

    N/A

    N/A

    SBB (Lot 8)

    Site Utilities

    Back hoe, excavator, trucks

    Noise due to equipment

    Genomics

    Install Metal Building

    N/A

    N/A

    SBB (site electrical)

    Pulling Medium Voltage cable

    N/A

    N/A

    SBB (site electrical)

    Setting new power pole

    N/A

    N/A

    Genomics

    Back fill

    Bobcat or skid-steer

    Noise due to equipment

     

    Current and Upcoming Anticipated Closures

    The following shutdown(s)/ closures are anticipated as indicated below. Updates to this schedule will be released weekly in the Project Construction Advisories until the work is complete.  Please contact John Franklin with any specific questions or concerns at john.franklin@ucr.edu.

     

    Description

    Location

    Duration & Date

    Impacted Buildings/ Facilities

    Lot 8

    Lot 8

    Permanently

    Lot 8

    Lot 43

    Lot 43

    Indefinitely

    Lot 43

  • 950592 - UCR SBB - Construction Alert #12- Week 01/30/2023

    Current Weeks

    Construction Activities

    Location

    Activity

    Equipment Used

    Anticipated Disturbance

    Genomics

    Underground Electrical

    N/A

    N/A

    Genomics

    CMU Stem wall

    N/A

    N/A

    SBB (Lot 8)

    Locate and Cap Existing Utilities

    N/A

    N/A

    SBB (Lot 8)

    Campus Drive Lane Closure

    N/A

    Single Lane Traffic

    SBB (Lot 8)

    Site Utilities

    Back hoe, excavator, trucks

    Noise due to equipment

    SBB (Lot 8)

    Electrical Trenching

    N/A

    Noise due to equipment (College Place)

    SBB (Lot 8)

    College Place Closure

    N/A

    College Place Closure

    Existing Sheds

    Demo Existing Sheds

    Excavator

    Noise due to equipment

     

    Week of February 06, 2023

    Construction Activities 

    Location

    Activity

    Equipment Used

    Anticipated Disturbance

    SBB (Lot 8)

    Locate and Cap Existing Utilities

    N/A

    N/A

    SBB (Lot 8)

    Campus Drive Lane Closure

    N/A

    Single Lane Traffic

    SBB (Lot 8)

    Site Utilities

    Back hoe, excavator, trucks

    Noise due to equipment

    SBB (Lot 8)

    Electrical Trenching

    N/A

    Noise due to equipment (College Place)

    SBB (Lot 8)

    College Place Closure

    N/A

    College Place Closure

    SBB (Lot 8)

    Gas Shutdown Feb. 10th

    N/A

    Shutdown gas to the greenhouses 

    Existing Sheds

    Demo Existing Sheds

    Excavator

    Noise due to equipment

     

     

     

     

     

    Week of February 13, 2023

    Construction Activities

     

    Location

    Activity

    Equipment Used

    Anticipated Disturbance

    SBB (Lot 8)

    Locate and Cap Existing Utilities

    N/A

    N/A

    SBB (Lot 8)

    Domestic Water Shutdown Feb. 15th

    N/A

    Shutdown water to the greenhouses 

    SBB (Lot 8)

    Campus Drive Lane Closure

    N/A

    Single Lane Traffic

    SBB (Lot 8)

    Site Utilities

    Back hoe, excavator, trucks

    Noise due to equipment

    SBB (Lot 8)

    Electrical Trenching

    N/A

    Noise due to equipment (College Place)

    SBB (Lot 8)

    College Place Closure

    N/A

    College Place Closure

    Genomics

    Anchor Bolt Installation

    N/A

    N/A

    Genomics

    Concrete Pour

    Concrete Pump

    Noise due to equipment

    Genomics

    Back fill

    Bobcat or skid-steer

    Noise due to equipment

    Genomics

    Form and reinforce SOG

    N/A

    N/A

     

    Current and Upcoming Anticipated Closures

    The following shutdown(s)/ closures are anticipated as indicated below. Updates to this schedule will be released weekly in the Project Construction Advisories until the work is complete.  Please contact John Franklin with any specific questions or concerns at john.franklin@ucr.edu.

