  1. The MRB1 construction fence will enclose the open area directly north of the Materials Science & Engineering 1 Building and will extend to encompass much of Parking Lot 25, immediately east of the Student Recreation Center.
  2. All normal access to MS&E will be maintained.
  3. Pedestrian access from Parking Lot 24 to Parking Lot 25, via the sidewalk in between the track and the soccer fields, will be closed as of August 19, 2016.
  4. Pedestrian access to the Athletics track, soccer & softball fields will be maintained.
  5. Construction traffic will access the MRB1 construction site from the north, via Parking Lot 25. 2-hour parking at Parking Lot 25 will be taken off-line as of September 12 to allow all MRB1 construction traffic to access the site via this parking lot.
  6. Accessible parking spaces will be maintained at the northern end of Parking Lot 25.
  7. Pedestrian access to the Student Recreation Center will be maintained from Linden and Aberdeen.