Batchelor Hall Renovation

Batchelor Hall Renovation

Batchelor Hall Project

Renovation 110,091 square feet facility built in 1960 due to building systems anticipated end of life, and desire to support research. Project proposes:

  • Replace heating, ventilation, and air condition system due to inefficiency, and compromised air quality
  • Upgrade electrical service to 480/277 in order to allow higher intensity research equipment
  • Upgrade/replace plumbing systems due to condition, and inadequate water treatment
  • Upgrade fire life safety system (fire alarm) due to none code compliance
  • Reconfigure laboratory space to improve research space usage and efficiency, work will be phased to limit user impact, and funding availability

Classification of Work:

  • Heating and cooling systems
  • Ventilation systems
  • Energy management systems
  • Primary and emergency electrical systems
  • Fire alarm and protection systems
  • De-ionized water and reverse osmosis systems
  • Hazardous materials abatement
  • Reconfiguration of research and laboratory and related spaces

Batchelor Hall Renovation Menu

Current Activity

  • Complete building investigation and lab walkthrough
  • Complete construction (and relocation) phasing and logistics plan
  • Complete project construction and relocation schedule
  • Complete project construction drawings

Next Steps

  • Project bidding (Sub Contractor Bidding)
  • Construction phase funding approval

Construction Notices

  • ¬†Project Team & Constructor will be scheduling lab walkthroughs with individual PI. ¬†Walkthroughs will allow the Project Team to determine potential impact to individual spaces, this information will be utilized in developing a Phasing/Logistics Plan and User Impact Mitigation measures