     

    Description

    Location

    Duration & Date

    Impacted Buildings/ Facilities

    Lot 8

    Lot 8

    Permanently

    Lot 8

    Lot 43

    Lot 43

    Indefinitely

    Lot 43

    Campus Drive

    Single Lane Closure

    Until 02/09/23

    Buildings along Campus Drive

  • 950592 - UCR SBB - Construction Alert #11- Week 01/23/2023

    Current Weeks

    Construction Activities

    Location

    Activity

    Equipment Used

    Anticipated Disturbance

    Genomics

    Underground Electrical

    N/A

    N/A

    Genomics

    Form and pour foundations

    pump

    Noise due to equipment

    SBB (Lot 8)

    Locate and Cap Existing Utilities

    N/A

    N/A

    SBB (Lot 8)

    Campus Drive Lane Closure

    N/A

    Single Lane Traffic

    SBB (Lot 8)

    Site Utilities

    Back hoe, excavator, trucks

    Noise due to equipment

    SBB (Lot 8)

    Electrical Trenching

    N/A

    Noise due to equipment (College Place)

    SBB (Lot 8)

    College Place Closure

    N/A

    College Place Closure

     

    Week of January 30, 2023

    Construction Activities 

    Location

    Activity

    Equipment Used

    Anticipated Disturbance

    Genomics

    Underground Electrical

    N/A

    N/A

    Genomics

    CMU Stem wall

    N/A

    N/A

    SBB (Lot 8)

    Locate and Cap Existing Utilities

    N/A

    N/A

    SBB (Lot 8)

    Campus Drive Lane Closure

    N/A

    Single Lane Traffic

    SBB (Lot 8)

    Site Utilities

    Back hoe, excavator, trucks

    Noise due to equipment

    SBB (Lot 8)

    Electrical Trenching

    N/A

    Noise due to equipment (College Place)

     

     

     

     

    SBB (Lot 8)

    College Place Closure

    N/A

    College Place Closure

     

     

    Week of February 6, 2023

    Construction Activities

     

    Location

    Activity

    Equipment Used

    Anticipated Disturbance

    SBB (Lot 8)

    Locate and Cap Existing Utilities

    N/A

    N/A

    SBB (Lot 8)

    Campus Drive Lane Closure

    N/A

    Single Lane Traffic

    SBB (Lot 8)

    Site Utilities

    Back hoe, excavator, trucks

    Noise due to equipment

    SBB (Lot 8)

    Electrical Trenching

    N/A

    Noise due to equipment (College Place)

    SBB (Lot 8)

    College Place Closure

    N/A

    College Place Closure

     

    Current and Upcoming Anticipated Closures

    The following shutdown(s)/ closures are anticipated as indicated below. Updates to this schedule will be released weekly in the Project Construction Advisories until the work is complete.  Please contact John Franklin with any specific questions or concerns at john.franklin@ucr.edu.

     

    Description

    Location

    Duration & Date

    Impacted Buildings/ Facilities

    Lot 8

    Lot 8

    Permanently

    Lot 8

    Lot 43

    Lot 43

    Indefinitely

    Lot 43

  • 950592 - UCR SBB - Construction Alert #10- Week 01/16/2023

    Current Weeks

    Construction Activities

     

    Location

    Activity

    Equipment Used

    Anticipated Disturbance

    Genomics

    Footing excavation

    Back Hoe, mini-ex, dump truck

    Noise due to equipment

    Genomics

    Rebar Install

    N/A

    N/A

    Genomics

    Underground Electrical

    N/A

    N/A

     

    Week of January 23, 2023

    Construction Activities

     

    Location

    Activity

    Equipment Used

    Anticipated Disturbance

    Genomics

    Underground Electrical

    N/A

    N/A

    Genomics

    Form and pour foundations

    pump

    Noise due to equipment

    SBB (Lot 8)

    Locate and Cap Existing Utilities

    N/A

    N/A

    SBB (Lot 8)

    Campus Drive Lane Closure

    N/A

    Single Lane Traffic

    SBB (Lot 8)

    Site Utilities

    Back hoe, excavator, trucks

    Noise due to equipment

    SBB (Lot 8)

    Electrical Trenching

    N/A

    Noise due to equipment (College Place)

     

     

