Breadcrumb

UTLF 

The Undergraduate Teaching and Learning Facility (UTLF) project will construct an approximately 120,000 gross-square-foot building to provide UC Riverside with critically needed classroom, class laboratory, and studio space to allow campus to serve current and future undergraduate students.


Project Scope:

UTLF will provide approximately 100,700 gross square feet (GSF) of new academic space. The space program is focused on undergraduate education and incorporates the following types of spaces, which strategically address some of the campus' most pressing instruction and instructional support space needs:

  • General assignment classrooms
  • Specialized teaching spaces such as labs and studios supporting the arts, engineering, and physical and natural sciences
  • Instructional support spaces

 

UTLF Project Updates

  • 950587 UTLF Construction Alert #44

    Current week

    Construction Activities

    Location

    Activity

    Heavy Equipment Used

    Anticipated Disturbance

    Building Site

    Storm Drain at Athletics Court Yard

    Excavator

    Medium-level Construction noise

    Building Site

    Deck Shoring

    Crane, Telehandler, Scissor lift

    Medium-level Construction noise

    Building Site

    Deck Rebar

    Crane, Hand Tools

    Medium-level Construction noise

    Building Site

    Strip & Clean

    Hand Tools

    Low-level Construction noise

    Building Site

    1st pass Framing

    Hand Tools, Table Saw

    Medium-level Construction noise

    Building Site

    Saturday Work

    Hand Tools

    Low-level Construction noise

    Building Site

    Install Air and Water Barrier

    Hand Tools

    Low-level Construction noise

    Building Site

    Flashing

    Hand Tools, Table Saw

    Medium-level Construction noise

    Building Site

    Install Brick Ties/Base Course/Brick

    Hand Tools, Table Saw

    Medium-level Construction noise

    Building Site

    Pour Level 5 Deck West

    Concrete Trucks, Concrete Pump

    Medium-level Construction noise

    Building Site

    Excavate Bridge Footings at Athletics Courtyard

    Mini-Excavator

    Medium-level Construction noise

     

    Week of April 21, 2025

    Construction Activities 

    Location

    Activity

    Heavy Equipment Used

    Anticipated Disturbance

    Building Site

    Storm Drain at Athletics Court Yard

    Excavator

    Medium-level Construction noise

    Building Site

    Strip & Clean

    Hand Tools

    Low-level Construction noise

    Building Site

    1st pass Framing

    Hand Tools, Table Saw

    Medium-level Construction noise

    Building Site

    Install Air and Water Barrier

    Hand Tools

    Low-level Construction noise

    Building Site

    Form and Pour Pads

    Concrete Trucks

    Medium-level Construction noise

    Building Site

    Flashing

    Hand Tools, Table Saw

    Medium-level Construction noise

    Building Site

    Install Brick Ties/Base Course/Brick

    Hand Tools, Table Saw

    Medium-level Construction noise

    Building Site

    Saturday Work

    Hand Tools

    Low-level Construction noise

    Building Site

    Erect Structural Steel at Dance Studio

    Crane

    Medium-level Construction noise

    Week of April 28, 2025

    Construction Activities 

    Location

    Activity

    Heavy Equipment Used

    Anticipated Disturbance

    Building Site

    Strip & Clean

    Hand Tools

    Low-level Construction noise

    Building Site

    1st pass Framing

    Hand Tools, Table Saw

    Medium-level Construction noise

    Building Site

    Flashing

    Hand Tools, Table Saw

    Medium-level Construction noise

    Building Site

    Install Brick

    Hand Tools, Table Saw

    Medium-level Construction noise

    Building Site

    Saturday Work

    Hand Tools

    Low-level Construction noise

    Building Site

    Form Concrete Stairs

    Hand Tools, Table Saw

    Medium-level Construction noise

    Building Site

    Start In-Wall Installation

    Hand Tools

    Low-level Construction noise

     

    Current and Upcoming Anticipated Closures

    The following shutdown(s)/ closures are anticipated as indicated below. Updates to this schedule will be released weekly in the Project Construction Advisories until the work is complete. 

     

    Description

    Location

    Duration & Date

    Impacted Buildings/ Facilities

     

     

     

     

     

     

     

     

    **No upcoming or anticipated closures. The constructions operations will occur periodically in the street and in and around the sidewalks adjacent to the construction jobsite. Please note that although there are not anticipated closures, there will be detour signs and traffic control between to safely route students and faculty around the operations, 04/14/25 and 04/21/25.
     
    Please contact -Sarah Sabera-Turab with any specific questions or concerns at:  sarah.sabera-turab@ucr.edu
     
     


     

Project Timeline: 

Anticipated Start:
July 2024


Anticipated Completion:
Fall 2026


PD&C Contact:

Project Manager: Sarah Sabera-Turab
tel: (951) 827-5825

Project Planner: Melissa Garrety
tel: (951) 827-7376

Project Working Group:

Ken Baerenklau, Associate Provost, Chair

Bracken Daley, Registrar

Connie Nugent, CNAS Divisional Dean of Student Academic Affairs

Covadonga Lamar Prieto, CHASS Associate Dean of Student Affairs

Huinan Liu, BCOE Associate Dean for Student Academic Affairs

Linda Walling, Chair of the Physical Resources Committee

Architect:

Steinberg Hart

GC:

McCarthy Building Co

 

 

Live Camera