- The MRB1 construction fence will enclose the open area directly north of the Materials Science & Engineering 1 Building and will extend to encompass much of Parking Lot 25, immediately east of the Student Recreation Center.
- All normal access to MS&E will be maintained.
- Pedestrian access from Parking Lot 24 to Parking Lot 25, via the sidewalk in between the track and the soccer fields, will be closed as of August 19, 2016.
- Pedestrian access to the Athletics track, soccer & softball fields will be maintained.
- Construction traffic will access the MRB1 construction site from the north, via Parking Lot 25. 2-hour parking at Parking Lot 25 will be taken off-line as of September 12 to allow all MRB1 construction traffic to access the site via this parking lot.
- Accessible parking spaces will be maintained at the northern end of Parking Lot 25.
- Pedestrian access to the Student Recreation Center will be maintained from Linden and Aberdeen.