     

     

    SBB (Lot 8)

    College Place Closure

    N/A

    College Place Closure

     

    Week of January 30, 2023

    Construction Activities

     

    Location

    Activity

    Equipment Used

    Anticipated Disturbance

    SBB (Lot 8)

    Locate and Cap Existing Utilities

    N/A

    N/A

    SBB (Lot 8)

    Campus Drive Lane Closure

    N/A

    Single Lane Traffic

    SBB (Lot 8)

    Site Utilities

    Back hoe, excavator, trucks

    Noise due to equipment

    SBB (Lot 8)

    Electrical Trenching

    N/A

    Noise due to equipment (College Place)

    SBB (Lot 8)

    College Place Closure

    N/A

    College Place Closure

     

    Current and Upcoming Anticipated Closures

    The following shutdown(s)/ closures are anticipated as indicated below. Updates to this schedule will be released weekly in the Project Construction Advisories until the work is complete.  Please contact John Franklin with any specific questions or concerns at john.franklin@ucr.edu.

     

    Description

    Location

    Duration & Date

    Impacted Buildings/ Facilities

    Lot 8

    Lot 8

    Indefinitely

    Lot 8

    Lot 43

    Lot 43

    Indefinitely

    Lot 43

     

  • 950592 - UCR SBB - Construction Alert #9

    Week of January 9, 2023

    Construction Activities

     

    Location

    Activity

    Equipment Used

    Anticipated Disturbance

    Lot 43

    Trailer Interior/Exterior Build-out

    Small hand tools

    Noise due to hand tools

    Bio-Control

    Relocate Existing Lines (Water, Telecom, and electrical)

    N/A

    N/A

    Genomics

    Excavate and Weather Protect Footings

    Back Hoe, mini-ex, dump truck

    Noise due to equipment

     

    Week of January 16, 2023

    Construction Activities

     

    Location

    Activity

    Equipment Used

    Anticipated Disturbance

    Genomics

    Footing excavation

    Back Hoe, mini-ex, dump truck

    Noise due to equipment

    Genomics

    Rebar Install

    N/A

    N/A

    Genomics

    Form and pour foundations

    pump

    Noise due to equipment

    Genomics

    Underground Electrical

    N/A

    N/A

     

    Week of January 23, 2023

    Construction Activities

     

    Location

    Activity

    Equipment Used

    Anticipated Disturbance

    SBB (Lot 8)

    Locate and Cap Existing Utilities

    N/A

    N/A

    SBB (Lot 8)

    Campus Drive Lane Closure

    N/A

    Single Lane Traffic

    SBB (Lot 8)

    Site Utilities

    Back hoe, excavator, trucks

    Noise due to equipment

    SBB (Lot 8)

    Electrical Trenching

    N/A

    Noise due to equipment (College Place)

    SBB (Lot 8)

    College Place Closure

    N/A

    College Place Closure

     

    Current and Upcoming Anticipated Closures

    The following shutdown(s)/ closures are anticipated as indicated below. Updates to this schedule will be released weekly in the Project Construction Advisories until the work is complete.  Please contact John Franklin with any specific questions or concerns at john.franklin@ucr.edu.

     

    Description

    Location

    Duration & Date

    Impacted Buildings/ Facilities

    Lot 8

    Lot 8

    Indefinitely

    Lot 8

    Lot 43

    Lot 43

    Indefinitely

    Lot 43

Project Timeline: 

Anticipated  Start:
Fall, 2022


Anticipated Completion:
Summer, 2024

 

PD&C Contact: 

Project Manager: John Franklin
tel: (951) 203-7920, (951) 827-2421
 

Project Planner: Melissa Garrety
tel: (951) 827-7376

 

Project Working Group: 

Danko Turcic

Jean Helwege

Jennifer Osborne

Kathy Drake

Kennett Lai

Patrick Latimer

Rami Zwick

Sabine Freij

 

Project Basis of Design: 

Steinberg Hart

 

Architect: 

Moore Ruble Yudell Architects

 

GC: 

McCarthy Construction

 

Signup for construction updates on this project

CLICK HERE

Live Cameras

Live Camera 1

 

Live Camera 1

Live Camera 2

 

Live Camera 2